Slide 1: PGE Investor Presentation
PGE Investor Presentation January, 2026

Slide 2: Agenda
Agenda • PGE at a glance • Summary of Q3 & 9M 2025 results and operations • Outlook for 2026 • Financials • PGE Group’s 2035 Strategy- Summary • Ongoing&completed investments • Market overview • Regulatory overview 2

Slide 3: PGE at a glance
PGE at a glance

Slide 4: PGE at a glance (2024)
PGE at a glance (2024) • Electricity net production 56.2 TWh 3.2 TWh in Renewables Segment • Installed electric capacity 18.9 GW • Wind farms 797 MW • Hydro 96 MW Power • 2 Lignite-fired power plants generation (Bełchatów and Turów) 7.2 GW • 3 Hard coal-fired power plants (Opole, Dolna Odra, Rybnik)

Slide 5: Our business segments 2024
Our business segments 2024 Key operational data a) of PGE Capital Group Renewables Gas-fired Conventional Railway Energy Generation Generation District Heating Distribution Services Supply 21 wind farms 43 photovoltaic power plants 5 conventional power Key assets of the 304.1 th km 18.4 thkm 29 run-

Slide 6: Our Vision: A leader in modern energy, flexibility, distribution and district heating
Our Vision: A leader in modern energy, flexibility, distribution and district heating #1 Flexible gas capacity #1 Energy distribution #1 Renewable energy #1 Clean district heating systems PGE by 2035 #1 Energy storage #1 Responsible Energy transition #1 Offer for Business Partners #1 Quality of resi

Slide 7: Strategic targets for 2035 by business segments
Strategic targets for 2035 by business segments Integrated Business Residential Distribution Renewables Gas Energy Energy Storage district heating Coal Energy Nuclear power TOTAL partners Customers systems +11 GW 100% #1 Location Key strategic 28 TWh 10 GW 18 GWh Asset #1 aspiration connected RES he

Slide 8: Value creation and CAPEX financing
Value creation and CAPEX financing Disciplined investment policy IRR >7.5% Investment discipline defining a selective approach to projects*, conservative macroeconomic assumptions and social responsibility. Adequate debt level NetDebt/EBITDA <3.5x Stable financial position supporting energy security

Slide 9: Potential for regular dividend payments
Potential for regular dividend payments Planned dividend payments upon achieving the following criteria: 1 Recurring net profit 2 Prospect of positive free cash flow for a minimum Addressing the issue of financing the operational gap of 2 years in coal-based energy segment (particularly in the ligni

Slide 10: PGE market position
PGE market position Electricity net generation Volume of distributed electricity Sales volume to final off-takers Other 5% Other PGE PGE 32% 22% Other 34% PGE 26% 36% Tauron 37% Tauron Orlen 18% 11% Tauron Orlen 7% Orlen 17% ENEA ENEA 10% ENEA 17% 13% 15% Data for 2024 10

Slide 11: Strategic goals 2035
Strategic goals 2035 Distribution Offshore Wind * Onshore Wind Flexible Gas Capacity Energy Storage Clean District Heating 4 GW 4 GW 4 GW CCGT plants 8 GWh BESS reducing CO2 Connected capacity 6 GW OCGT plants emissions 10 GWh Pumped new RES 11 GW Storage Hydro by 60% by 2030 new customers 12 GW 0.5

Slide 12: Summary of Q3 & 9M 2025 results and operations
Summary of Q3 & 9M 2025 results and operations

Slide 13: Key financial data
Key financial data [PLN m] Q3 2025 Q3 2024 y/y 9M 2025 9M 2024 y/y Sales 13 785 15 562 -11% 44 756 46 856 -4% EBITDA 2 644 2 458 8% 10 290 7 598 35% Recurring EBITDA 1 2 957 2 454 20% 10 560 7 291 45% EBIT 1 498 1 297 15% -2 024 4 156 - 1 Recurring EBIT 2 012 1 325 52% 7 544 3 983 89% 2 Net profit (

