  1. Slide 1: Portfolio Valuation of PPL Hydro Asset Acquisition

    Portfolio Valuation of PPL Hydro Asset Acquisition Gary Dorris, Ph.D. Sean Burrows, Ph.D. Mark Dyson Understanding the Latent Value of Hydro Generation Alex Lauderbaugh Brock Mosovsky, Ph.D. November 13, 2013 [email protected] 303.415.0311 www.ascendanalytics.com

  2. Slide 2: Outline

    Outline • Portfolio Characteristics and Valuation Results • Quantifying the Value of Risk • Market Inputs • Simulation Validation • Operating Dynamics and Detailed Results Preliminary Data 2

  3. Slide 3: Preliminary Results of Hydro Acquisition Analysis

    Preliminary Results of Hydro Acquisition Analysis Preliminary Data 3

  4. Slide 4: Best Practices in Resource Analysis

    Best Practices in Resource Analysis • Portfolio perspective  Fuel diversity  Reliability and intermittent resources  Uncertainty in fuel, emissions, and power • Use of market for fuel and power • Analyze generation resource options with respect to market dynamics • Capture new dynamics  Weather

  5. Slide 5: Key Points of Analysis

    Key Points of Analysis • Supply Cost and Risk = costs and uncertainty in energy supply costs (fixed and variable) • Risk Premium = monetized value of risk—uncertainty in supply costs • Net Position Exposure = balance of NWE resources relative to load obligations • Supply portfolios to be assessed: o

  6. Slide 6: Tools of Supply Planning Model Attributes

    Tools of Supply Planning Model Attributes Uncertainty Factor Production Cost Models Integrated Risk Based Planning Models Load Growth Fixed Simulated Uncertainty Load Patterns “Typical” profile Uncertainty in Profile and Usage Pattern Conservation Fixed Weather Based Demand Response Weather Fixed We

  7. Slide 7: Net Position Report

    Net Position Report 2000 NWE net position 0 -2000 GWh/yr -4000 -6000 -8000 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 Base-mean Base-p5 Base-p95 Base plus hydro-mean Base plus hydro-p5 Base plus hydro-p9

  8. Slide 8: PPL Hydro Assets

    PPL Hydro Assets Capacity Storage Generator MW Net Factor (%) (A/F) Thompson 94 60 14,970 Falls Mystic Lake 12 50 Kerr* 194 64 200,000 Madison 8 85 27,200 Hebgen - - 386,000 Hauser Lake 19 81 64,253 Holter 48 75 82,000 Black Eagle 21 73 1,820 Rainbow 60 60 1,050 Cochrane 69 50 2,700 Ryan 60 80 5,000

  9. Slide 9: Quantifying the Value of Risk

    Quantifying the Value of Risk Preliminary Data 9

  10. Slide 10: Deterministic vs. Stochastic Models

    Deterministic vs. Stochastic Models • Heavy dependence on deterministic results with scenarios  Excessive focus over input forecasts  The likelihood of result is not understood  Model inputs are variable and interdependent • What’s the impact of unused information?  Inaccurate forecasting  Asse

  11. Slide 11: Definition of Common Planning Risk Metrics

    Definition of Common Planning Risk Metrics Cost at Risk (CaR) for Rev Req = CaR = 95th percent costs – mean costs How do you decide the value of risk? Avista IRP 2011 • Risk metrics are useful but need to be translated into a monetary value by quantifying the value of uncertainty Preliminary Data 11

  12. Slide 12: Risk Premium (RP)

    Risk Premium (RP) How to calculate the RP in discrete time? • Calculate the area under the cost distribution curve. f (x ) • The orange dotted section has been overlaid with rectangles to reflect this discretized area. • RP calculation is the same calculation used to value options or assess actuaria

  13. Slide 13: Simulation Validation

    Simulation Validation Preliminary Data 13

  14. Slide 14: Integrating Physical and Financial Uncertainty

    Integrating Physical and Financial Uncertainty Dispatch Detail • Hourly chronological dispatch • Forced Outages modeled as random events • Seasonal and peak period generating characteristics Optimal Resource Selection Unified simulation framework reflecting joint financial and physical uncertainty o

