Rtg Mining, Inc. · TSX:RTG

Rtg Mining — Investor Presentation (April 2016)

32 slides from Rtg Mining's investor presentation, April 2016

  1. Slide 1: Corporate Presentation April 2016

    Corporate Presentation April 2016

  2. Slide 2: Forward Looking Statements

    FORWARD LOOKING STATEMENTS Certain statements contained in this presentation constitute forward looking statements within the meaning of applicable securities laws including, among others, statements made or implied relating to RTG’s and / or Sierra’s objectives, strategies to achieve those objectiv

  3. Slide 3: Qualified Persons

    QUALIFIED PERSONS The information in this report that relates to Exploration Results at the Mabilo Project is based upon information prepared by or under the supervision of Robert Ayres BSc (Hons), who is a Qualified Person and a Competent Person. Mr Ayres is a member of the Australian Institute of

  4. Slide 4: Company Overview

    COMPANY OVERVIEW • British Virgin Islands-incorporated company listed on the TSX (RTG) and ASX (RTG) • Focused on developing the high grade copper/gold/magnetite Mabilo Project (RTG 58-64%) in the Philippines • Mabilo Project represents a significant, near term, high- grade (copper and gold) and low

  5. Slide 5: Corporate Overview

    CORPORATE OVERVIEW* Capital Structure Share Price Share Price A$0.55 0.9 900 Volume Share Price Common Shares 134M 0.8 800 0.7 700 Options 8.8M 0.6 600 Fully Diluted 143M 0.5 500 '000 A$ 0.4 400 Market Capitalisation A$74M 0.3 300 0.2 200 Cash & Cash Equivalents A$5.3M 0.1 100 *As at 29 February 201

  6. Slide 6: Mabilo Project Overview

    MABILO PROJECT OVERVIEW • High grade gold/copper magnetite skarn deposit located in the Camarines Norte Province, Eastern Luzon, Philippines • Feasibility Study complete demonstrating a robust and financially viable new development opportunity • RTG owns 58%-64% of the project in joint venture with

  7. Slide 7: Comparison with Other Development Projects

    COMPARISON WITH OTHER DEVELOPMENT PROJECTS Significant by-product credits set the Mabilo deposit apart from its open-pit peers Source: Metals Economics / Intierra Au Eq. Grade using spot commodity prices TSX: TSX:RTG//ASX: RTG//ASX:RTG//RTGMINING.COM RTG//RTGMINING.COM 7

  8. Slide 8: Two Stage Development of Mabilo

    TWO STAGE DEVELOPMENT OF MABILO • High grade shallow oxide mineralisation will be prioritised for initial exploitation in Stage 1 Stage 1 DSO • Early start up strategy that will enable Operation early cashflows, with nominal capital expenditure requirements • Stage 2 will focus on concentrate produc

  9. Slide 9: Mabilo Resources

    MABILO RESOURCES 2015 Updated Mabilo Resource Estimate Gold equivalent* Copper equivalent* Indicated and Inferred 1.97 Moz @ 4.8 g/t Au Eq 472 kt @ 3.70% Cu Eq JORC (2012) Cu Au Resource** 12.76Mt 1.80% 1.9g/t *Equivalent calcs at US$5000/t Cu and US$1200/oz Au and calculated before recoveries Conta

  10. Slide 10: Mabilo Probable Mineral Reserve

    MABILO PROBABLE MINERAL RESERVE Ore Waste Strip Ratio Class Type Mt Fe % Au g/t Cu % Ag g/t Mt Gold Cap 0.351 40.1 3.11 0.38 3.26 Supergene 0.104 36.5 2.20 20.7 11.9 Probable Oxide 0.182 43.6 2.52 4.17 19.9 77.713 10.0 Skarn Fresh 7.155 45.9 1.97 1.70 8.73 Total Probable Ore 7.792 45.5 2.04 1.95 8.7

  11. Slide 11: Current Defined Mineralised Zones at Mabilo

    CURRENT DEFINED MINERALISED ZONES AT MABILO Showing Copper Grade Shells and Drilling TSX: TSX:RTG//ASX: RTG//ASX:RTG//RTGMINING.COM RTG//RTGMINING.COM 11