Slide 14: One-off items
One-off items Computation of recurring EBITDA and recurring EBIT: [PLN m] Q3 2025 Q3 2024 y/y 9M 2025 9M 2024 y/y Provision for restructuring of Dolna Odra power plant -233 0 - -233 0 - Write-off of strategic inventories -23 0 - -135 0 - Change of reclamation provision 0 -412 - -79 -20 295% Voluntar

Slide 15: Development of EBITDA by major value drivers Q3 2025
Development of EBITDA by major value drivers Q3 2025 (PLN m) Q3 2024 EBITDA RAPORTED 2 458 One-offs 4 - Price of electricity (PLN -1 080 m) (-89.8 PLN/MWh) Q3 2024 EBITDA RECURRING 1 2 454 - Electricity volume (PLN -422 m) (-0.7 TWh) Sales of electricity-Generation 1 502 + Price of CO2 (PLN +596 m)

Slide 16: Development of EBITDA by major value drivers 9M 2025
Development of EBITDA by major value drivers 9M 2025 (PLN m) 9M 2024 EBITDA RAPORTED 7 598 One-offs 307 9M 2024 EBITDA RECURRING 7 291 - Price of electricity (PLN -3 003 m) (-77.9 PLN/MWh) 1 - Electricity volume (PLN -263 m) (-0.4 TWh) Sales of electricity-Generation 3 266 + Price of CO2 (PLN +2 462

Slide 17: Recurring EBITDA Q3'25 – composition and development
Recurring1 EBITDA Q3’25 – composition and development (PLN m) 283 76 2 957 295 1 300 207 212 182 402 Energy Gas-fired District Renewables Coal Energy Distribution Railway Supply Other EBITDA generation Heating Services Q3 2025 402 182 212 207 1 300 295 283 76 2 957 Share in EBITDA (%) 14% 6% 7% 7% 4

Slide 18: Recurring EBITDA 9M'25 – composition and development
Recurring1 EBITDA 9M’25 – composition and development (PLN m) 1 536 321 10 560 952 3 924 1 451 600 1 371 405 Energy Gas-fired District Renewables Coal Energy Distribution Railway Supply Other EBITDA generation Heating Services 9M 2025 1 371 405 600 1 451 3 924 952 1 536 321 10 560 Share in EBITDA (%

Slide 19: Capital expenditures in 9M 2025
Capital expenditures in 9M 2025 PLN 466 m Coal Energy CAPEX Key projects PLN 256 m in 9M 2025 Railway Energy PLN 863 m Services 3% 6% District 11% Heating PLN 1 315 m Construction of CCGT unit in Rybnik PLN 1.2 bn Generation Gas-fired Generation 17% TOTAL CAPEX PLN 2 377 m Construction of CCGT unit

Slide 20: Key operating volumes
Key operating volumes Volumes: generation, sales, distribution [TWh] Q3 2025 Q3 2024 y/y 9M 2025 9M 2024 y/y Net electricity generation, by fuels: 12.58 13.16 -4% 40.09 40.67 -1% lignite 6.95 7.94 -12% 21.47 22.93 -6% incl. Turów 7 unit 0.39 0.47 -17% 1.25 1.30 -4% hard coal 2.87 2.87 0% 9.79 10.93

Slide 21: Electricity prices and CO2 cost
Electricity prices and CO2 cost Average realized wholesale price of electricity [PLN/MWh] Q3 2025 Q3 2024 y/y 9M 2025 9M 2024 y/y Coal Energy segment 487 585 -17% 498 581 -14% Gas-fired Generation segment 536 612 -12% 561 612 -8% District Heating segment 491 627 -22% 483 634 -24% Total (Coal En., Ga

