Tata Power Company Limited · NSE:TATAPOWER
Tata Power — The Tata Power Company — Investor Presentation (June 2009)
52 slides from Tata Power's investor presentation, June 2009
Slide 1: The Tata Power Company Limited Investors' Meet - June 2009
The Tata Power Company Limited Investors’ Meet - June 2009 1
Slide 2: Disclaimer
Disclaimer Certain statements made in this presentation may not be based on historical information or facts and may be “forward looking statements”, including those relating to The Tata Power Company Limited’s general business plans and strategy, its future outlook and growth prospects, and future d
Slide 3: Agenda
Agenda Part A: Overview of Tata Power Part B: Standalone Business Part C: Projects Part D: Other Power Businesses Part E: Other Businesses Part F: Financial Performance 3
Slide 4: Part A: Overview of Tata Power
Part A: Overview of Tata Power 4
Slide 5: A Tata Company
A Tata Company Lid Largest Group Companies Tata Consultancy Services Information Technology Tata Steel Tata Motors Materials Tata Communications Indian Hotels Services Tata Chemicals Voltas Tata Teleservices Tata Tea Titan
Slide 6: Tata Power Group – Major Investments
Tata Power Group – Major Investments Tata Power Subsidiaries Joint Ventures Investments & Associates 100% Coastal Gujarat KPC 7% TTML 30% Power Ltd. 8% TTSL 100% Trust Energy 30% Arutmin Resources Pte. Ltd Indocoal 40% Panatone 74% Maithon Power 30% Ltd. Tubed Coal 17% Tata Comm.* Industrial Energy
Slide 7: Businesses
• Trombay 12, 13 • Hydro 12, 14 Businesses • Jojobera 18 • Belgaum 17 • Haldia 16 • Wind Farm 19 • Solar PV 44 • Mundra 22-25 Division Generation • Maithon 26-28 • IEL 29-30 Other Entities Transmission • Mumbai 15 • Powerlinks 40 Power Business Distribution • Mumbai 15 • Delhi: NDPL 39 • Tata Power
Slide 8: Part B: Standalone Business
Part B: Standalone Business 8
Slide 9: Generation: Business Models
Generation: Business Models 9
Slide 10: Impact of New CERC Norms
ld Impact of New CERC Norms TATA Parameter Before Return on Equity Depreciation Long Term Loans - Refinance Costs - Net Savings O&M expenses Working Capital Incentives 14% (post tax) * 3.6% + AAD + Borne by beneficiaries + Fully passed on + Low base allowance (Rs/MW) * ~4% annual increase + At 80% a
Slide 11: Existing Presence
Existing Presence Powerlinks Mumbai 2027 MW NDPL Mumbai License Area Generation Thermal 1480 MW Gujarat 50 MW Hydro 447 MW Jojobera 428 MW Distribution Haldia 90 / 120 MW Transmission Mumbai Merchant Capacity Maharashtra 99 MW Thermal Thermal 2179 2179 MW MW Trombay 100 MW Belgaum 81 MW Hydro Hydro
Slide 12: Mumbai License Area (LA) - Generation
Mumbai License Area (LA) - Generation Thermal Hydro Trombay - Thermal Unit Capacity Fuel Location Capacity Unit 4* 150 MW Oil & Gas Khopoli 72 MW Unit 5 500 MW Oil, Coal & Gas Bhivpuri 75 MW Unit 6 500 MW Oil & Gas Bhira 300 MW Unit 7 180 MW Gas Total 447 MW Unit 8 150 MW Coal Total 1480 MW * Unit 4
Slide 13: LA Generation Performance - Thermal
LA Generation Performance - Thermal Generation (MU) Availability (%) PLF (%) Aux. Consumption (%) “Greentech “Greentech Safety Safety Gold Gold Award Award 2008” 2008” for for Outstanding Outstanding achievement achievement in in Safety Safety Management th Management for for the the 55th consecutiv
Slide 14: LA Generation - Hydro
LA Generation - Hydro Generation (MU)* Availability (%) *Decrease due to adherence to KWTA limits PLF (%) Aux. Consumption (%) Bhira Bhira Pump Pump Storage Storage Scheme Scheme received received CEA CEA Silver Silver Shield for 22nd Shield for nd best best performing performing station station in
Slide 15: LA Transmission & Distribution
LA Transmission & Distribution • Around 1100 ckm network comprising of 973 ckm of 220 kV / 110 kV overhead lines and 124 ckm of 220 kV / 110 kV underground cables. • Over 25,400 customers with 2468 MUs of sales (mostly to high value bulk consumers) • 17 receiving and distribution stations, 318 consu
Slide 16: Merchant Capacity
Merchant Capacity Haldia* Trombay - Unit 8 Project Capacity 100 / 120 MW 100 / 250 MW Customers PPA with Tata Power Trading PPA with Tata Power Trading Hot flue gases from Hoogly Fuel Imported Coal Metcoke *Total Capacity 120MW: 90 MW commissioned, 30 MW expected to be commissioned in Q2FY09. 20 MW