  12. Slide 12: Stage 1 – Direct Shipping Ore Operation

    STAGE 1 – DIRECT SHIPPING ORE OPERATION Stage 1 Overview • Stage 1 consists of DSO operation providing early cash flow • Within 4–5 months of permitting, DSO generates cashflows • 3 key oxide products: • oxide gold cap (3.28 g/t Au) • oxide skarn (3.51 g/t Au and 4.74% Cu) • chalcocite supergene cop

  13. Slide 13: Mabilo Stage 1 DSO - A Robust Project

    MABILO STAGE 1 DSO - A ROBUST PROJECT SUMMARY OF DFS Capex US$17.4M Net Operating Cashflow after Tax US$68M* Production Equivalent Cu produced 25,300 t 35,000 t Au produced 39,000 oz 144,000 oz Average Costs Per tonne US$61.91 Per Cu eq US$0.42/lb Per Au eq US$224/oz NSR Gold cap ore 100% Copper in

  14. Slide 14: Stage 2 – Concentrate Production

    STAGE 2 – CONCENTRATE PRODUCTION • Stage 2 consists of the construction of a 1.35 mtpa process plant • 8 year project life • Low production costs • Produces 3 high quality concentrate products: • 27% Cu / 21 g/t Au copper gold con • 3 g/t Au pyrite con • 65% magnetite con • No deleterious elements,

  15. Slide 15: Stage 2 - Process Flowsheet

    STAGE 2 - PROCESS FLOWSHEET TSX: TSX:RTG//ASX: RTG//ASX:RTG//RTGMINING.COM RTG//RTGMINING.COM 15

  16. Slide 16: Stage 2 – Concentrate Production

    STAGE 2 – CONCENTRATE PRODUCTION Capex US$161M PROJECT OVERVIEW (includes US$15m of recoverable VAT) NPV* 1.35Mtpa 10% 10% Case Increase in Increase in Pre-Strip US$24.4M (includes Commodity Commodity US$2.61M of Prices Price + recoverable VAT) 2.8Mt Net Annual Operating US$52M* 0% 223M 285M 471M Ca

  17. Slide 17: Mabilo Project Timing

    MABILO PROJECT TIMING Granting of DSO Operating Permit Startup of DSO 3-4 months Potential DSO Pre-Strip 4 months commencement 2016 Processing Gold Cap 5 months Material Copper Chalcocite 6 months Permitting Stage 2 12 months Potential Primary Plant commissioned early 2018 Detailed 3-4 months Engine

  18. Slide 18: Mabilo Joint Venture with Galeo Mining

    MABILO JOINT VENTURE WITH GALEO MINING • RTG management team has had a relationship with Galeo for ~8 years (mining contractor at Masbate) • Galeo are a high net worth partner with existing successful DSO operation in the Philippines • Earning up to 42% (currently earned 36%) • Earn-in includes fund

  19. Slide 19: Mabilo - Significant Exploration Upside

    MABILO - SIGNIFICANT EXPLORATION UPSIDE Magnetic Anomalies • Drilling since maiden resource indicates strong growth potential • Significant exploration potential remains along strike, regionally and at depth • Potential for high grade copper/gold corridor • Magnetic anomalies at Venida Pit and South

  20. Slide 20: Exploration - Nalesbitan

    SIGNIFICANT PORPHYRY COPPER POTENTIAL • 1,161 hectare property area • Located 15km west of Mabilo • Nalesbitan Hill represents a large, high- sulphidation epithermal gold mineralizing system with an intense alteration halo • 7 main project areas on the tenement EXPLORATION - NALESBITAN • Associated

  21. Slide 21: Bunawan Exploration Overview

    BUNAWAN EXPLORATION OVERVIEW • Significant landing holding – 88 sq km (second only to Medusa Mining) • Similar geological setting to the high grade Co-O Mine held by Medusa Mining • Excellent exploration potential with 4 projects in prolific mining region (surrounding Medusa Mining) • High grade Au