Slide 22: Outlook for 2026
Outlook for 2026

Slide 23: Recurring EBITDA: outlook for 2026
Recurring EBITDA: outlook for 2026 2026 vs 2025 Main factors perspective − Lower margin at pumped-storage power plants Renewables − Lower revenues from certificates Gas-fired + Expected higher margin on sales of electricity Generation − Expected lower revenues from balancing capacities market − Expe

Slide 24: Financials
Financials

Slide 25: Cash from operations, investments and net debt
Cash from operations, investments and net debt Consolidated Cash Flows . . . [PLN m] Q3 2025 Q3 2024 9M 2025 9M 2024 Operating CF 1 315 8 514 13 448 14 619 Investing CF -2 971 -2 692 -7 171 -7 394 Financial CF 1 188 -598 3 022 -4 384 Change of cash and equivalents -468 5 224 9 299 2 841 Consolidated

Slide 26: Debt – data of September 30, 2025
Debt – data of September 30, 2025 Gross debt and net debt* (in PLN million) 20 000 Gross debt Net debt 15 000 10 000 5 000 0 Mar-20 Jun-20 Sep-20 Dec-20 Mar-21 Jun-21 Sep-21 Dec-21 Mar-22 Jun-22 Sep-22 Dec-22 Mar-23 Jun-23 Sep-23 Dec-23 Mar-24 Jun-24 Sep-24 Dec-24 Mar-25 Jun-25 Sep-25 -5 000 Currenc

Slide 27: Available financing and debt maturity
Available financing and debt maturity Drawn debt and availability of external financing (in PLN m) as of September 30, 2025 18 000 Drawn Undrawn 16 000 14 000 12 000 10 000 8 000 6 000 4 000 2 000 0 Environmental EBRD EIB Current account Domestic bonds' EMTN program Revolving loans BGK BGK - KPO* lo

Slide 28: Stable finances
Stable finances Q3 2025 H1 2025 Gross Debt (PLN bn) 13.9 12.9 Net debt (PLN bn) 0.4 -1.0 Net Debt/LTM EBITDA 0.02x -0.07x Debt position Net Economic Financial Debt (PLN bn) 15.5 14.6 NEFD/ LTM EBITDA recurring 1.10x 1.07x Net Debt/Equity 0.01x -0.03x MOODY’S FITCH Long-term company rating (IDR) Baa1

Slide 29: Sources of financing for the investment programme (1/2)
Sources of financing for the investment programme (1/2) New Gas Capacities District Heating Distribution REVENUE STREAMS • Capacity Market • Sale of electricity and heat • Regulated revenue • Balancing capacities • Capacity Market • Non-tariff revenues • Energy market • Balancing capacities FINANCIN

Slide 30: Sources of financing for the investment programme (2/2)
Sources of financing for the investment programme (2/2) Offshore Onshore RES Energy Storage REVENUE STREAMS • Contract for Difference • Sale of electricity (i.a. wholesale market and PPA) • Capacity Market • Sale of electricity • Guarantees of origin • Balancing capacities • Energy market FINANCING

Slide 31: PGE Group's 2035 Strategy - Summary
PGE Group’s 2035 Strategy - Summary 31

Slide 32: Target results of PGE Group Strategy by 2035
Target results of PGE Group Strategy by 2035 30 bn PLN 28 TWh 235 bn PLN EBITDA RENEWABLE ENERGY TOTAL CAPEX #ValueCreation #CleanEnergy #EnergySecurity 10 GW 75% +11 GW FLEXIBLE GAS CO2 EMISSIONS RES CONNECTION CAPACITY POWER PLANTS DECREASE TO SMART GRID #Flexibility #Responsibility #ReliableDistr

Slide 33: PGE defines Security as Flexibility enabling renewable development
PGE defines Security as Flexibility that enables further development of renewable energy sources while ensuring the stability of the power system Volatility on both the supply and demand sides is increasing in the short and medium term. This requires greater flexibility in both energy generation and

Slide 34: Solutions transferring market changes into price effects for Customers
PGE will introduce solutions that transfer the benefits of market structure changes into tangible price effects for active Customers The development of renewable energy sources is contributing to a decline in wholesale prices, but increased electricity price volatility poses a challenge for many mar