Slide 17: Belgaum
Belgaum Capacity • 81 MW Generation (MU) Fuel Type • Heavy Fuel Oil Customer • KPTCL • 12 year PPA till 2012 Business • Bid Driven – Case 2 Model • Fuel charge is pass through • Fixed costs billed as per the bid PLF (%) 19 27 33 63 17
Slide 18: Jojobera
Jojobera Capacity • 428 MW Generation (MU) • Unit 1-3: 120 MW each, Unit 4: 67.5 MW Fuel Type • Domestic Coal Customer • Tata Steel Business • Captive Model • Fuel and Interest are a pass through • Other expenses on normative basis PLF (%) 77 73 76 80 1st 1st Prize Prize for for Ash Ash management m
Slide 19: Wind
Wind Capacity • 191 MW Generation (MU) Customer • Maharashtra: PPA with TPC-D • Karnataka: BESCOM • Gujarat: GUVNL • 3rd Party Sale: PPA with TPTCL Business • Regulated Model • Tariff based on State regulations except PLF (%) 18 19 20 19 for 3rd party sale through TPTCL * Third Party Sale allowed su
Slide 20: Part C: Projects
Part C: Projects 20
Slide 21: Generation Projects Under Implementation
Generation Projects Under Implementation Maithon1050 MW Mundra 4000 MW Jojobera/Jamshedpur 240 MW Haldia 30 / 120 MW Maharashtra 98 MW Thermal Thermal 5320 5320 MW MW Wind Wind 98 98 MW MW 21
Slide 22: Mundra UMPP
Capacity • 4000 MW (5 x 800 MW) Ownership Structure • 100% subsidiary; Coastal Gujarat Power Limited Business Model • Case 2 – Bid Driven Fuel Requirement • Imported Coal Fuel Source • Offtake agreement with KPC and Arutmin Customers • Gujarat (1805 MW), Maharashtra (760 MW), Punjab (475 MW), Haryan
Slide 23: Mundra UMPP
Current Status • Overall 23% work completed; 6000 people on site Construction • Unit 1: TG (Turbine Generator) deck staging work and erection of Activities front and LHS water panels of boiler complete • Unit 2: TG deck column casting complete; ceiling girders erected • Unit 3: Structural erection i
Slide 24: Mundra – Site Photographs
Mundra– Site Photographs Use of Heavy Equipment like this 1250 Ton Crane has accelerated project execution N LA fro m u r es t pic w Ne 24
Slide 25: Mundra – Boiler Unit 1 and Unit 2
Mundra – Boiler Unit 1 Mundra – Boiler Unit 2 25
Slide 26: Maithon
Capacity • 1050 MW (2 x 525MW) Ownership Structure • 74: 26 JV of Tata Power and Damodar Valley Corporation Business Model • CERC Regulated Fuel Requirement • Domestic Coal Fuel Source • 100% linkage sanctioned. Active discussions on to sign Fuel Supply Agreements with coal mines Customers • DVC (30
Slide 27: Maithon
Current Status • Over 48% of work completed Construction • Unit 1: Drum lifting complete Activity • Unit 2: Foundation and raft casting for TG #2 and foundation for Boiler Unit #2 complete • Tower and gantry erection and Stringing completed inside 400 kV switchyard. Slip form erection for Chimney is
Slide 28: Maithon – Site Photographs
Maithon– Site Photographs Boiler 2 Unit 1- Mill Bunker 28
Slide 29: Captive Power Plants
JAMSHEDPUR (PH #6) JOJOBERA (Unit #5) Project Capacity • 120 MW • 120 MW Ownership Structure • IEL (74:26 JV of Tata • IEL Power and Tata Steel) Business Model • CPP • CPP Funding • Project Cost: Rs 490 Crores • Project Cost: Rs 620 Crores • D/E 70:30 • D/E 70:30 Completion • July 2009 • December 20
Slide 30: Jojobera (Unit 5)
Jojobera (Unit 5) Boiler Pressure Parts Erection in Progress HP Heaters Under Erection 30
Slide 31: Captive Coal Blocks
Captive Coal Blocks Mandakini Coal Block • 7.5 MTPA (with JV partners with each partner having a 1/3rd share of 2.5 MTPA) at Dist. Angul, Orissa • Mining plan approved by MoC submitted to State Govt. • Application of ground water submitted to CGWA on Apr 09 • Environment Clearance, Acquisition of la
Slide 32: Other Projects in Pipeline
Other Projects in Pipeline Generation Others 32
Slide 33: Generation Capacity (Tata Power Group)
Generation Capacity (Tata Power Group) 8242 5842 4242 3104 2786 33
Slide 34: Part E: Other Power Businesses
Part E: Other Power Businesses 34
Slide 35: Indonesian Coal Mines
Indonesian Coal Mines Organizational Structure Offtake Agreement • 40% representation on the Board of • 10.1+ 20% MT on a take or pay basis Commissioners and the Board of Directors • Indocoal Resources (Cayman) agrees to with affirmative rights trade outside of India any coal that TPCL • CFOs at KPC
Slide 36: Indonesian Coal Mines
