Chaparral Energy Inc

Chaparral Energy — Royal Bank of Canada Finance Conference 2013

51 slides from Chaparral Energy's conference presentation, Jun 4, 2013

  1. Slide 1: Chaparral Energy Royal Bank of Canada Finance Conference June 2013

    Slide 1: Chaparral Energy Royal Bank of Canada Finance Conference June 2013

    Chaparral Energy Royal Bank of Canada Finance Conference June, 2013

  2. Slide 2: Forward-looking statements

    Slide 2: Forward-looking statements

    This presentation contains "forward-looking statements" within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. These forward-looking statements are subject to certain risks, trends and uncertainties that could

  3. Slide 3: Company Representatives

    Slide 3: Company Representatives

    3 Company Representatives Joe Evans Chief Financial Officer & Executive Vice President Mark Fischer Chief Executive Officer & President Melinda Conner Corporate Finance Manager

  4. Slide 4: Chaparral Overview

    Slide 4: Chaparral Overview

    Chaparral Overview  Founded in 1988, Based in Oklahoma City  Core areas — Mid-Continent (Oklahoma) and Permian Basin (W. Texas)  Stable 1P base with large potential upside – 727 MMBoe, R/P 16 years  Oil focused:  Third largest “oil” producer in Oklahoma  (71% oil; 29% gas) – 2012 SEC Reserves

  5. Slide 5: Operating Areas

    Slide 5: Operating Areas

    Operating Areas As of December 31, 2012 (SEC) Core Area Growth Area Acreage Field Offices Headquarters North Texas Reserves: 3.8 MMBoe, 3% of total Production: 0.4 Mboe/d, 2% of total Permian Basin Reserves: 17.1 MMBoe, 12% of total Production: 3.2 MBoe/d, 13% of total Company Total December 2012 pr

  6. Slide 6: Strong Record of Reserve and Production Growth

    Slide 6: Strong Record of Reserve and Production Growth

    Strong Record of Reserve and Production Growth Year-End SEC Reserves (MMBoe) (1) 2003 – 2012 CAGR = 12% Annual Production (MMBoe) 2003 – 2012 CAGR = 15% Chaparral’s reserve replacement ratio averaged 383% per year since 2003 6 Year Oil Gas 2007 $96.01 $6.80 2008 $44.60 $5.62 2009 $61.18 $3.87 2010 $

  7. Slide 7: 2011 to 2012 SEC Reserves Reconciliation

    Slide 7: 2011 to 2012 SEC Reserves Reconciliation

    2011 to 2012 SEC Reserves Reconciliation 7 Total YTD Proved Volume Reconciliation Volumes in MMBOE Beginning Balance (12/31/2011) 156.3 2012 Production -9.1 Extensions & Discoveries 13.3 Improved Recoveries (EOR) 0.8 Divestitures -3.8 Pricing Revisions -12.0 Other Revisions 0.5 Ending Balance (12/31

  8. Slide 8: Current Production

    Slide 8: Current Production

    Current Production Production by Quarter 8 23,278 23,018 26,098 27,223 24,928 - 5,000 10,000 15,000 20,000 25,000 30,000 Q1,2012 Q2,2012 Q3,2012 Q4,2012 Q1,2013 BO E P D Production in the 1th quarter of 2013 decreased 10% over the previous quarter and increased 6% when compared to the 1th Quarter 20

  9. Slide 9: Financial Position to Execute Strategy

    Slide 9: Financial Position to Execute Strategy

    Net Debt / EBITDA Liquidity ($mm) Financial Position to Execute Strategy $325 $300 $400 $69 $300 $400 $550 2012 2016 2017 2018 2019 2020 2021 2022 Current Maturity Profile ($mm) 5.6x 4.4x 4.9x 3.2x 3.3x 3.9x 3.9x 2.3x 2.0x 2.0x 0.0x 0.0x 0.1x 0.1x 2007 2008 2009 2010 2011 2012 Q1 2013 Total net debt

  10. Slide 10: Capital Budget

    Slide 10: Capital Budget

    Capital Budget ($mm) Component 2010 2011 2012 2013B 2013B Allocation% Drilling $196 $172 $239 $206 50% EOR 36 86 187 $130 32% Enhancements 39 32 20 $20 5% Acquisitions 41 17 48 $25 6% Other (P&E, Capitalized G&A, etc) 32 28 37 $30 7% Total $344 $336 $531 $411 100% Key Drilling Areas Capital Wells No

