Slide 1: Merger with Tellurian
October 2016 Merger with Tellurian NASDAQ: MPET FILED BY MAGELLAN PETROLEUM CORPORATION PURSUANT TO RULE 425 UNDER THE SECURITIES ACT OF 1933 AND DEEMED FILED PURSUANT TO RULE 14a-12 UNDER THE SECURITIES EXCHANGE ACT OF 1934 SUBJECT COMPANY: TELLURIAN INVESTMENTS INC. (FILE NO. 333-213923)
Slide 2: Forward-looking statements
1 Forward-looking statements This presentation contains forward-looking statements within the meaning of U.S. federal securities laws. The words “anticipate,” “assume,” “believe,” “budget,” “estimate,” “expect,” “forecast,” “initial,” “intend,” “plan,” “potential,” “project,” “will,” and similar exp
Slide 3: Combined company ownership
2 Combined company ownership Tellurian Investments Inc. (“Tellurian”) was founded in February 2016 to develop low cost LNG export projects on the US Gulf Coast – Tellurian was co-founded by Charif Souki and Martin Houston and is led by Meg Gentle (CEO) Definitive Merger Agreement between Magella
Slide 4: Merger conditions
3 Merger conditions Board Proposed merger results from extensive strategic alternatives review process – None of Magellan’s remaining assets currently generate revenues Ability to participate in unique business plan – Driftwood LNG positioned to take advantage of growing LNG market Attractive
Slide 5: Proposed mtpa LNG export facility in Louisiana
4 Proposed 26 mtpa LNG export facility in Louisiana Location Site Driftwood LNG project 26 mtpa liquefaction capacity = 5 LNG plants, each made up of 1 natural gas pre-treatment unit and 4 liquefaction units with nominal capacity of 1.3 mtpa each (i.e. 5.2 mtpa per plant) ~800-acre site on the C
Slide 6: Developing low cost LNG export projects on the US Gulf Coast
5 Developing low cost LNG export projects on the US Gulf Coast Engineering and construction improvements – Design based on existing technologies and off-the-shelf equipment (vs. expensive bespoke designs) – Higher density of production, using less pipe – Targeting construction costs of $450 to $55
Slide 7: Strategically aligned with best-in-class partners to reset LNG cost benchmarks
6 Strategically aligned with best-in-class partners to reset LNG cost benchmarks Integration with development partners Function Partner Description EPC Bechtel is a world leader in the LNG industry and has built 41 facilities producing 120 mtpa to date: c. 45% of global capacity Founders have de
Slide 8: Proposed project schedule
7 Proposed project schedule Key milestones Approximately 2 years to conduct environmental studies, permitting and FERC application – FERC pre-filing process initiated in June 2016 and stakeholder engagement underway – FERC expected to issue ‘notice to proceed’ in 2018 Approximately 4 years from
Slide 9: Pro-forma management team
8 Charif Souki, Chairman Founded Cheniere Energy, the first LNG export company in the United States, growing it to a $9 Bn company while serving as CEO from 2002 to 2015 A lifelong entrepreneur, Charif has spent 20 years raising and investing capital in a range of industries globally Pro-forma m