Indonesian Coal Mines Debt Repayment Schedule Loan Loan Amount Interest Maturity Repayment Details Amount O/S Rate (USD mn) (USD mn) Non- Recourse 590 454 1M LIBOR May 2014 Bullet of USD 175 million + 3.25% Recourse 270 270 6M LIBOR May 2014, Two equal installments at end of + 0.9% 2015 6th year and
Slide 37: Indonesian Coal Mines – Structure of Investment
Indonesian Coal Mines – Structure of Investment Tata Power Company Ltd. (India) Bhivpuri Bhira Investments Ltd. Investments Ltd. (Cyprus) (Mauritius) Indocoal KPC Arutmin (Cayman Islands) (Indonesia) (Indonesia) Bumi Resources (Indonesia) 37
Slide 38: Shipping Subsidiaries
Shipping Subsidiaries • Trust Energy Asia Ltd incorporated in Singapore for owning ships to meet shipping requirements and trading in fuels, Eastern Energy Private Ltd incorporated for chartering of ships • Present shipping requirements of 8 vessels for Mundra • To be met through a combination of lo
Slide 39: North Delhi Power Limited (NDPL)
North Delhi Power Limited (NDPL) Customer Base • >1 million customers with 5000 Mus PAT Rs. cr of consumption Business Model • Regulated Revenue • Rs 2479 Cr Incentive • AT & C Losses upto 15%: 50% of Structure additional revenue due to loss reduction over regulatory targets • AT & C Losses below 15
Slide 40: Powerlinks Transmission Limited
Powerlinks Transmission Limited Capacity PAT Rs. cr • 1200 km 400 kV double-circuit transmission lines Business Model • Regulated Revenue FY09 • Rs 273 Cr Incentive • As a percent of equity on availability Structure above Target of 98% Dividend • 10% (PY: 8%) 40
Slide 41: Tata Power Trading Company Limited
Tata Power Trading Company Limited TPTCL Sales (MU) FY09: Revenue – Rs 21.67 billion, PAT – Rs 0.07 billion, Dividend – 20% (PY: 20%) 16000 14000 12000 10000 8000 INR / MWh 6000 4000 2000 Spot High and Average price of power traded on Indian Energy Exchange 0 1-Feb 5-Feb 9-Feb 13-Feb 17-Feb 21-Feb 2
Slide 42: Part F: Other Businesses
Part F: Other Businesses 42
Slide 43: Strategic Electronics Division (SED)
Strategic Electronics Division (SED) • Revenues of Rs.101 cr (Mar 09) against Rs.55 cr during the previous year. • In March ’09 SED received its largest ever order of Rs. 182.46 cr to manufacture 16 Wheeled Launchers for the Akash Weapon System to be delivered to Indian Air Force in the next 33 mont
Slide 44: Tata BP Solar
Tata BP Solar • 51:49 JV between BP Solar and Tata Power • Market leader in Solar Photovoltaic technology in India with a turnover of Rs 1147 crores in FY09 • Nearly 75% of sales from exports largely to Europe and USA • Plant with Solar cell manufacturing Facility with installed capacity of 46 MW an
Slide 45: Part G: Financial Performance
Part G: Financial Performance 45
Slide 46: Standalone - Year Ended March 31, 2009
Standalone - Year Ended March 31, 2009 Rupee in Billions FY09 FY08 Operating Income 72.36 59.16 Operating Expenditure (61.17) (49.86) Operating Profit 11.19 9.37 Interest & Finance Charges (1.61) (1.36) Depreciation (3.29) (2.91) Other Income 4.88 4.66 Profit Before Tax 11.17 9.70 Provision for Taxe
Slide 47: Consolidated - Year Ended March 31, 2009
Consolidated - Year Ended March 31, 2009 Rupee in Billions FY09 FY08 Operating Income 175.88 108.91 Operating Expenditure (140.53) (88.02) Operating Profit 35.34 20.89 Interest & Finance Charges (5.32) (4.55) Depreciation / Impairment (9.37) (5.59) Other Income 3.99 4.79 Profit Before Tax 24.64 15.5
Slide 48: Funding Requirement
Funding Requirement Own Funds Debt (Rs.5,500 Crores) (Rs.18,100 Crores) • Internal accruals: Rs.2,800 Crores • Domestic loans through domestic • Remainder financial institutions, banks and – Dilution at subsidiary level capital markets – Disinvestment of various holdings • Foreign loans through exte
Slide 49: Tata Power – Financials (Standalone)
Tata Power – Financials (Standalone) Annual Sales (MU) Profit After Tax (In Billion Rs.) EPS (in Rs.) Net Worth (In Billion Rs.) 49
Slide 50: Tata Power – Financials (Consolidated)
Tata Power – Financials (Consolidated) Profit After Tax (In Billion Rs.) EPS (in Rs.) Net Worth (In Billion Rs.) 50
Slide 51: Dividend History
ld Dividend History TATA 50 - - 50 mam Dividend (Rs) 45 - man Earnings (Rs) y =#te Payout Ratio (%) FYO5 FYO6 FY07 FYO8 FYO9
Slide 52: Thank you
<p TATA Thank you We take pride in Lighting up Lives! cs