  11. Slide 11: Drilling Resource Potential

    Slide 11: Drilling Resource Potential

    11 Drilling Resource Potential

  12. Slide 12: Substantial Resource Potential

    Slide 12: Substantial Resource Potential

    Substantial Resource Potential 12  Near-Term  1,697 Unrisked (1,116 Risked) Net Undrilled Wells  146 MMBoe Proved Reserves Plus 581 MMBoe Unproved Resource Potential  Conventional Drilling (ROR 50% - 75%)  Anadarko Granite Wash  Anadarko Cleveland Sand  Unconventional Resource Play Drilling (

  13. Slide 13: Northern Oklahoma Mississippi Play

    Slide 13: Northern Oklahoma Mississippi Play

    Northern Oklahoma Mississippi Play  The Northern Oklahoma Mississippi Play (“NOMP”) is a key near–term focus area for Chaparral  Chaparral acreage over 128,000 net acres in the NOMP  Over 107 MMBoe of potential  800 unrisked drilling well inventory Chaparral Acreage 13 Overview NOMP Asset Map NO

  14. Slide 14: NOMP Play Map

    Slide 14: NOMP Play Map

    NOMP Play Map Billings West [Yetowsone} =| = = Ke DS i tag Jefferson Nash fri" | and saan Cont ais PT =| =< [nese | 7 — Lest noble 71 50 Dey 988 80PO + Legend 3k Chaparral Driling 2013 ht Wells & wig © chaparea Acreage | “ zl = Ci chaparral weit i || outside operated weit iq > Chaparral Current Drit

  15. Slide 15: West Noble Area

    Slide 15: West Noble Area

    15 West Noble Area: ~20,500 Net Acres  Recent NOMP Acquisition – 14,500 Acres

  16. Slide 16: NOMP Economics

    Slide 16: NOMP Economics

    NOMP Economics • EUR : 352 Mboe • Oil and NGL %: 40-50% • Well cost: $3.3 - $4.0 million Oil • EUR: 154 MBbl • IP (30 Day) 155 BOPD • Initial Decline: 73% • b Factor: 1.5 Gas • EUR: 1,190 MMCF • IP (30 Day) 1,044 MCFD • Initial Decline: 73% • b Factor: 1.5 NGLs(a) • EUR: 67 MBBL • IP (30 Day) 59 BOP

  17. Slide 17: NOMP Core BOEPD vs Type Curve

    Slide 17: NOMP Core BOEPD vs Type Curve

    17 NOMP CORE BOEPD – ALL INTEREST MISS-HZ NORMALIZED AVERAGE VS 352 MBOE TYPE CURVE

  18. Slide 18: Marmaton Shelf Play

    Slide 18: Marmaton Shelf Play

    Marmaton Shelf Play 18 Lamaster 2H-23 Peak Rate: 579 Boepd Johnston 1H-24 Peak Rate: 606 Boepd Jay 1H-1098 Peak Rate: 265 Boepd Lamaster 1H-23 Peak Rate: 769 Boepd Marmaton Well Economics IP Rates: 150 – 600 Boe/d EUR: 150 – 200 Mboe Well Cost: $3.5 – $4.0 million % Oil 90% IRR: 25% – 70% Chaparral

  19. Slide 19: Marmaton Shelf Activity

    Slide 19: Marmaton Shelf Activity

    Marmaton Shelf Activity 19 Chaparral Acreage Marmaton Vertical Wells 2013 Horizontal Wells Current Chaparral Rigs

  20. Slide 20: Marmaton Shelf Economics

    Slide 20: Marmaton Shelf Economics

    Marmaton Shelf Economics Type Curve Parameters • EUR : 168 Mboe • Oil and NGL %: 90% • Well cost: $3.5 - $4.0 million Oil • EUR: 157 MBbl • IP (30 Day) 285 BOPD • Initial Decline: 99.7% • b Factor: 1.18 Gas • EUR: 65MMCF • IP (30 Day) 124 MCFD • Initial Decline: 99.7% • b Factor: 1.18 NGLs(a) • EUR:

  21. Slide 21: Marmaton Shelf Results

    Slide 21: Marmaton Shelf Results

    Marmaton Shelf Results AN WSRatvon( EA ul a =e. Sian tt A] eee oe | 10 BOEPD [sn-sstoe —ennornae arenas rnin nas} Chaparral

  22. Slide 22: Chaparral: A Growing Mid-Continent CO2 EOR Company

    Slide 22: Chaparral: A Growing Mid-Continent CO2 EOR Company

    22 Chaparral: A Growing Mid-Continent CO2 EOR Company

  23. Slide 23: Chaparral is a Leader in the CO2-EOR Industry

    Slide 23: Chaparral is a Leader in the CO2-EOR Industry

    # of Active Producer CO2-EOR Projects 31 22 8 7 7 7 6 5 4 4 4 Total 105 Source: April 2012 Oil & Gas Journal Note: Chaparral projects include the North Burbank Unit 23 Chaparral is a Leader in the CO2-EOR Industry Chaparral is the third most active CO2-EOR producer in the U.S.

