Companhia Energetica de Minas Gerais SA · BMFBOVESPA:CMIG3

Companhia Energetica de Minas Gerais SA — Investor Presentation (March 2011)

143 slides from Companhia Energetica de Minas Gerais SA's investor presentation, March 2011

  1. Slide 1: Successful Strategy

    Slide 1: Successful Strategy

    Successful Strategy Performance reflects balanced portfolio structure March, 2011

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    Disclaimer Some statements and estimates in this material may represent expectations about future events or results that involve risks and uncertainties known and unknown. There is no guarantee that the events or results referred to in these expectations will occur. These expectations are based on p

  3. Slide 3: Brazil's Leading Power Utility

    Slide 3: Brazil's Leading Power Utility

    Brazil’s Leading Power Utility Integrated Growth in Market cap Role in Power EBITDA of US$ industry Utility in 2004-09 11.03(1) B. Brazil (2) Leading #1 +90% #3 consolidator In the Power Industry since 1952 (1) As of March 2nd, 2011 (2) In the Power Industry 3

  4. Slide 4: Cemig: Strength in Numbers

    Slide 4: Cemig: Strength in Numbers

    Cemig: Strength in Numbers (1) Number of power plants 66 Total installed capacity 6,896 MW Locations in Minas Gerais State 5,415 Size of concession area vs. France Larger Electricity Distribution lines 474,559 km Power Transmission lines 8,768 km (1) As of September 30, 2010 4

  5. Slide 5: Cemig at a Glance

    Slide 5: Cemig at a Glance

    Cemig at a Glance ● Based in State of Minas Gerais, controlling shareholder – growing throughout Brazil and Chile ● Strong financial profile 2009 – Net revenues: R$ 11.7B – EBITDA: R$ 4B ● Highest liquidity in the sector – listed on 3 stock exchanges New York, São Paulo, Madrid – More than 114,000 s

  6. Slide 6: The Cemig Story – Agenda

    Slide 6: The Cemig Story – Agenda

    The Cemig Story – Agenda The positioning The performance The growth 6

  7. Slide 7: Cemig is Uniquely Positioned

    Slide 7: Cemig is Uniquely Positioned

    Cemig is Uniquely Positioned 1 The Brazil advantage 2 Unmatched scale 3 Diversified portfolio 4 Leader in renewable energy 5 Strong governance 7

  8. Slide 8: An Emerging Powerhouse Economy

    Slide 8: An Emerging Powerhouse Economy

    1 BRAZIL ADVANTAGE An Emerging Powerhouse Economy Latin American economy #1 Ranking of economy in world #7 GDP 2010 US$2.1 Trillion GDP growth 2010 7.5% Population 191M Power industry net revenue - 2010 >US$145 Billion Investment grade by Moody’s, Fitch and S&P 8

  9. Slide 9: Largest Integrated Utility in Brazil

    Slide 9: Largest Integrated Utility in Brazil

    2 UNMATCHED SCALE Largest Integrated Utility in Brazil #1 #3 #3 #1 Electricity Largest power Largest power Integrated + + distributor* transmission generation utility group group Power Generation RR AP Power Generation (under construction) Power Transmission AM MA Power Transmission (under construct

  10. Slide 10: Diversified, Low Risk Business Portfolio

    Slide 10: Diversified, Low Risk Business Portfolio

    3 DIVERSIFIED Diversified, Low Risk Business Portfolio Breakdown of EBITDA (2009) 1% 5% 30% 51% 13% Power Generation Power Transmission Electricity Distribution Natural gas Others Most of revenues are inflation protected 10

  11. Slide 11: Leader in Renewable Hydro Power Energy

    Slide 11: Leader in Renewable Hydro Power Energy

    4 RENEWABLE LEADER Leader in Renewable Hydro Power Energy Power Generation by Source 8% 5,7% 16% 16% 76,9% 98% 60% 2.5% 14,9% 2% World 06 Brazil 09 Cemig 10 Fossil Source Fuels Nuclear Hydro Others 11

