  1. Slide 1: Stakeholder Consultation Meeting

    Stakeholder Consultation Meeting Oakdale West Estate February 2020 1

  2. Slide 2: Overview

    Overview • Welcome and Introductions • Environmental Performance Update • Community Interactions Update • Safety Update • Approvals and Proposals Update • Upcoming Project Program • Stakeholder Feedback & Questions 2

  3. Slide 3: Welcome and Introductions

    Welcome and Introductions Project Team: Organisation Goodman AT&L Burton Robson Civil SLR Ersed Contractors Projects Consulting Role Proponent Project Manager & Oakdale West – Western North Stakeholder Environmental Contract Stage 1 Internal South Link Engagement Representative Superintendents Infra

  4. Slide 4: Site Plan

    Site Plan global environmental and advisory solutions S LR®

  5. Slide 5: Master Plan

    SSDA Estate Masterplan 7 = , WY) Y4 a Master Plan global environmental and advisory solutions

  6. Slide 6: Environmental Performance

    Environmental Performance 1. Sediment and Erosion – Significant Rain Event – on flow occurred to downstream receivers, with flows in line with predevelopment overland flows, with notification provided to downstream stakeholders – Sedimentation transported via overland flow within the creek to the no

  7. Slide 7: Community Interactions

    Community Interactions 1. Enquires made regarding noise experienced by residents during early morning deliveries of plant and machinery to the site – determined main source was noise of machinery moving from transport into the site. Protocols modified to address this issue. 2. Meetings held with res

  8. Slide 8: Safety

    Safety • No external safety incidents • Due to environmental conditions associated with heat and smoke haze, the health and safety of workers has been monitored closely. • The previous structures on site contained low levels of asbestos, which has now been removed in accordance with EPA and Council

  9. Slide 9: Approvals and Proposals

    Approvals and Proposals • Approval granted by the NSW State Government to increase hours of works for a limited area of the site (Lots 2A and 2B) temporarily. • Modifications 1, 2, and 3 to SSD 7348 still under assessment by the NSW State Government. 9

  10. Slide 10: Project Program – February/March

    Project Program – February/March Oakdale West Estate – Burton Contractors • Acceleration works to Lot 2B underway • Earthworks to Western Noise Bund nearing completion • Cut to Fill in Precinct 1 commenced • Cut to Fill in Precinct 2 commenced • Cut to Fill in Precinct 3 commenced • Placing material

  11. Slide 11: Communications and Consultation Channels

    Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: [email protected] • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E

  12. Slide 12: Stakeholder Feedback & Questions

    Stakeholder Feedback & Questions 12