Slide 35: 2035 Strategy addresses growing volatility of business environment
PGE Group’s 2035 Strategy – Executive Summary The PGE Group’s 2035 Strategy to addresses the growing volatility and unpredictability of the business environment New technologies are redefining business Aspirations and regulatory requirements are models, requiring continuous adaptation and influencin

Slide 36: Mission: Providing Energy for a Secure Future
PGE Group’s 2035 Strategy – Executive Summary Mission: Providing Energy for a Secure Future Energy supply security We ensure stable energy supplies thanks to flexible sources, smart grid infrastructure and energy storage facilities. By supporting the competitiveness Group’s value creation of Poland'

Slide 37: Smart grid determining a new energy system architecture
PGE Group’s 2035 Strategy – Executive Summary The development of smart grid is determining a new energy system architecture A reasonable balance, increased flexibility and the ability to integrate renewable energy sources are essential for a secure and successful energy transition. Onshore & Flexibl

Slide 38: The flexibility portfolio as a driver of diversified revenue streams
The flexibility portfolio as a driver of diversified revenue streams To ensure the secure and stable functioning of the Polish Power System, the Transmission System Operator determines the necessary power configuration using advanced tools. Why flexibility? Diversified revenue streams Illustrative s

Slide 39: Role of the PGE Group's segments
PGE Group’s 2035 Strategy – Executive Summary Role of the PGE Group’s segments Integrated district Residential Distribution Renewables Gas energy Energy Storage Coal Energy Business partners Nuclear power heating systems customers +11 GW 100% #1 Location Key strategic 28 TWh 10 GW 18 GWh Asset #1 as

Slide 40: #1 Energy distribution
#1 Energy distribution Smart grid connection availability more than doubled Group PGE Our motivation: PGE S.A. For whom: Strategic outlook Investment financing Supporting the growth of renewables Strategic and ownership supervision Prosumers Development of distributed generation PGE Dystrybucja (PV,

Slide 41: Rational development of the distribution segment
Rational development of the distribution segment as a foundation for the PGE Group’s value growth PGE Group's investments will be focused on increasing connection capacity, observability and controllability, as well as on automating grid operation. Operational efficiency and alignment of development

Slide 42: #1 Renewable Energy
#1 Renewable Energy 26 TWh of green electricity from offshore and onshore RES Grupa PGE Our motivation PGE S.A. For whom Strategic outlook Investment financing Decarbonisation of the generation mix and Sourcing and managing partnerships Energy consumers maintenance of the position as the leading Sal

Slide 43: Clean energy for economic competitiveness and resource independence
Clean energy for economic competitiveness and resource independence Affordable energy is key to business competitiveness, clean transport and efficient district heating. PGE Group's investments and competencies will allow Poland to reduce its reliance on fuel imports and meet its emission reduction

Slide 44: #1 Flexible gas capacity
#1 Flexible gas capacity 10 GW of dispatchable capacity, enabling a safe energy transition Our motivation PGE S.A. For whom Strategic outlook Investment financing (including project finance) Maintaining the position of the leading System operator Developing an auction strategy electricity supplier t

Slide 45: PGE Group's aspirations regarding gas energy
PGE Group's aspirations regarding gas energy The revenue streams of the gas-fired units will be based on the capacity market, electricity sales, and the provision of balancing services. Planned installed capacity 10.0 CCGT plants OCGT plants Under construction Depending on 4.9 the new capacity 4 GW

Slide 46: #1 Energy Storage
#1 Energy Storage 18 GWh capacity for RES integration and market balancing Grupa PGE Our motivation PGE S.A. For whom Strategic outlook Investment financing Sustaining the position as the leading Transmission System Operator Commercial storage management electricity supplier to the Polish Power Syst