  24. Slide 24: CO2 EOR Focused Areas

    Slide 24: CO2 EOR Focused Areas

    CO2 EOR Focused Areas 24  CO2 Project Inventory  70 units with 1P, 2P & 3P EOR reserves  9 units with proved reserves  9 units with CO2 injection  CO2 Infrastructure – 473 Miles  318 miles of active line  68 miles under construction  87 miles of inactive line  CO2 Supply  47 MMscf/D of exi

  25. Slide 25: Current CO2 Infrastructure/Future EOR Potential

    Slide 25: Current CO2 Infrastructure/Future EOR Potential

    Coffeyville Fertilizer Plant Koch Fertilizer Plant Arkalon Ethanol Plant Agrium Fertilizer Plant 25 Current CO2 Infrastructure/Future EOR Potential Total OOIP 3,735 MMBo Primary Production 628 MMBo Secondary Recovery 597 MMBo Tertiary Potential 410 MMBo Net Tertiary Potential 197 MMBo Active CO2 fie

  26. Slide 26: EOR 2013 Capital Budget

    Slide 26: EOR 2013 Capital Budget

    EOR 2013 Capital Budget(1) 26 Budget by Category ($mm) 2012 2013B Infrastructure / Pipelines 105 62 Drilling 20 16 Enhancements / CO2 Purchases 62 52 Total $187 $130  Burbank Area  North Burbank Unit $84  Panhandle Area  Farnsworth Unit $21  Booker Area 9  Camrick Area 9  NE Hardesty (Non-op)

  27. Slide 27: Enhanced Oil Recovery Active Projects

    Slide 27: Enhanced Oil Recovery Active Projects

    “Enhanced Oil Recovery” – Active Projects* 27 * NBU included in base beginning October 2013; no EOR expected until Q4’13. Initial NBU Added

  28. Slide 28: Potential EOR Production Growth

    Slide 28: Potential EOR Production Growth

    Chaparral – Potential EOR Production Growth 0 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 2010 2015 2020 2025 2030 2035 2040 Net Oil Production 28 Additional production from non Business Plan projects meeting corporate economic hurdles Additional CO2 Plan w/ +100 mmcfpd in 2015 at Burbank

  29. Slide 29: North Burbank CO2 Development

    Slide 29: North Burbank CO2 Development

    29 North Burbank CO2 Development

  30. Slide 30: North Burbank Unit Overview

    Slide 30: North Burbank Unit Overview

    North Burbank Unit – Overview  Chaparral’s North Burbank Unit is its largest EOR field and CO2 injection into the North Burbank Unit started in June 2013  Chaparral anticipates that it will spend $800 million associated with this EOR project throughout the life of the field 30 Burbank Area: Net Po

  31. Slide 31: Burbank in Perspective

    Slide 31: Burbank in Perspective

    31 Burbank in Perspective Secondary Development Primary Development Ne t B O P D Tertiary Development “Waterflood” +12000 BOPD “CO2 EOR”

  32. Slide 32: North Burbank Unit Achieved Miscibility

    Slide 32: North Burbank Unit Achieved Miscibility

    32 May 2012 Average pressure 1405 psia Ph-I Vicinity North Burbank Unit – Achieved Miscibility Pressure in Phase 1 June 2012 1438 Jul 1461 August 2012 1492 September 2012 1553 October 2012 161 November 162 psia December 1650 February 2013 1704 March 2013 1736 April 3 174

  33. Slide 33: Coffeyville CO2 System

    Slide 33: Coffeyville CO2 System

    Coffeyville CO2 System 33  The Coffeyville CO2 System  $110 million of total capital expenditures  23,500 HP compression facility  68.3-mile 8-inch pipeline with potential capacity of approximately 60 MMcf/d.  CO2 is sourced from the CVR Partners fertilizer plant in Coffeyville, KS.  Commenced

  34. Slide 34: Coffeyville CO2 Plant Phase Complete

    Slide 34: Coffeyville CO2 Plant Phase Complete

    34 COFFEYVILLE CO2 PLANT – PHASE 1 COMPLETE

  35. Slide 35: Coffeyville CO2 Plant

    Slide 35: Coffeyville CO2 Plant

    35 COFFEYVILLE CO2 PLANT

  36. Slide 36: Coffeyville CO2 Plant

    Slide 36: Coffeyville CO2 Plant

    COFFEYVILLE CO, PLANT Chaparral ENERG

  37. Slide 37: Coffeyville CO2 Plant

    Slide 37: Coffeyville CO2 Plant

    COFFEYVILLE CO, PLANT Chaparral 7

  38. Slide 38: Coffeyville CO2 Pipeline: Trenching Right of Way

    Slide 38: Coffeyville CO2 Pipeline: Trenching Right of Way

    38 COFFEYVILLE CO2 PIPELINE: TRENCHING RIGHT OF WAY Digging the trench in preparation for laying the pipeline ~68 miles; Coffeyville, KS to Shidler, OK

