Elia Group Sa/nv — Corporate Update (March 2014)

18 slides from Elia Group Sa/nv's corporate update, Mar 20, 2014

  1. Slide 1: Status WG European Market Design

    Status WG European Market Design Users Group 20 March 2014

  2. Slide 2: WG European Market Design

    WG European Market Design • Latest meeting: 20 December 2013 • Next meeting: 31 March 2014 • Ongoing projects: • Day Ahead Market Coupling in N-WE region • Flow-Based Market Coupling in CWE region • Cross- Border Intraday (N-WE+) UG Plen. – 20/03/2014 2

  3. Slide 3: N-WE Day Ahead Market Coupling

    N-WE Day Ahead Market Coupling UG Plen. – 20/03/2014 3

  4. Slide 4: NWE Day-Ahead Price Coupling

    NWE Day-Ahead Price Coupling BEFORE - Two separate Market Couplings (CWE & Nordic) linked by a volume coupling (ITVC organised by EMCC) - Sequential calculation approach - No common algorithm applied SINCE delivery date February 5th 2014 - Full coupling with GB - One single price coupling based on a

  5. Slide 5: First results

    First results UG Plen. – 20/03/2014 5

  6. Slide 6: First results

    First results UG Plen. – 20/03/2014 6

  7. Slide 7: Post Go-Live Activities

    Post Go-Live Activities Testing & extensions :  SWE (South West Europe) : May 2014 ?  Italian Borders : end of 2014 ?  CWE Flow Based  Long Clock Changes UG Plen. – 20/03/2014 7

  8. Slide 8: CWE Flow-Based Market Coupling

    CWE Flow-Based Market Coupling UG Plen. – 20/03/2014 8

  9. Slide 9: CWE FB MC Project Status

    CWE FB MC Project Status • Successful launch of daily parallel run publication on February, 24th • Bilateral meetings have been organized by the Project with MPs to discuss their needs in terms of transparency and data publication • Planning has been updated and communicated during last PLEF UG Plen

  10. Slide 10: CWE FB MC Project Planning

    CWE FB MC Project Planning Project partners foresee a readiness target date by the end of September but a contingency period is needed until end of November in case of unforeseen issues related to:  MPs’ readiness  IT system readiness and successful testing  Appropriate management of interactions

  11. Slide 11: CWE FB MC: Feedback bilateral meetings with MPs

    CWE FB MC: Feedback bilateral meetings with MPs CWE Project Partners have now a better understanding what is needed in order to support MPs as best as they can in the switch from ATC to FB Summary of discussion  MPs’ main concern: predictability of prices over varying time horizons (from multi-year

  12. Slide 12: External parallel run results: Price convergence

    External parallel run results Price convergence (= percentage of time with single CWE price) 100% 90% ATC FB FBI 80% Price convergence 70% 60% 50% 40% 30% 20% 10% 0% 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47

  13. Slide 13: External parallel run results Yearly results for 2013

    External parallel run results Yearly results for 2013 Welfare increase of 79M€ (307 days simulated of 365) for 2013 with an average daily gain of 257 K€: Average baseload prices and price spreads: UG Plen. – 20/03/2014 13

  14. Slide 14: Cross-Border Intraday (N-WE+)

    Cross-Border Intraday (N-WE+) UG Plen. – 20/03/2014 14

  15. Slide 15: High level overview of current status

    High level overview of current status - Early Start Agreement (ESA) is in place – Step 1 has commenced and resources have been mobilised within Deutsche Börse (DBAG), Power Exchanges (PXs) and Transmission System Operators (TSOs) – This phase delivers: - The detailed project plan, - Details of the p

  16. Slide 16: Joint Project Approach

    Joint Project Approach Design Local /regional Implementation projects Local /Regional Implementation Projects (LIPs) Roadmap interim Solution LIPs framework conditions Roadmap info from LIPs satisfied Common framework for Follow-up/coordinate implementation of pre- and postcoupling Interim Solution

  17. Slide 17: High level PX project plan with DBAG

    High level PX project plan with DBAG ESA Project under ESA Project under Contract Signature ESA ESA Step 2 Step 1 Project Design and Development Planning Business Blueprint FAT & IAT (for ESA Step UAT Activi Development and infrastructure 2 onwards) ties Quality D&D Contract Maintenance planning Neg

  18. Slide 18: Project Structure and interfaces

    Project Structure and interfaces NRAs / ACER / AESAG / Stakeholder Committee (to be defined) “NWE + TSO“ Intraday Steering Committee “XBID PXs“ Steering Committee (ID SC) Steering Committee TS Core O Tea PM m “NWE + TSO“ ID Coordination “XBID PXs“ Coordination Team Team (ID CT) PM Project Team O Mon