Slide 1: Service Application Process
Service Application Process
Slide 2: Project Covered Application
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 3: Project Covered Application: Submit initial requirements
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 4: Initial Requirements
Initial Requirements Service Application can already proceed even with the initial submission of the following three important requirements: 1. SEC Registration or Latest General Information Sheet (GIS) 2. Electrical Plan and Load Schedule 3. Letter of request for electric connection and authorizati
Slide 5: Project Covered Application: Receives and reviews application
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 6: Project Covered Application: Survey and cost estimate
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 7: Annex 1. Service Standards for Service Availability
Annex 1. Service Standards for Service Availability Secondary Nominal Primary Nominal Service Voltages Voltages Voltages 230 Volts, 400 Volts, 460 Volts 13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV Allowable Frequency Variations • Nominal fundamental frequency shall be 60 Hz • Meralco shall design and o
Slide 8: Annex 1. Service Standards: Nominal Voltage Limitations
Annex 1. Service Standards for Service Availability Secondary Nominal Primary Nominal Service Voltages Voltages Voltages 230 Volts, 400 Volts, 460 Volts 13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV Nominal Voltage Limitations 230 Volts, Single Phase (1Ø), Two (2)- Maximum capacity of MERALCO-supplied Wi
Slide 9: Annex 1. Service Standards: Secondary Voltage Requirements
Annex 1. Service Standards for Service Availability Secondary Nominal Primary Nominal Service Voltages Voltages Voltages 230 Volts, 400 Volts, 460 Volts 13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV Nominal Voltage Requirements 230 Volts, Single Phase (1Ø), Two (2)- • service shall be metered at the seco
Slide 10: Annex 1. Service Standards: Primary Voltage Requirements
Annex 1. Service Standards for Service Availability Secondary Nominal Primary Nominal Service Voltages Voltages Voltages 230 Volts, 400 Volts, 460 Volts 13.2 kV, 13.8 kV, 34.5 kV, 69 kV, 115 kV Nominal Voltage Requirements 13.2/7.62 kV Three Phase (3Ø), Four (4)- • service shall be metered at the pr
Slide 11: Annex 2. Standard Connection Facilities
Annex 2. Standard Connection Facilities DISTRIBUTION BUSINESS SEGMENT
Slide 12: Annex 2. Standard Connection Facilities
Annex 2. Standard Connection Facilities • Assets used to provide Distribution Connection Services • Minimum facilities necessary to establish a connection for a typical customer within a customer segment - Service drop for residential customers - Service drop and distribution transformer (if any) fo
Slide 13: Annex 2. Major Customer Segments
Annex 2. Standard Connection Facilities 3 Major Customer Segments SEGMENT CONNECTION Low Voltage Service ≤ 460 volts Distribution Voltage Service 3.6kV – 34.5 kV Sub-transmission Voltage 69kV – 115kV Service
Slide 14: Low Voltage Service: ≤ 460 volts
Annex 2. Standard Connection Facilities A. Low Voltage Service: ≤ 460 volts SCF for non-residential customer
Slide 15: Low Voltage Service: ≤ 460 volts
Annex 2. Standard Connection Facilities A. Low Voltage Service: ≤ 460 volts
Slide 16: Distribution Voltage Service: 3.6 kV to 34.5 kV
Annex 2. Standard Connection Facilities B. Distribution Voltage Service: 3.6 kV to 34.5 kV SCF for non-residential customer
Slide 17: Distribution Voltage Service: 3.6 kV to 34.5 kV
Annex 2. Standard Connection Facilities B. Distribution Voltage Service: 3.6 kV to 34.5 kV
Slide 18: Sub-transmission Voltage Service: 69 kV to 115 kV
Annex 2. Standard Connection Facilities C. Sub-transmission Voltage Service: 69 kV to 115 kV
Slide 19: Sub-transmission Voltage Service: 69 kV to 115 kV
Annex 2. Standard Connection Facilities C. Sub-transmission Voltage Service: 69 kV to 115 kV
Slide 20: Project Covered Application: Intent to proceed and sign-off
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 21: Annex 3. Estimated Lead Time per Activity
Annex 3. Estimated Lead Time per Activity PRECEDING LEAD TIME NO ACTIVITY ACTIVITY (DAYS)* 1 Submission of Application and Initial Requirements (Letter of Request, EE Plan) N/A 2 2 Receipt of Application & Advise of all pertinent requirements 1 2 3 Submission of Initial Vault Drawing 2 7 4 Initial S
Slide 22: Annex 3. Estimated Lead Time per Activity
Annex 3. Estimated Lead Time per Activity Estimated time of 113 days * to energize Activity Lead Time per Activity (Days)* Submission of Application and Initial 2 Requirements (Letter of Request, EE Plan) Receipt of Application & Advise of all 2 Processing & Critical activities pertinent requirement
Slide 23: Project Covered Application: Service entrance construction
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 24: Annex 4. Connection Point of Customer Facilities
Annex 4. Connection Point of Customer Facilities to Meralco’s Distribution System The Single-Line Diagram shows the arrangement and the facilities at the Connection Point for the connection of Customer’s Primary-Side Facilities with the Company’s Distribution System.
Slide 25: Annex 5. List of Meralco and Customer Assets
Annex 5. List of Meralco and Customer Assets MERALCO FACILITIES Facilities Quantity 27kV Surge Arrester 6 Units Fuse Cut-Out or Power Fuse 3 Units 34.5kV Current Transformer (CT) 3 Units 34.5kV Potential Transformer (PT) 3 Units Meter and Accessories 1 Set Metering Pole 1 Unit CUSTOMER FACILITIES Fa
Slide 26: Project Covered Application: Design and project cost
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 27: Project Covered Application: Contract presentation and acceptance
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 28: Annex 6. Contracts
Annex 6. Contracts Customer Required Contracts Captive Long form contract / ASEE Line extension agreement (if applicable) * either cash advance or CIAC Contestable Connection agreement (FABD – Fixed Asset Boundary Document) DWSA (Distribution Wheeling Service Agreement) Line extension agreement (if
Slide 29: Project Covered Application: Inspection of compliance
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 30: Project Covered Application: Payment and CFEI
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 31: Project Covered Application: Construct lines and facilities
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of
Slide 32: Project Covered Application: Project completed
Project Covered Application 6 major steps before energization. For each step, the customer and Meralco have responsibilities to fulfill 1 2 3 4 5 6 Design Presentation Payment / Construct Receipt of Pre-Survey and Prepare and Acceptance compliance to Lines Application and Processing Project Cost Of