  12. Slide 12: Best-in-Class Corporate Governance

    Slide 12: Best-in-Class Corporate Governance

    5 GOVERNANCE Best-in-Class Corporate Governance Minas Gerais, controlling shareholder – a positive influence – one of fastest growing, investor-friendly states in Brazil – growth and profitability interest aligned with minority shareholders – 6 from a total of 14 members are appointed by minority sh

  13. Slide 13: The Cemig Story – Agenda

    Slide 13: The Cemig Story – Agenda

    The Cemig Story – Agenda The positioning The performance The growth 13

  14. Slide 14: Growth in EBITDA

    Slide 14: Growth in EBITDA

    Growth in EBITDA R$ billion 7% CAGR 4,1 4,1 4,0 EBITDA Margin: 33% 3,1 3,2 3,0 2005 2006 2007 2008 2009 2010* (*)Up to September 30, 2010 14

  15. Slide 15: Net Income Continues to Expand

    Slide 15: Net Income Continues to Expand

    Net Income Continues to Expand R$ million 3% CAGR 1.887 1.861 1.719 1.744 1.662 Net Margin:14% 1.263 2005 2006 2007 2008 2009 2010* (*)Up to September 30, 2010 15

  16. Slide 16: Attractive and Secure Dividend Payout

    Slide 16: Attractive and Secure Dividend Payout

    Attractive and Secure Dividend Payout (1) Dividend Payout Dividend Yield (% of Net Income) (%) 80 9 50 6 50 50 5 5 2006 2007 2008 2009 2006 2007 2008 2009 (1) Proposal for 2009 Net Income distribution was approved : • Ordinary Dividends of R$ 931 million - Dividends per share: R$1.50 • Stock Dividen

  17. Slide 17: Strong Balance Sheet to Support Growth

    Slide 17: Strong Balance Sheet to Support Growth

    Strong Balance Sheet to Support Growth (September 30th, 2010) Net debt to EBITDA 2.1X Debt in foreign currency(*) < 2% Cash on hand R$4.2B Net Revenue 2010 R$ 9.1B *Net of financial hedging 17

  18. Slide 18: EBITDA guidance

    Slide 18: EBITDA guidance

    EBITDA guidance EBITDA guidance(1) 2010-2014 R$ million (upper + lower limits of range) 6000 Year Lower limit Upper limit 5250 2010 3,825 4,400 2011 4,773 5,491 4500 2012 4,832 5,560 2013 4,483 5,158 3750 2014 4,879 5,614 3000 Consolidated figures include values from Holding and 2010 2011 2012 2013

  19. Slide 19: The Cemig Story – Agenda

    Slide 19: The Cemig Story – Agenda

    The Cemig Story – Agenda The positioning The performance The growth 19

  20. Slide 20: Clear Long Term Goals

    Slide 20: Clear Long Term Goals

    Clear Long Term Goals Current Share of Brazil Long Term Goal Markets 20% 12% 10% 7% 4% Share of Natural Electricity Distribution Power Generation Power Transmission ALL power markets Gas Distribution 20

  21. Slide 21: Target Ebitda contribution by business in the long run

    Slide 21: Target Ebitda contribution by business in the long run

    Target Ebitda contribution by business in the long run CIA. ENERGÉTICA DE MINAS GERAIS Power Power Electricity Natural Generation Transmission Distribution Gas Distribution Telecom Services 40% 20% 40% 21

  22. Slide 22: Growth Drivers

    Slide 22: Growth Drivers

    Growth Drivers 1 Leverage price increases $ 2 Improve operating efficiency 3 Geographic expansion 22

  23. Slide 23: Record of Successful Acquisitions

    Slide 23: Record of Successful Acquisitions

    GROWTH DRIVER #2 Record of Successful Acquisitions Business Model for Growth ● Record of 5 acquisitions in last 5 years totaling R$ 3B (excluding debt) ● Partnerships with Equity Investment Funds (FIPs) in recent acquisitions (Terna and Light) create a new growth driver ● Structuring of partnerships