Slide 47: Broad exposure to available energy storage technologies
Broad exposure to available energy storage technologies Energy storage facilities will enable reliable short-term system balancing and support the continued integration of renewable energy sources. Through price arbitrage opportunities, they can also contribute to the stabilisation of electricity an

Slide 48: #1 Clean district heating
#1 Clean district heating Leader in integrated, efficient district heating systems Group PGE Our motivation PGE S.A. For whom Strategic outlook Heat consumers Keeping the local heat markets’ leadership Financing of investments Reliability of heat supply Optimising gas contracting sources Monetising

Slide 49: District heating on the road to climate neutrality
District heating on the road to climate neutrality A roadmap is being developed for each heating system location to achieve climate neutrality while maintaining the price competitiveness of district heating. Structure of district heating production Energy efficiency of Modernisation and Scoping effe

Slide 50: Investments in transformation and modernisation of district heating systems
Investments in the transformation and modernisation of district heating systems The transformation of district heating assets will allow us to achieve climate neutrality while maintaining price attractiveness and security of supply. Average annual EBITDA 2.8 Transformation of Modernisation and devel

Slide 51: A responsible approach to the transition from coal energy
A responsible approach to the transition from coal energy Change in Decline in coal Need to maintain Evolution of the Circular generation mix energy demand power in the system competence profile Economy • Competitiveness of coal- • The need for cost • Coordination of available • A qualified, experie

Slide 52: Nuclear energy as a long-term strategic option
Nuclear energy as a long-term strategic option For the period beyond 2035, the PGE Group will continue to develop additional strategic options, seeking the most effective pathways to achieve the Net Zero scenario. The key criterion will remain the creation of Group value based on zero-emission gener

Slide 53: Financial effects of the Strategy
Financial effects of the Strategy 53

Slide 54: Consistent approach to value creation and investment financing
PGE Group’s 2035 Strategy – Executive Summary Consistent approach to value creation and investment financing Disciplined investment policy IRR >7.5% Investment discipline defining a selective approach to projects*, conservative macroeconomic assumptions and social responsibility. Adequate debt level

Slide 55: Balanced capital expenditure structure supported by regulated revenues
PGE Group’s 2035 Strategy – Executive Summary A balanced capital expenditure structure supported by stable, regulated revenues and secured opportunities for profitable growth. CAPEX by monetisation mechanisms Energy and Tariffs capacity markets Electricity sales Distribution CHP bonus 39.0% 39.0% Th

Slide 56: Development programme based on regulated revenues and RES growth
An ambitious development programme based on regulated revenues and building growth potential in RES and flexibility An investment programme focused on grid infrastructure, renewables Approximately 25% of CAPEX consists of acquisitions and and flexibility. development options, which will be pursued d

Slide 57: CAPEX structure and expected evolution of EBITDA structure
PGE Group’s 2035 Strategy – Executive Summary CAPEX structure and expected evolution of EBITDA structure Around 25% of CAPEX is made up of acquisitions and development EBITDA secured by distribution and regulatory mechanisms, with growth options, which will be implemented depending on the financial

Slide 58: EBITDA evolution towards regulated segments, renewables and flexibility
EBITDA evolution towards regulated segments, renewables, and mechanisms that reward flexibility The new strategy creates strong EBITDA structure (PLN bn) financial foundations for long-term growth beyond 2035 PLN 30 bn Others 4% 4% Sales 6% Railway services PLN 17 bn 26% Distribution 7% 2% 7% 10% En

Slide 59: Business profile transformation and ability to finance growth
Business profile transformation will give the PGE Group greater ability to finance its growth The Group aims to improve its risk profile by adopting new growth At present the PGE Group maintains a low net debt-to-EBITDA ratio financing models, enabling a safe increase in net debt levels while compar

Slide 60: Potential for regular dividend payments
Potential for regular dividend payments Dividend payments planned upon achieving the following criteria: 1 Recurring net profit 2 Prospect of positive free cash flow Addressing the issue of financing the operational gap for a minimum of 2 years in coal-based energy segment (particularly in the ligni