  22. Slide 22: Bunawan Reconnaissance Program Completed

    BUNAWAN RECONAISSANCE PROGRAM COMPLETED • Substantial mineralization found within broad corridor along southern margin of the Mahunoc diatreme • 8-hole initial drill program completed (3500m) in late 2014 • Walk up targets already identified with potential for 3 types of mineralization: • Low sulphi

  23. Slide 23: Management Expertise

    MANAGEMENT EXPERTISE Proven Track Record MANAGEMENT EXPERIENCE • Developed and operated 7 gold mines in Project Location Ounces/Yr 5 different countries (including Philippines) Marymia W. Australia 75,000 • All executed on schedule & on budget Bullabulling W. Australia 100,000 • 8th Development proj

  24. Slide 24: Board and Management

    BOARD AND MANAGEMENT BOARD CHAIR Chartered Accountant with over 30 years of experience in the resources sector. Previously Chairman and CEO of CGA Michael Carrick Mining, Chairman of AGR and CEO of Resolute. He has been responsible for the development of seven major gold mines in five countries. Cha

  25. Slide 25: Contacts

    CONTACTS EXPERTISE Philippines Justine Magee New Developments President & CEO Capital Markets Tel: +61 8 6489 2900 Fax: +61 8 6489 2920 Email: [email protected] PROJECTS Low Cost Mark Turner High Grade Chief Operating Officer Major Upside Tel: +61 8 6489 2900 Infrastructure Fax: +61 8 6489 2920 E

  26. Slide 26: Appendix

    APPENDIX BUSINESS MODEL RESERVE & RESOURCE CROSS SECTION DRILLING 26

  27. Slide 27: RTG Business Model

    RTG BUSINESS MODEL UNLOCK VALUE IN DEVELOPMENT PROJECTS AND CREATE A LIQUIDITY EVENT FOR ALL SHAREHOLDERS • Focused on high grade, low operating cost gold projects • Targeting projects with low technical and project risk • Goal of delineating substantial in-ground resources & reserves • Significant

  28. Slide 28: 2015 Resource Estimate

    2015 RESOURCE ESTIMATE Mabilo Deposit – South and North Zones Million Contained Au Contained Cu Contained Fe Au Equivalent* Weathering State Classification Cu% Au g/t Ag g/t Fe% Tonnes (‘000s oz) (‘000s t) (‘000s t) (‘000s oz) Indicated 0.78 4.1 2.7 9.7 41.2 67.1 32.1 320.8 197.0 Oxide & Inferred 0.

  29. Slide 29: 2015 Oxide Resource Estimate

    2015 OXIDE RESOURCE ESTIMATE Contained Au Contained Cu Contained Fe South Mineralized Zone MillionTonnes Au g/t Cu% Fe% (‘000s oz) (‘000s t) (‘000s t) Oxide Gold Cap 0.33 3.1 0.2 42.6 33.3 0.7 142.2 Oxide Copper/Gold 0.28 2.4 2.6 44.0 21.6 7.1 121.4 Indicated Supergene Chalcocite 0.10 2.3 23.2 38.4

  30. Slide 30: South Body Cross Sections

    SOUTH BODY CROSS SECTIONS TSX: TSX:RTG//ASX: RTG//ASX:RTG//RTGMINING.COM RTG//RTGMINING.COM 30

  31. Slide 31: North Body Cross Sections

    NORTH BODY CROSS SECTIONS TSX: TSX:RTG//ASX: RTG//ASX:RTG//RTGMINING.COM RTG//RTGMINING.COM 31

  32. Slide 32: Significant Drill Results

    SIGNIFICANT DRILL RESULTS Hole Interval Metres AU g/t Cu% Ag g/t Fe% Au Equivalent Grades MDH-01 26-86 60 2.28 3.28 11.8 49.05 8.16 g/t MDH-05 51-113 62 2.66 2.76 10.3 48.82 7.75 g/t MDH-07 39-136 97 2.25 2.22 7.1 50.26 6.53 g/t MDH-10 59-123.4 64.4 2.25 2.28 10.2 45.25 6.57 g/t Consistent widths of

RTG Mining — Investor Presentation (April 2016) on 6ix