Cleanaway Waste Management Ltd. · ASX:CWY

Cleanaway Waste Management — Corporate Update (July 2016)

10 slides from Cleanaway Waste Management's corporate update, Jul 13, 2016

  1. Slide 1: Tullamarine Landfill Community Meeting

    Tullamarine Landfill Community Meeting 13 July 2016

  2. Slide 2: Leachate Management

    Leachate Management  Commencing leachate removal from Mound 1  Testing to see how much can be feasibly recovered  Trial will commence in July/August  Will report results at next meeting  Leachate trial is not a regulatory requirement

  3. Slide 3: Groundwater Report Timeline

    Groundwater Report Timeline  TECHNICAL REVIEW  The Technical Review Report will be ready for the community by end of July.  Report still with Environmental Auditor for review – review process taking longer than expected.

  4. Slide 4: Additional Off-site Groundwater Wells

    Additional Off-site Groundwater Wells  Proposed new well locations to provide delineation of existing groundwater impacts in MB86.  Groundwater flow direction considered in proposed locations of new wells.  Proposed drilling locations selected based on accessibility and consideration underground/

  5. Slide 5: New Groundwater Monitoring Boreholes

    New Groundwater Monitoring Boreholes Proposed Locations Non regulatory requirement

  6. Slide 6: Air Quality Testing Update

    Air Quality Testing Update  Flare sampling for methane destruction efficiency took place in April 2016 and June 2016.  No methane was detected to the detection limits of the instrumentation in the stack sample port on both occasions.  A second full emissions test is to be completed during July wh

  7. Slide 7: Setting Up for Sampling - 12/7/2016

    Setting Up for Sampling - 12/7/2016

  8. Slide 8: Cap Management

    Cap Management  Settlement is monitored every three months.  Inspections completed monthly.  Contractors on site every two weeks for maintenance.  Site walkover SEM survey completed annually.  Cleanaway staff on site 24/7.

  9. Slide 9: Stormwater Connection Timeline

    Stormwater Connection Timeline  Redesign and retender before end of 2016.  Commence work after from beginning 2017.  18 month programme of work.

  10. Slide 10: Stormwater Redesign

    Stormwater Redesign Landscaped Channels