Slide 61: ESG as a source of stakeholder value
ESG as a source of stakeholder value The strategic goals of the PGE Group are adopted with the aim of positively impacting the surroundings. Integrating the ESG aspects into management practices ensures complete alignment with sustainability principles. ENVIRONMENTAL SOCIAL GOVERNANCE Minimising the

Slide 62: PGE's transition on the path to Net Zero
PGE’s transition on the path to Net Zero The implementation of flexibility initiatives will enable PGE Group's electricity generation mix PGE Group to responsibly expand its portfolio of 58 renewable sources. Strategic options Coal Gas Onshore RES TWh Offshore Energy Storage CO2 emissions – BAU scen

Slide 63: Ongoing & completed investments
Ongoing & completed investments

Slide 64: PGE offshore wind projects portfolio
PGE offshore wind projects portfolio Ownerships: Baltica 1 (100% PGE) Baltica 1+ (100% PGE) Baltica 2 (50% PGE, 50% Ørsted) Baltica 2+ (50% PGE, 50% Ørsted) Baltica 3 (50% PGE, 50% Ørsted) Baltica 5 (~66% PGE, ~34% ENEA) Baltica 7 (~55% PGE, ~45% Tauron) 64 Baltica 9+ (100% PGE)

Slide 65: Baltica 2 project in progress
Baltica 2 project in progress Annual generation: 5.4 TWh Installation Terminal T5 in Gdańsk • Base port for pre-assembly of Installation port in Roenne turbine components – rotor nacelle assemblies, blades and • Base port for monopiles towers • Alternative port for pre-assembly of turbine components

Slide 66: Financing Structure of the Baltica 2
Financing Structure of the Baltica 2 Loan from BGK bank, approx. PLN Ørsted A/S 3.9 bn - financing PGE SA from National Recovery and Resilience Plan for equity contribution1 approx. PLN 11.1 bn HoldCo Ørsted Project financing from bank HoldCo PGE Ørsted Baltica 2 Holding sp. z Finance consortium (25

Slide 67: CfD for the Baltica 2, Baltica 3, FEW Baltic II
CfD for the Baltica 2, Baltica 3, FEW Baltic II Offshore wind support based on CfD scheme Projects of I phase of suport scheme 1. Secured CfD strike price: PLN 319.60/MWh (EUR 71.82/MWh) (in 2021 prices) 2. Annual indexation with the consumer price index (CPI) for the previous year or inflation targ

Slide 68: Baltica 2 project in progress
Baltica 2 project in progress Annual generation: 5.4 TWh Installation Terminal T5 in Gdańsk • Base port for pre-assembly of Installation port in Roenne turbine components – rotor nacelle assemblies, blades and • Base port for monopiles towers • Alternative port for pre-assembly of turbine components

Slide 69: Offshore wind – 2025 auction
Offshore wind –2025 auction ▪ The Act of November 27, 2024 amending law on promotion of generation of electricity in offshore wind farms stipulates different prices for different locations of maritime areas. ▪ Ministry of Climate and Environment published in January 2025 ordinance on maximum electri

Slide 70: 1st gas power plant in Poland - Gryfino commissioned in 2024
1st gas power plant in Poland - Gryfino commissioned in 2024 Gross capacity: 2x683 MWe Net efficiency : approx. 63% Fuel: gas Net emission rate : <0.35 t CO2/MWh Contract value (net): PLN 3.70 billion LTSA value: PLN 1.03 billion (12 years) Commissioning date: August - October 2024 Key dates and eve

Slide 71: CCGT Rybnik – alternative for coal units
CCGT Rybnik – alternative for coal units Capacity: 882 MWe General efficiency of the unit: approx. 64% Fuel: natural gas Net emission rate : <0.35 t CO2/MWh Contract value (net): PLN 3.15 billion LTSA value (net): PLN 762.5m (12 years) Commissioning date: Q1 2027 Ecological effects – assumed decreas