  15. Slide 15: Confidence Intervals and Simulation Spread

    Confidence Intervals and Simulation Spread Forward Price Simulations Mid-C Heavy price simulations spread from the mean • Simulated forward prices are plotted over time for the mean, 5th, and 95th percentiles • Expect that uncertainty will grow with time F0=E(Ft)=E(FT)=E(St) Confidence Intervals for

  16. Slide 16: Forward Price Validation History and Simulations: Natural Gas

    Forward Price Validation History and Simulations: Natural Gas Forward Price Validation Historic prompt month prices for Henry Hub Price Paths for Final Evolved Forward Curve Simulation • Large price spikes followed by mean reversion • 2 to five year cycle AECO Natural Gas • Large volatility in price

  17. Slide 17: Volatilities

    Volatilities Volatility in Forward Contracts by Delivery Date • Calculated from recent forward market transactions • Controls the amount of uncertainty in simulated forward prices • Decreases exponentially through time • Displays seasonal trends • Distinct patterns observed by commodity Preliminary

  18. Slide 18: Fuel Price Simulations

    Fuel Price Simulations • Simulated forward prices are plotted over time for the mean, 5th, and 95th percentiles PRB Coal • Seasonal changes in price and uncertainty AECO Gas • Uncertainty grows with time • Average price increases to account for inflation Preliminary Data 18

  19. Slide 19: Scenario Analysis

    Scenario Analysis Common Scenarios: High, Med, Low • Which forecast are the best? Gas Price Scenario Analysis • Scenarios with prices monotonically increasing 14.00 over time. 12.00 • Are these prices consistent 10.00 with observed patterns? Scenario 1=$4 • What’s the probability $/MBtu 8.00 Scenari

  20. Slide 20: Gas Price Simulation

    Gas Price Simulation 2013 Resource Procurement Plan 9.5 Natural Gas Price Comparisons (all forecasts include transportation costs to & through MT) 8.5 7.5 6.5 $/MMBtu 5.5 4.5 3.5 2011 RPP Base Case : Levelized $6.43 2013 EIA AEO : Levelized $5.21 2013 NPCC Medium Case : Levelized $5.32 2013 RPP Asce

  21. Slide 21: Forward Price Validation

    Forward Price Validation Risk Bands for Implied On-Peak Heat Rates Maintaining Correlations • Simulations maintain implied heat rate distributions • Correctly value generation assets • Preserve proper value of portfolio risks • Enables proper value of cross hedges 120 12 100 10 80 8 60 6 Simulated f

  22. Slide 22: Carbon Penalty Effect

    Carbon Penalty Effect Forecasting Carbon Costs • In 2021, a carbon penalty is priced in to both generation and forward curves. Carbon Market Price Projections $100 Avista (2013 IRP) $90 PacifiCorp (2013 $80 IRP) PGE (2012 IRP) Dollars per Ton ($/ton) $70 PSE (2013 IRP) $60 NWE (Carbon $50 Forecast)

  23. Slide 23: Weather, Hydro Flows, Load, Price Simulations

    Weather  Hydro Flows  Load  Price Simulations Hydro Flows Intermittent Generation Gas Electric Weather Load Price Preliminary Data 23

  24. Slide 24: Weather-Load-Price Paradigm

    Weather-Load-Price Paradigm Weather Load Price • Weather is a • Load is driven • Electricity price stochastic primarily by is input–so an weather—high predominantly appropriate and low driven by load, range of future temperatures though other states must be increase the factors simulated based deman

  25. Slide 25: Weather Overview

    Weather Overview • Weather data taken from the National Climatic Data Center  Publicly available at http://ncdc.noaa.gov  10+ years of historical data  More than 30 weather stations across Montana Preliminary Data 25

  26. Slide 26: Weather Load Relationship

    Weather Load Relationship Weather-Load Validation Maintaining Correlations Simulated vs. Historical • Incorporating weather into the load model maintains integrity in the weather – load relationship • Simulations nicely smooth out “bumps” of historical weather record • Simulations provide for new ex

  27. Slide 27: Load – Evaluating Difference 5th, Mean, 95th

    Load – Evaluating Difference 5th, Mean, 95th Load Simulation Validation Results • Demonstrate a robust model to simulate future load • Capture uncertainty in load growth with extreme weather scenarios validated prior to a load simulation • Validated monthly load values • Validated hourly load values

