Malaysia Marine & Heavy Engineering Holdings Bhd. · MYX:MHB
Malaysia Marine & Heavy Engineering Holdings Bhd — Q1 2019 Earnings Presentation
24 slides from Malaysia Marine & Heavy Engineering Holdings Bhd's earnings presentation, Apr 25, 2019

Slide 1: Quarterly IR Updates: 1st Quarter 2019 Financial Results & Updates
QUARTERLY IR UPDATES 1st Quarter 2019 Financial Results & Updates 25th April 2019 1

Slide 2: Disclaimer
Disclaimer This Presentation is not intended to form the basis of any investment decision with respect to Malaysia Marine and Heavy Engineering Holdings Berhad (MHB). Neither this presentation nor anything contained herein shall form the basis of, or be relied upon in connection with, any contract o

Slide 3: Contents
Contents • Business Highlights • Projects • Financials • Shareholding Information • Key Focus Areas 3

Slide 4: Key Highlights
Key Highlights FINANCIALS • Revenue of RM203.1 mil • Pre-tax loss of RM29.5 mil Heavy Engineering Unit (HEU) milestones: • Awarded Frame Agreement for EPC of fixed offshore structure works for PETRONAS for 6 years Marine Business Unit (MBU) milestones: • Awarded Master Service Agreement for Integrat

Slide 5: Contents
Contents • Business Highlights • Projects • Financials • Shareholding Information • Key Focus Areas 5

Slide 6: Bokor Phase 3 Re-Development CPP
Progress at 49.4% as at March 2019 Bokor Phase 3 Re-Development CPP 6

Slide 7: Gumusut-Kakap Phase II Extension Subsea Manifold
Progress at 99.7% as at March 2019 Gumusut-Kakap Phase II Extension Subsea Manifold 7

Slide 8: RAPID Package 3 Area 2
Progress at 99.9% as at March 2019 RAPID Package 3 Area 2 8

Slide 9: RAPID Package 14
Progress at 99.9% as at March 2019 RAPID Package 14 9

Slide 10: Pluto Water Handling Module
Progress at 15.5% as at March 2019 Pluto Water Handling Module 10

Slide 11: Tembikai NAG Offshore Wellhead Facilities
Progress at 47.2% as at March 2019 Tembikai NAG Offshore Wellhead Facilities 11

Slide 12: Notable Marine Repair Projects delivered in Q1 2019
Notable Marine Repair Projects delivered in Q1 2019 LNG Carrier Velikiy Novgorod LNG Carrier Galicia Spirit Vessel owner: Sovcomflot Vessel owner: Teekay Shipping Glasgow Ltd Deadweight: 93,486 tonnage Deadweight: 79,166 tonnage Job scope: Dry docking & repair (1st special survey) Job scope: Dry doc

Slide 13: Notable Marine Repair Projects delivered in Q1 2019 (2/2)
Notable Marine Repair Projects delivered in Q1 2019 (2/2) LNG Carrier Seri Amanah LNG Carrier Trinity Glory Vessel owner: Eaglestar Shipmanagement (L) Pte Ltd Vessel owner: “K” Line LNG Shipping (UK) Ltd Deadweight: 83.400 tonnage Deadweight: 79,605 tonnage Job scope: Afloat repair Job scope: Dry do

Slide 14: Dry Dock 3 (DD3)
Progress at 58.4% as at March 2019 Dry Dock 3 (DD3) 14

Slide 15: Contents
Contents • Business Highlights • Projects • Financials • Shareholding Information • Key Focus Areas 15

Slide 16: Income Statement, Sequential Quarter
Financial Updates Income Statement, Sequential Quarter Income Statement (RM 'm) 1Q 2019 4Q 2018 • Revenue Revenue 203.1 273.2 Heavy Engineering 125.4 224.0 • HEU – Lower revenue from ongoing projects Marine 77.7 49.2 • MBU – Higher revenue due to increase in LNG dry docking activities Operating Loss

Slide 17: Income Statement, Year-on-Year
Financial Updates Income Statement, Year-on-Year Income Statement (RM 'm) 1Q 2019 1Q 2018 • Revenue Revenue 203.1 188.3 • HEU – Higher revenue recognised from higher Heavy Engineering 125.4 111.3 Marine 77.7 77.0 progress of ongoing projects • MBU – Revenue was marginally higher mainly due to revenu

Slide 18: Balance Sheet
Financial Updates Balance Sheet Balance Sheet (RM 'm) Mar 2019 Dec 2018 Non-Current Assets 1,982.2 1,905.6 Inventories 5.1 5.6 • Total assets of RM3.2bil Receivables 676.1 648.0 Cash 517.2 601.5 Higher Non-Current Assets – PPE, mainly due to Others 20.5 20.5 investment in DD3 Total Assets 3,201.1

Slide 19: Backlog & Order Intake
Backlog & Order Intake RM (‘000) MHB Backlog 2,000 Backlog 1,500 1,000 1,273 500 1,023 864 629 785 CPP Bokor 0 Dec15 Dec16 Dec17 Dec18 Mar19 March 2019 RM864 mil New Order Intake RM (‘000) 2,000 Tembikai NAG 1,500 Sepat Phase 2A Besar F12 RAPID Woodside Pluto 1,000 CPOC Turret 500 1,145 652 Marine B

Slide 20: Contents
Contents • Business Highlights • Projects • Financials • Shareholding Information • Key Focus Areas 20

Slide 21: Shareholding Information & Share Price
Corporate Updates Shareholding Information & Share Price Share Price (RM) Technip 8.50% Technip 8.50% 2.00 1.80 Urusharta Urusharta Jamaah 6.60% Jamaah 6.60% 1.60 0.86 1.40 14/03/2019 PNB & PNB Unit PNB & PNB Unit As of As of 1.20 Trust Funds 1.84% Trust Funds 1.90% 0.55 31 Dec 2018 31 Mar 2019 EPF

Slide 22: Contents
Contents • Business Highlights • Projects • Financials • Shareholding Information • Key Focus Areas 22

Slide 23: Key Focus Areas
Key Focus Areas • HEU tenders worth ~ RM6.3 billion have been submitted as of March 2019 • Strategy & Initiatives Continue pursuing existing business of Marine & Heavy Engineering, seizing available floaters conversion opportunities and expanding marine capacity through additional dry dock Devel

Slide 24: Thank You
Thank You MALAYSIA MARINE AND HEAVY ENGINEERING HOLDINGS BERHAD (178821-X) Level 31, Menara Dayabumi, Jalan Sultan Hishamuddin, 50050 Kuala Lumpur, Malaysia T :+603 2273 0266 F :+603 2273 8916 Ww : www.mhb.com.my MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD (14558-P) (a wholly owned subsidiary of M
Source: Internet Archive copy of mhb.com.my
More decks from Malaysia Marine & Heavy Engineering Holdings Bhd.
Q4 2025 Earnings Presentation24 slides · Feb 23, 2026
Q3 2025 Earnings Presentation23 slides · Nov 14, 2025
Q2 2025 Earnings Presentation25 slides · Aug 22, 2025
Q1 2025 Earnings Presentation23 slides · May 27, 2025
Q4 2024 Earnings Presentation24 slides · Feb 19, 2025
Q2 2024 Earnings Presentation26 slides · Aug 21, 2024
All 35 Malaysia Marine & Heavy Engineering Holdings Bhd decks