Slide 72: New Czechnica CHP project commissioned May 2025
New Czechnica CHP project commissioned May 2025 Capacity: 179 MWe and 315 MWt + heat accumulator 13000m3 General efficiency of the unit: approx. 85% Fuel: natural gas Net emission rate : <0.35 t CO2/MWh Contract value (net): PLN 1.16 billion* LTSA value (net): PLN 25m & EUR 20.7m (103 months) Commis

Slide 73: Development of PV farms
Development of PV farms – Focus on completion of rational projects on advanced stage Strategic objective: 1 GW in 2035 Ca. 4 000 ha of land secured to develop >2GW Projected growth – own developments + acquisition of projects Project managed by PGE Energia Odnawialna S.A. Installed capacity – 231 MW

Slide 74: Market overview
Market overview

Slide 75: Polish Power System - installed capacity
Polish Power System- installed capacity Installed capacity in the Polish Energy System (MW) December 2024 • Continuous development of new RES capacities: • PV +4 411 MW y/y • (including +1 363 MW y/y prosumers installations) • Wind +721 MW y/y PV 21 157 Biomass 970 Wind 10 140 Biogas 306 other 707 N

Slide 76: Polish Power System - generation mix
Polish Power System- generation mix Share in electricity generation of particular technologies • Total gross generation (%) of generation in 2024 +2% y/y on higher demand for electricity and natural gas lower import of electricity 12% other • Conventional sources 2% -2% y/y • Lignite +4% y/y lignite

Slide 77: Electricity market - balance of energy
Electricity market - balance of energy Domestic consumption and generation [GWh] Q3 2024 Q3 2025 16.5 Generation Electricity consumption Domestic consumption -4.4% (-1.75 TWh y/y) 16.0 15.5 Balance of foreign exchange 15.0 (+1.06 TWh y/y) 14.5 14.0 Electricity generation -1.7% (-0.69 TWh y/y) 13.5 1

Slide 78: Electricity market - prices
Electricity market - prices BASE Forward next year and CO2 prices Q3 2025 2,000 [PLN/MWh] RTT Y+1 Average BASE_Y-26 1,800 Average RTT Y+1 1,600 CO2 • Price of BASE_Y-26 contract 1,400 throughout the Q3 2025 at level 410-430 PLN/MWh. 1,200 • Current prices on forward 1,000 market at approx. 445 800 P

Slide 79: Regulatory overview – Capacity Market & Balancing Capacity Market
Regulatory overview – Capacity Market & Balancing Capacity Market

Slide 80: Capacity market derogation for coal units 2025-2028
Capacity market derogation for coal units 2025-2028 ▪ European Parliament amended in June 2024 electricity market regulations 2019/942 and 2019/943 as regards derogation for the generating units that emits more than 550 g of CO2 per kWh (including coal generation) for the capacity mechanism. ▪ Derog

Slide 81: Capacity market – results of auctions
Capacity market – results of auctions PGE contracts 2029 2030 Coal H2 2025 Coal 2026 47 44 63 349 2 210 1435 1 399 2 559 2 174 138 MW MW MW MW 947 1 098 2 111 2 557 incl. incl. Żarnowiec BESS (17y) 138 MW OCGT Rybnik 549 MW (15y) Gryfino BESS (17y) 121 MW OCGT Gryfino 549 MW (15y) 2026 2027 2028 4 0

Slide 82: Reform of balancing market
Reform of balancing market ▪ Implementation of balancing market reform (from June 14, 2024): ▪ Implementation of balancing capacity market - pricing for ancillary services set in daily auctions. ▪ Generators responsible for implementation of notified production plans and covering of start-up costs ▪

Slide 83: Regulatory overview – Offshore Wind
Regulatory overview – Offshore Wind