  24. Slide 24: Clear Priorities for 2011

    Slide 24: Clear Priorities for 2011

    Clear Priorities for 2011 1 Execute cost reductions 2 Integrate Terna and Light acquisitions Priorities 3 Participate in green fields 4 Select new acquisitions 24

  25. Slide 25: Why Invest in Cemig

    Slide 25: Why Invest in Cemig

    Why Invest in Cemig Leading power utility in Brazil Powerful drivers fueling growth Sound Balance Sheet Consistent profitable track record Strong Dividend Policy World Leader in Sustainability 25

  26. Slide 26: Appendix

    Slide 26: Appendix

    CLMIG A Melhor Energia do Brasil. Appendix 26

  27. Slide 27: Agenda

    Slide 27: Agenda

    Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 27

  28. Slide 28: Brazilian GDP growth is driven by domestic market

    Slide 28: Brazilian GDP growth is driven by domestic market

    Brazilian GDP growth is driven by domestic market Economics Largest Latin America economy 7th largest world economy BRAZIL GDP (2010): US$ 2.1 trillion (+7.5%) Electric Power Industry Inhabitants: 191 million Area: 8.5 million km2 Power Generation Currency(1): Reais (BRL) – US$1 = R$ 1.66 Installed

  29. Slide 29: Companies and Consortia of the Cemig Group

    Slide 29: Companies and Consortia of the Cemig Group

    COMPANIES AND CONSORTIA OF THE CEMIG GROUP At March 2nd, 2010 CIA. ENERGÉTICA DE MINAS GERAIS CEMIG Geração e Usina Térmica Cia. Transleste Cia. de Gás de Light S.A. Parati S.A. CEMIG Transmissão S.A. Ipatinga S.A. de Transmissão Minas Gerais Distribuição S.A. 26.06% 49% 100% 25% 55.20% 100% 100% Ci

  30. Slide 30: Strong shareholders base assures liquidity

    Slide 30: Strong shareholders base assures liquidity

    Strong shareholders base assures liquidity North America EUROPA Luxembourg Jersey Germany ASIA Canada México UK Holland Belgium Brunei United States Spain France Austria Singapore Switzerland Norway Portugal South Korea Ireland Denmark Poland Japan Guernsey Italy Romania Malasia Sweden Taiwan Centra

  31. Slide 31: Cemig: a global investment option

    Slide 31: Cemig: a global investment option

    Cemig: a global investment option Non-Brazilian investors as % of free float* 60% 40% 20% 0% jan/06 jan/07 jan/08 jan/09 jan/10 Preferred Share ADR Bovespa * Free float = all shares in circulation except those held by the State of Minas Gerais and SEB. • The percentage of non-Brazilian investors in

  32. Slide 32: The blend of shareholders provides long term perspective

    Slide 32: The blend of shareholders provides long term perspective

    The blend of shareholders provides long term perspective Our shareholder diversity provides a global business Total Shares management vision focused on sustainability of the company's activities ON PN 44% 56% Listed in major stock exchanges BOVESPA (Brazil) 5% 11% ON NYSE (USA) LATIBEX (Spain) 33% 5

  33. Slide 33: Corporate Governance: implementation of best practices

    Slide 33: Corporate Governance: implementation of best practices

    Corporate Governance: implementation of best practices Highlights • Code of ethics; • 6 BoD members appointed by minority shareholders; Shareholders • BoD approves all investments above R$14mn; • BoD approves nomination of external auditors; • Executive Board coordinates external auditor selection p

  34. Slide 34: Leadership in sustainability, a core value at Cemig

    Slide 34: Leadership in sustainability, a core value at Cemig

    Leadership in sustainability, a core value at Cemig • Social and Environmental responsibilities • Long-term vision commitment • To guarantee the preservation of our activities • Prevent undue costs to be passed to the society through a balanced relationship with the environment and the community • R

  35. Slide 35: Why is Cemig Sustainable?

    Slide 35: Why is Cemig Sustainable?

