  1. Slide 1: Service Application Process

    Service Application Process

  2. Slide 2: Project Covered Application

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  3. Slide 3: Project Covered Application: Submit initial requirements

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  4. Slide 4: Initial Requirements

    Initial Requirements Service Application can already proceed even with the initial submission of the following three important requirements: 1. SEC Registration or Latest General Information Sheet (GIS) 2. Electrical Plan and Load Schedule 3. Letter of request for electric connection and authorizati

  5. Slide 5: Project Covered Application: Receives and reviews application

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  6. Slide 6: Project Covered Application: Survey and cost estimate

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  7. Slide 7: Annex 1. Service Standards for Service Availability

    Annex 1. Service Standards for Service Availability Secondary Nominal Primary Nominal Service Voltages Voltages Voltages 230 Volts, 400 Volts, 460 Volts 13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV Allowable Frequency Variations • Nominal fundamental frequency shall be 60 Hz • Meralco shall design and o

  8. Slide 8: Annex 1. Service Standards: Nominal Voltage Limitations

    Annex 1. Service Standards for Service Availability Secondary Nominal Primary Nominal Service Voltages Voltages Voltages 230 Volts, 400 Volts, 460 Volts 13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV Nominal Voltage Limitations 230 Volts, Single Phase (1Ø), Two (2)- Maximum capacity of MERALCO-supplied Wi

  9. Slide 9: Annex 1. Service Standards: Secondary Voltage Requirements

    Annex 1. Service Standards for Service Availability Secondary Nominal Primary Nominal Service Voltages Voltages Voltages 230 Volts, 400 Volts, 460 Volts 13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV Nominal Voltage Requirements 230 Volts, Single Phase (1Ø), Two (2)- • service shall be metered at the seco

  10. Slide 10: Annex 1. Service Standards: Primary Voltage Requirements

    Annex 1. Service Standards for Service Availability Secondary Nominal Primary Nominal Service Voltages Voltages Voltages 230 Volts, 400 Volts, 460 Volts 13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV Nominal Voltage Requirements 13.2/7.62 kV Three Phase (3Ø), Four (4)- • service shall be metered at the pr

  11. Slide 11: Annex 2. Standard Connection Facilities

    Annex 2. Standard Connection Facilities DISTRIBUTION BUSINESS SEGMENT

  12. Slide 12: Annex 2. Standard Connection Facilities

    Annex 2. Standard Connection Facilities • Assets used to provide Distribution Connection Services • Minimum facilities necessary to establish a connection for a typical customer within a customer segment - Service drop for residential customers - Service drop and distribution transformer (if any) fo

  13. Slide 13: Annex 2. Major Customer Segments

    Annex 2. Standard Connection Facilities 3 Major Customer Segments SEGMENT CONNECTION Low Voltage Service ≤ 460 volts Distribution Voltage Service 3.6kV – 34.5 kV Sub-transmission Voltage 69kV – 115kV Service

  14. Slide 14: Low Voltage Service: ≤ 460 volts

    Annex 2. Standard Connection Facilities A. Low Voltage Service: ≤ 460 volts SCF for non-residential customer

  15. Slide 15: Low Voltage Service: ≤ 460 volts

    Annex 2. Standard Connection Facilities A. Low Voltage Service: ≤ 460 volts

  16. Slide 16: Distribution Voltage Service: 3.6 kV to 34.5 kV

    Annex 2. Standard Connection Facilities B. Distribution Voltage Service: 3.6 kV to 34.5 kV SCF for non-residential customer

  17. Slide 17: Distribution Voltage Service: 3.6 kV to 34.5 kV

    Annex 2. Standard Connection Facilities B. Distribution Voltage Service: 3.6 kV to 34.5 kV

  18. Slide 18: Sub-transmission Voltage Service: 69 kV to 115 kV

    Annex 2. Standard Connection Facilities C. Sub-transmission Voltage Service: 69 kV to 115 kV

  19. Slide 19: Sub-transmission Voltage Service: 69 kV to 115 kV

    Annex 2. Standard Connection Facilities C. Sub-transmission Voltage Service: 69 kV to 115 kV

  20. Slide 20: Project Covered Application: Intent to proceed and sign-off

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  21. Slide 21: Annex 3. Estimated Lead Time per Activity

    Annex 3. Estimated Lead Time per Activity PRECEDING LEAD TIME NO ACTIVITY ACTIVITY (DAYS)* 1 Submission of Application and Initial Requirements (Letter of Request, EE Plan) N/A 2 2 Receipt of Application & Advise of all pertinent requirements 1 2 3 Submission of Initial Vault Drawing 2 7 4 Initial S

  22. Slide 22: Annex 3. Estimated Lead Time per Activity

    Annex 3. Estimated Lead Time per Activity Estimated time of 113 days * to energize Activity Lead Time per Activity (Days)* Submission of Application and Initial 2 Requirements (Letter of Request, EE Plan) Receipt of Application & Advise of all 2 Processing & Critical activities pertinent requirement

  23. Slide 23: Project Covered Application: Service entrance construction

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  24. Slide 24: Annex 4. Connection Point of Customer Facilities

    Annex 4. Connection Point of Customer Facilities to Meralco’s Distribution System The Single-Line Diagram shows the arrangement and the facilities at the Connection Point for the connection of Customer’s Primary-Side Facilities with the Company’s Distribution System.

  25. Slide 25: Annex 5. List of Meralco and Customer Assets

    Annex 5. List of Meralco and Customer Assets MERALCO FACILITIES Facilities Quantity 27kV Surge Arrester 6 Units Fuse Cut-Out or Power Fuse 3 Units 34.5kV Current Transformer (CT) 3 Units 34.5kV Potential Transformer (PT) 3 Units Meter and Accessories 1 Set Metering Pole 1 Unit CUSTOMER FACILITIES Fa

  26. Slide 26: Project Covered Application: Design and project cost

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  27. Slide 27: Project Covered Application: Contract presentation and acceptance

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  28. Slide 28: Annex 6. Contracts

    Annex 6. Contracts Customer Required Contracts Captive Long form contract / ASEE Line extension agreement (if applicable) * either cash advance or CIAC Contestable Connection agreement (FABD – Fixed Asset Boundary Document) DWSA (Distribution Wheeling Service Agreement) Line extension agreement (if

  29. Slide 29: Project Covered Application: Inspection of compliance

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  30. Slide 30: Project Covered Application: Payment and CFEI

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  31. Slide 31: Project Covered Application: Construct lines and facilities

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  32. Slide 32: Project Covered Application: Project completed

    Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of

  33. Slide 33: Thank You!

    MERALCO? \ RT NES PQWERU FORUM SERIES Thank You!