Slide 84: Offshore wind support scheme
Offshore wind support scheme Phase I Phase II Administrative decision Auctions (maximum capacity) of the President of ERO. MW Decision of the European Commission on acceptance of the state aid. 2 000 Drafted total of 2 000 17.9GW in Applications should be years submitted by March 31, 4 000 2021-2031

Slide 85: Offshore wind – CFD price-setting process
Offshore wind – CFD price-setting process Maximum settlement Phase II Phase I price of the electricity Minister of Climate and Maximum settlement price Maximum bid price for Environment/Minister of auction of the electricity State Assets Application for decision on the -technical and economic parame

Slide 86: Offshore wind – settlement of the CFD contract
Offshore wind – settlement of the CFD contract ▪ Contract granted for 25 years (counted from the first feeding into the grid electricity from the offshore windfarm). ▪ Electricity volume limited up to 100 000 hours of generation at full capacity. Indicated load factor assuming 25 years of generation

Slide 87: Regulatory overview
Regulatory overview

Slide 88: Fundamentals of the distribution business (PGE Dystrybucja S.A.)
Fundamentals of the distribution business (PGE Dystrybucja S.A.) RAB (with RAB-AMI) development1 (PLN m) 25 635 24 058 21 570 19 806 RAB 2023 RAB 2024 RAB 2025 RAB 2026 2023 2024 2025 2026 1 Based on a Tariff WACC: 7.48% 7.48% 7.48% 7.48% 2 Including AMI, regulatory indicator (WR) and reinvestment p

Slide 89: Fundamentals of the distribution business (Railway Energy Services)
Fundamentals of the distribution business (PGE Energetyka Kolejowa Operator sp. z o.o.- Railway Energy Services Segment) Regulated Asset Base RAB (PLN m) 4 701 4 776 4 221 3 559 RAB 2023 RAB 2024 RAB 2025 RAB 2026 2023 2024 2025 2026 WACC: 5.78% 8.97% 9.81% 8.48% 89

Slide 90: Tariffs in district heating – heat generation
Tariffs in district heating – heat generation Tariffs approved by the Energy Regulatory Office for 12-month period Non-CHP plants CHP plants Full cost method Simplified method* (Planned costs and revenues as an input) (Initial price calculated for year 0 adjusted every year) Yearly adjustment ERO pu

Slide 91: Cogeneration Support Scheme
91 Cogeneration Support Scheme Support length <1 MW <1-50 MW >=50 MW 15 years from the first EXISTING CHP certificate Individual guaranteed MODERNISED 5-6-7 years from the Guaranteed premium premium (CAPEX >=50%*) modernisation SIGNIFICANTLY Enrollment on 15 years after the MODERNISED Pay-as-bid auc

Slide 92: Price-freeze mechanism 2023-2025
Price-freeze mechanism 2023-2025 (simplified, illustrative only) EFFECT ON SUPPLY COVID-19 EFFECT ON GENERATION FUND (abandoned from 2024) Compensation for supply companies Revenue surplus Price cap for eligible retail PRICE Maximum price consumers DIFFERENCE allowed for power PAYMENT generators FUN

Slide 93: Disclaimer
Disclaimer This presentation has been prepared by the management of PGE Polska Grupa Energetyczna S.A. (the “Company” or “PGE”) and other entities. This presentation does not constitute or form part of and should not be constructed as, an offer to sell, or the solicitation or invitation of any offer

Slide 94: Investor Relations contacts
Investor Relations contacts Paweł Bujnowski Krzysztof Dragan Stanisław Ozga CFA Director, IR and ESG [email protected] [email protected] [email protected] Mob: +48 887 663 402 Mob: +48 601 334 290 Mob: +48 887 171 324 94

Slide 95: Thank you
Thank you
Source: Internet Archive copy of gkpge.pl
More decks from PGE Polska Grupa Energetyczna S.A.
FY2025 Earnings Presentation21 slides · Apr 16, 2026
FY2025 Earnings Presentation21 slides · Apr 16, 2026
Q4 2025 Earnings Presentation53 slides · Apr 15, 2026