  1. Slide 1: Thai Oil Public Company Limited KM Session: Energy Recovery Unit

    -Use only for KM Session- -1- Thai Oil Public Company Limited KM Session : Energy Recovery Unit 6 February 2019 Time : 14.00 - 16.00 hrs. Venue : Ballroom @ The Okura Prestige Hotel Bangkok

  2. Slide 2: Disclaimer

    -Use only Strictly for Confidential KM Session- -2- Disclaimer The information contained in this presentation is intended solely for your personal reference. Please do not circulate this material. If you are not an intended recipient, you must not read, disclose, copy, retain, distribute or take any

  3. Slide 3: Agenda

    -Use only Strictly for Confidential KM Session- -3- Agenda Rationale & Overview of Transaction Key Terms of Agreement Technical Aspect of ERU Way Forward

  4. Slide 4: Rationale & Overview of Transaction

    -Use only for KM Session- -4- Rationale & Overview of Transaction

  5. Slide 5: Rationale & Timeline

    -Use only Strictly for Confidential KM Session- -5- Rationale & Timeline Benefits to TOP Why GPSC ? • Reduce overall CAPEX of CFP Project • Expert and skillful in power business • Reduce D/EBITDA ratio and increase liquidity • Understands the operation of oil refinery for future investment petrochem

  6. Slide 6: Overview of Transaction

    -Use only for KM Session- -6- Overview of Transaction Construction Phase Asset Sales and 1 Purchase Agreement “APA” Project Co. Seller Acquire ERU after construction Purchaser Operation Phase 2 Project Co. 4 Fuel and Utilities Supply Power Purchase Agreement “FUSA” Agreement “PPA” The purchasing pri

  7. Slide 7: Key Terms of Agreement

    -Use only for KM Session- -7- Key Terms of Agreement

  8. Slide 8: Key Terms of Asset Sales and Purchase Agreement (APA)

    -Use only for KM Session- -8- 1 Key Terms of Asset Sales and Purchase Agreement (“APA”) Seller Project Co. Purchaser CFP COD Q1 2023 Project Timeline EPC Commencement (RFSU) (RFPT) (PAC) Date Ready for Start- Ready for Q3 2023 up of CFP Performance Test Provisional of CFP Acceptance of CFP Contract

  9. Slide 9: Key Terms of Fuel and Utilities Supply Agreement (FUSA)

    -Use only for KM Session- -9- 2 Key Terms of Fuel and Utilities Supply Agreement (“FUSA”) Fuel and Utilities Delivery Project Co. Owner/Buyer Supply fuel and utilities necessary for ERU operation Supplier e.g. Pitch, Steam, Others Contract Term Initial Term 25 years Extended Term ~5 years Closing Da

  10. Slide 10: Key Terms of Operation and Maintenance Services Agreement (OMA)

    -Use only for KM Session- -10- 3 Key Terms of Operation and Maintenance Services Agreement (“OMA”) Provide O&M Service Operator Project Co. Owner Obtaining and maintaining operation and maintenance of ERU and related facilities (Installed capacity 250 MW) Pitch management including waste management

  11. Slide 11: Key Terms of Power Purchase Agreement (PPA)

    -Use only for KM Session- -11- 4 Key Terms of Power Purchase Agreement (“PPA”) Products Delivery Project Co. Seller Sell electricity, steam, condensate water and sulfuric acid to CFP Purchaser Contract Term Initial Term 25 years Extended Term ~5 years Closing Date Key Terms of PPA Contracted Capacit

  12. Slide 12: Key Terms of Land Sub-Lease Agreement & Novation Agreement

    -Use only for KM Session- -12- Key Terms of Land Sub-Lease Agreement & Novation Agreement 5 Land Sub-Lease Agreement Summary 6 Novation Agreement Summary Project Co. TOP transfers Rights, Benefits and Obligation in relation to ERU to GPSC Area : Approx. 36 Rai (Dhanarak Land) • EPC • Licensor Rental

  13. Slide 13: Technical Aspect of ERU

    -Use only for KM Session- -13- Technical Aspect of ERU

  14. Slide 14: CFP Project & ERU Asset

    -Use only Strictly for Confidential KM Session- -14- CFP Project & ERU Asset LPG Tops ISOM SRU Sulfur 5 Naphtha HDT-3 CCR-1/2 Platformate PX/BZ TPX HDT-4 Hy. Naph CDU-3 4 180 kbd Crude LPG LPG Kerosene Tops KMT-1/2 Lt.Naph 400 kbd Isomerate Gasoline New HDS-2/3 CDU-4 Diesel Jet/Kero 220 kbd HDS-4 Di

  15. Slide 15: Scope of ERU

    -Use only Strictly for Confidential KM Session- -15- Scope of ERU ERU • Electricity 250 MW (internal use 50 MW, supply to CFP 180 - 200 MW) • Steam to CFP 174 TPH Scope of ERU Backup Electricity from EGAT Flue Gas Treatment (3 units) ESP SNOX Steam Fuel Gas = 540 KgPH Fly Ash 16 TPD NG = 6 KgPH MP =

  16. Slide 16: Way Forward

    -Use only for KM Session- -16- Way Forward

  17. Slide 17: Way Forward

    -Use only Strictly for Confidential KM Session- -17- Way Forward Feb Q3’23 Jan’19 Mar’19 Apr’19 2020-2023  TOP BoD approved to  KM Session with  TOP AGM to  Provisional carve out ERU analysts and bankers consider and Acceptance &  Conference call with  Local & foreign approve to enter Transfer