    Why is Cemig Sustainable? 1. Financial Strength 2. Strategic Management 3. Commitment to clients 4. Profitable Investments 5. Technological Innovation 6. Commitment to stakeholders 7. Dedication towards the environment 8. Focus on Renewables 9. Care for human capital 10.Social Responsibility 35

  36. Slide 36: Global Compact

    Slide 36: Global Compact

    Global Compact In 2009 Cemig joined the Global Compact and published its “Corporate Social Responsibility” handbook. The principles of the Global Compact 1. Businesses should support and respect the protection of internationally proclaimed human rights in their area of influence; and 2. make sure th

  37. Slide 37: The Largest Integrated Power Utility in Brazil

    Slide 37: The Largest Integrated Power Utility in Brazil

    The Largest Integrated Power Utility in Brazil Power Generation Free Customers 6,896 MW of capacity 25% share Power Transmission 8,768 Km Retail Electricity Distribution Largest distribution 474,559 Km company September, 2010 figures 37

  38. Slide 38: The Portfolio: guaranteeing results

    Slide 38: The Portfolio: guaranteeing results

    The Portfolio: guaranteeing results Figures for 2009 Net revenue Net income 2% 1% 2% 3% Electricity Distribution Power Generation 6% 13% 20% • 2 companies • 18 companies • Net revenue: R$ 7.8 billion • Net revenue: R$ 3.0 billion 25% • Net income: R$ 417 million • Net income R$ 1.3 billion 64% • Ebi

  39. Slide 39: EBITDA Guidance 2010-2011

    Slide 39: EBITDA Guidance 2010-2011

    EBITDA Guidance 2010-2011 Cemig Distribuição Cemig GT - Consolidated 1800 3000 1550 2500 1300 2000 Lower Upper Lower Upper Year Year limit limit limit limit 1050 2010 894 1,093 1500 2010 2,182 2,666 2011 1,382 1,689 2011 2,479 3,030 800 1000 2010 2011 2010 2011 Participation in other companies – Cem

  40. Slide 40: Net Income and Ebitda per company

    Slide 40: Net Income and Ebitda per company

    Net Income and Ebitda per company (R$ Million) Net Income per Company Up to Up to Company ∆V% ∆V% 2009 ∆V% 2008 ∆V% Sep/10 Sep/09 Cemig Geração/Transmissão (*) 737 58% 1,003 70% 1,297 70% 986 52% Cemig Distribuição 170 13% 279 20% 338 18% 709 38% Light 74 6% 50 4% 78 4% 129 7% Gasmig 37 3% 30 2% 42

  41. Slide 41: Ebitda breakdown – 3Q10

    Slide 41: Ebitda breakdown – 3Q10

    The Portfolio: guaranteeing results Ebitda breakdown– 3Q10 5% 29% 49% 17% Generation Transmission Distribuition Natural Gas and Others 41

  42. Slide 42: Financial Highlights

    Slide 42: Financial Highlights

    Financial Highlights Income Statement – consolidated (R$ million) 2010* 2009* Change % Net Revenue 9,047 8,323 9% EBITDA 3,011 2,888 4.3% EBITDA Margin % 33 35 -4% Net Income 1,263 1,427 -11% Net Margin % 14 17 -19% Balance Sheet – consolidated (R$ million) 2010* 2009* Fundamentals remain solid Cash

  43. Slide 43: Debt profile lengthened with reduction of costs

    Slide 43: Debt profile lengthened with reduction of costs

    Debt profile lengthened with reduction of costs Maturities timetable (R$ Million) Emission of debentures has promoted Average tenor: 3.6 years the lengthened of our debt from 3 to 3.9 years 3.281 Average cost of debt (real terms) 2.602 1.832 9,7 9,0 1.466 7,3 5,8 6,2 6,8 1.082 1.135 5,4 5,3 5,7 690

