Capital Power Corporation · TSX:CPX
Capital Power — Corporate Update (December 2022)
27 slides from Capital Power's corporate update, Dec 13, 2022
Slide 1: York Energy Centre Battery Energy Storage System Project
York Energy Centre Battery Energy Storage System Project Virtual Public Community Meeting December 13, 2022 1
Slide 2: Welcome! Meeting Overview
Welcome! Meeting Overview • Background on Capital Power and Manulife. • The need for new generation and capacity in Ontario. • Overview of Battery Energy Storage System (BESS) technology. • Proposal for a 120-megawatt BESS for the York Energy Centre (YEC). • Question & Answer Session. 2
Slide 3: Land acknowledgement
Land acknowledgement In the spirit of reconciliation, we respectfully acknowledge that we operate within the ancestral homelands, traditional and treaty territories of the Indigenous peoples of Turtle Island, or North America. We also acknowledge that we are on the traditional territories of the Wen
Slide 4: Manulife Financial
Manulife Financial • A large and leading Toronto based financial services company. • Presence in 22 countries and territories. • Approximately $1 Trillion of assets under management. • Partner with Capital Power on YEC and 1,600 MW Midland Cogeneration – the largest cogeneration facility in the US.
Slide 5: Capital Power highlights
Publicly-traded company (TSX: CPX) headquartered Capital Power highlights in Edmonton ~800 employees; regional offices in Boston, Toronto and Calgary Own ~7,400 MW of power generation produced at 28 facilities in Canada and U.S. 5 Facilities and ~1500 MW in Ontario Named one of the World’s Most Ethi
Slide 6: Providing Safe, Reliable Electricity to Ontario
Providing Safe, Reliable Electricity to Ontario Five facilities 1,500 megawatts 40 employees Millions spent annually on contracted support and equipment York Energy Centre Goreway Power Station East Windsor Cogeneration Centre Port Dover and Nanticoke Wind Energy Kingsbridge Wind Energy Project 6
Slide 7: Capital Power invests to create impact
Capital Power invests to create impact Over $5.5M donated in 2022 to power sustainable communities Equity & Culture - Wellbeing - Climate Action Partnering with local organizations: • Carrot Fest (Bradford West Gwillimbury) • Cawthra Mulock Nature Reserve • Holland Marsh Soupfest • Crime Stoppers •
Slide 8: The Growing Demand for Electricity in Ontario
The Growing Demand for Electricity in Ontario 8
Slide 9: Ontario's Independent Electricity System Operator
Ontario’s Independent Electricity System Operator • Independent Electricity System Operator (IESO) is responsible for planning and operating Ontario’s electricity grid. • IESO forecasts changes in demand and supply to ensure that Ontario ratepayers have an affordable, reliable supply of electricity
Slide 10: The Future Need for Power in Ontario
The Future Need for Power in Ontario • Ontario’s electricity supply will be reduced in the near term: • Retirement of the Pickering Nuclear Generating Station. • Other nuclear refurbishment outages. • Expiring contracts. • Demand for electricity is increasing in Ontario due to: • Population growth.
Slide 11: Anticipated Ontario Demand, 2023 to 2041
Anticipated Ontario Demand, 2023 to 2041 11
Slide 12: Local Need
Local Need • Township of King and surrounding area are seeing the need for new capacity. • The IESO forecast suggests local demand will outstrip existing capacity by 2027. 12
Slide 13: The IESO's Current Procurement Process
The IESO’s Current Procurement Process • The IESO is seeking 4,000 MW of new capacity: • 1,500 MW will be procured under the Expedited Long-Term Request for Proposal (RFP) process. Another 2,500 MW will be procured under the Long-Term 1 RFP. • Project bids due February 16, 2023. • Contract with the
Slide 14: Battery Energy Storage Systems
Battery Energy Storage Systems 14
Slide 15: Battery Energy Storage System (BESS) Overview
Battery Energy Storage System (BESS) Overview • BESS facilities help balance the electricity grid. • They are charged when demand is low and feed electricity into the grid when demand is high and/or generation from other resources is low. • The BESS will use lithium-ion batteries, the most common ty
Slide 16: Global Growth of BESS Projects
Global Growth of BESS Projects • BESS facilities are becoming vital to the effort of moving to lower-carbon sources of power. • The U.S. had over 8,200 MW of BESS installed by late 2022. Global installed BESS is expected to reach 80,000 MW by 2030. • Canada is a relative newcomer to BESS projects. G
Slide 17: Proposed BESS at the York Energy Centre
Proposed BESS at the York Energy Centre 17
Slide 18: York Energy Centre Location
York Energy Centre Location • Township of King, York Region • Located on two parcels, municipally known as 18781 and 18765 Dufferin Street. • South of the community of Ansnorveldt and the Holland River.
Slide 19: York Energy Centre
York Energy Centre • YEC generates ~400 MW of power. • Largest quick response facility in Ontario, providing essential backup generation support to the Ontario grid. • YEC began operating in 2012 and provides employment to nine permanent staff.
Slide 20: BESS Site
BESS Site • Proposed north of the YEC on property owned by General location of Capital Power. BESS site • Located in the former YEC construction laydown area. • BESS footprint will be ~1.5 ha (or 4 acres). • A new high-voltage transformer will connect the BESS to the YEC substation for interconnecti
Slide 21: Key Design Elements and Conceptual Layout
Key Design Elements and Conceptual Layout • Proposing a Battery Energy Storage System to provide up to 120 MW of output for up to four-hours. • An enclosure wall would be built to reduce noise. • Sited outside of agricultural areas. • Trees/shrubs will be planted to create visual barriers. • No air
Slide 22: Conceptual Layout
Conceptual Layout BESS Facility Existing Transmission Line Existing operation BESS Transformer Point of Interconnection 22
Slide 23: Regulatory Approvals
Regulatory Approvals • If awarded an IESO contract, various permits and approvals will be needed before the Project can proceed. These are expected to include: • Environmental Assessment Act requirements • Environmental Compliance Approvals • Local & Municipal Approvals, working with: - Township of
Slide 24: Future Studies
Future Studies • Various studies will be needed to inform the project design and support regulatory approvals. These studies will identify features that may need protection, mitigation and/or monitoring and will include: • Stormwater Management • Noise • Natural Environment • Visual Aesthetics • Lan
Slide 25: Project Timeline
Project Timeline • If the Project is successful in the IESO Expedited RFP process: Milestone Anticipated Timing Environmental studies and regulatory approvals 2023 Construction mobilization Early 2024 (pending regulatory approvals) Delivery and installation of battery modules Mid-2024 Technical comm
Slide 26: Questions and Answers
Questions and Answers Capital (5 apital @
Slide 27: Contact us
Contact us [email protected] 1-855-703-5005 capitalpower.com