  28. Slide 28: Load Validation

    Load Validation Load Confidence Intervals August • Confidence intervals for hourly load by month at the mean, 5th, and 95th percentiles • Alignment of simulations with historical data January Daily Load Shape • Morning and evening peak during cold months • Single afternoon peak during warm months Pr

  29. Slide 29: Spot Price Simulations

    Spot Price Simulations Daily historical market prices for Mid-C Heavy Mid-C February Confidence Intervals compared to NWE load • Low correlation between NWE load and power prices. Hourly P10-Mean-P90 Confidence Intervals for February Mid-C power prices • Historical in red, simulation in blue • Good

  30. Slide 30: Comparisons of Hydro Generation, Load, Prices, & Weather

    Comparisons of Hydro Generation, Load, Prices, & Weather Daily market prices for Mid-C heavy compared to AECO gas • Power shows a positive correlation with gas • Extreme weather days (below 10th percentile of average temp) highlighted in orange AECO Gas confidence Intervals • Historical in red, simu

  31. Slide 31: Comparisons of Hydro Generation, Load, Prices, & Weather

    Comparisons of Hydro Generation, Load, Prices, & Weather Daily historical Mid-C vs. Hydro generation • Meaningful negative correlation between power Simulated Confidence Intervals vs. Historical Hydro Generation prices and hydro generation. 450000 • Extreme weather days (below 10th percentile of 400

  32. Slide 32: Historical River Flows

    Historical River Flows River Discharge • June river discharge for years 1957-2012. • Notice negligible correlation between river systems. River Discharge 700 600 Columbia River (1000 ft3/s) 500 400 300 200 100 0 0 5 10 15 20 25 30 35 Missouri River (1000 ft3/s) Preliminary Data 32

  33. Slide 33: Wind Generation Validation

    Wind Generation Validation • Simulated wind production matches the historical behavior of NWE wind assets • Wind is scaled to meet 15% of load in 2015 onwards 80% 70% Wind Monthly Capacity Factor 60% 50% 40% 30% 20% 10% 0% 1 2 3 4 5 6 7 8 9 10 11 12 Month Historical data Sim P5 Sim Mean Sim P95 Prel

  34. Slide 34: Site A: Hourly Wind and Load

    Site A: Hourly Wind and Load Average of hourly load and wind generation 100% 800 90% 700 80% Wind Capacity Factor 600 70% 60% 500 Load MW 50% 400 40% 300 30% 200 20% 10% 100 0% - 3/31 0:00 3/31 6:00 3/31 12:00 3/31 18:00 Gordon Butte Wind NWE Load • Wind generation declines as system load peaks • Wi

  35. Slide 35: Site B: Hourly Wind and Load

    Site B: Hourly Wind and Load Average of hourly load and wind generation 100% 800 90% 700 80% 600 Wind Capacity Factor 70% 60% 500 Load MW 50% 400 40% 300 30% 200 20% 10% 100 0% - 3/31 0:00 3/31 6:00 3/31 12:00 3/31 18:00 Judith Gap Wind NWE Load • Diversifying wind portfolio can “make the wind blow

  36. Slide 36: Hourly Portfolio Attributes

    Hourly Portfolio Attributes Preliminary Data 36

  37. Slide 37: Net Energy Position

    Net Energy Position Current supply portfolio: 2020 31% 47% 53% 69% Hydro added to portfolio: 2020 Owned Market purchases 13% 87% Preliminary Data 37

  38. Slide 38: Resource Integration: Ancillary Service Implications

    Resource Integration Ancillary Service Implications • Perception that increasing RPS creates value for flexible resources  Negative power prices  Large potential swings in supply greater demand for ancillary services and flexibility 1,000 15% of Load Supplied from Renewables 900 800 700 600 Wind

  39. Slide 39: Generation Stations Report

    Generation Stations Report • Net Position Report  Portfolios o Generation o Load • Stations Report  Capacity factor  Fuel consumed  Generation  Emissions (CO2) Preliminary Data 39

  40. Slide 40: Contact Information

    Contact Information U.S. Offices Headquarters: Gary Dorris | 303.415.0311 1877 Broadway St President Suite 706 [email protected] Boulder, CO 80302 (303) 415-1400 Other Offices: Berkeley, CA Bozeman, MT