  39. Slide 39: Operating Team - Injection into North Burbank

    Slide 39: Operating Team - Injection into North Burbank

    Operating Team - Injection into North Burbank – June 2013 39

  40. Slide 40: Other CO2 Injection Projects

    Slide 40: Other CO2 Injection Projects

    40 Other CO2 Injection Projects

  41. Slide 41: Camrick CO2-EOR Flood

    Slide 41: Camrick CO2-EOR Flood

    G ro ss B o e /d G ro ss C O 2 P u rc h ases, M c f/ d Secondary Development Primary Development Tertiary Development Camrick CO2–EOR Flood 41 +1500 BOPD

  42. Slide 42: North Perryton CO2-EOR Flood

    Slide 42: North Perryton CO2-EOR Flood

    42 North Perryton CO2–EOR Flood G ro ss B o e /d G ro ss C O 2 P u rc h ases, M c f/ d Secondary Development Primary Development Tertiary Development +600 BOPD

  43. Slide 43: Booker Area CO2-EOR Flood

    Slide 43: Booker Area CO2-EOR Flood

    43 Primary Development Secondary Development Tertiary Development Booker Area CO2–EOR Flood G ro ss B o e /d G ro ss C O 2 P u rc h ases, M c f/ d +1100 BOPD

  44. Slide 44: Farnsworth Area CO2-EOR Flood

    Slide 44: Farnsworth Area CO2-EOR Flood

    44 Primary Development Tertiary Development Secondary Development Farnsworth Area CO2–EOR Flood (West Side Only) Gr o ss B o e /d G ro ss C O 2 P u rc h ases, M c f/ d +2900 BOPD

  45. Slide 45: Potential in Excess of 700 MMBoe

    Slide 45: Potential in Excess of 700 MMBoe

    45 Potential in Excess of 727 MMBoe  Near-term + Long-term strategy yields significant value increase  ~ 70% Oil  Near-term focus on NOMP  De-risk play, unlock value  Production growth  Long-term focus on EOR  Low-risk production upside  Long-life, stable production * Woodford, Bone Spring,

  46. Slide 46: Financial Overview

    Slide 46: Financial Overview

    Financial Overview Chaparra

  47. Slide 47: Financial Summary

    Slide 47: Financial Summary

    47 Financial Summary 2010 2011 2012 1Q, 2013 Price Oil & NGL – Wellhead ($/Bbl) $74.53 $87.52 $78.65 $78.16 Gas – Wellhead ($/Mcf) $4.36 $4.08 $2.64 $3.14 Production (MMBoe) 8.1 8.7 9.1 2.2 Oil & NGL (MMBbls) 4.0 5.0 5.8 1.4 Gas (Bcf) 23.7 21.6 19.8 4.8 Financial Data ($mm) Operating Expenses: Lease

  48. Slide 48: Financial Metrics per Boe

    Slide 48: Financial Metrics per Boe

    Financial Metrics per Boe Production (Boe) / Day LOE / Boe EBITDA / Boe G&A / Boe 48 20,926 22,055 23,712 24,912 24,928 0 10,000 20,000 30,000 2009 2010 2011 2012 1Q, 2013 $12.32 $13.18 $14.03 $14.37 $15.15 $0 $5 $10 $15 $20 2009 2010 2011 2012 1Q,2013 $3.11 $3.72 $4.86 $5.46 $6.25 $0 $2 $4 $6 $8 20

  49. Slide 49: Operating Statistics 2013 Guidance

    Slide 49: Operating Statistics 2013 Guidance

    Operating Statistics 2013 Guidance Capital Expenditures $410 - $420 million Production 9.6 - 9.8 MMBoe General and Administrative $5.50 - $6.00/Boe Lease Operating Expense $14.25 - $14.75/Boe 2013 Guidance 49

  50. Slide 50: Hedge Portfolio

    Slide 50: Hedge Portfolio

    50 Hedge Portfolio : % of TP Reserves (As of June 3, 2013) Note: Dollars represent average strike price of hedges (includes all derivative instruments) Gas Basis Hedges YR Price % TP ’13 $ 0.20 78% ’14 $ 0.22 68%

  51. Slide 51: Question & Answer

    Slide 51: Question & Answer

    Question & Answer Chaparra

Source: SEC EDGAR · 8-K filed Jun 4, 2013