  44. Slide 44: Financial discipline to lower debt cost and reduce FX exposure

    Slide 44: Financial discipline to lower debt cost and reduce FX exposure

    Financial discipline to lower debt cost and reduce FX exposure Main indexors Main Creditors (R$ million) September 30, 2010 Debentures Holders R$ 4,913 38% Banco do Brasil R$ 3,116 24% 1% BNDES R$ 1,710 13% 55% 16% Banco Itaú BBA(*) R$ 952 8% Bradesco(*) R$ 662 5% 3% Unibanco R$ 378 3% 16% Eletrobrá

  45. Slide 45: Superior credit capacity recognized by the major rating agencies

    Slide 45: Superior credit capacity recognized by the major rating agencies

    Superior credit capacity recognized by the major rating agencies AA(bra) Cemig H, Cemig GT and Cemig D National scale Investment Grade Speculative Grade AA+ AA AA- A+ A A- BBB+ BBB BBB- BB+ BB BB- B+ B B- CCC CC C RD D Aa1.br Cemig GT and Cemig D National scale Aa2.br Cemig H National scale Investme

  46. Slide 46: Opportunities of raising funds to finance expansion

    Slide 46: Opportunities of raising funds to finance expansion

    Opportunities of raising funds to finance expansion Cemig is ready to enjoy market liquidity Local Bank Market Local Capital Market Debt rollover Debêntures are the major source of funds for investment (long term and inflation indexed) Assignment of receivables Securitizations Project Finance (Cemig

  47. Slide 47: Agenda

    Slide 47: Agenda

    Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 47

  48. Slide 48: Long Term Strategic Plan addresses sustainable growth

    Slide 48: Long Term Strategic Plan addresses sustainable growth

    Long Term Strategic Plan addresses sustainable growth… • Broadening of CEMIG's area of activity, focusing on the electric industry – Growth within Brazil's geographical area – First steps towards international investments – Expansion in line with Brazilian regulatory limits and sustainable growth –

  49. Slide 49: Investment policy to guarantee sustainable growth

    Slide 49: Investment policy to guarantee sustainable growth

    …Investment policy to guarantee sustainable growth • Pillars of our activity: • Focus on electricity sector and related activities • Profitability: return compatible with each business • Partnerships with strategic investors: corporate governance • Growth through new projects, long-term vision • Opp

  50. Slide 50: Strategic Plan Results

    Slide 50: Strategic Plan Results

    Strategic Plan Results Power Generation Power Transmission lines - km 81% 142 521 44 76 8.768 4.856 164 6.896 17% 2004 sep/10 5.949 Sub-transmission lines -km 6% 16.086 17.095 2004 sep/10 Electricity Distribution lines -km Our power matrix ensures higher 25% operational margins 367.437 457.464 2004

  51. Slide 51: Strategic Plan Results

    Slide 51: Strategic Plan Results

    Strategic Plan Results Net margin (%) 27 Ebitda margin (%) 20 42 17 17 18 40 38 38 35 Net income (R$ million) Ebitda (R$ million) 1,887 1,861 4,062 4,099 4,039 1,662 1,719 1,743 3,058 3,222 2005 2006 2007 2008 2009 2005 2006 2007 2008 2009 Dividend pay-out (% of Net income) 103 80 Dividends 50 50 50

  52. Slide 52: Strategic Plan Results: Dividends

    Slide 52: Strategic Plan Results: Dividends

    Strategic Plan Results: Dividends (1) Proposal for 2009 Net Income distribution was approved : • Ordinary Dividends of R$ 931 million - Dividends per share: R$1.50 • Stock Dividend of 10% Extraordinary Dividends was also approved and paid in December 2010: • R$900 million – Dividends per share: R$1.

  53. Slide 53: Results reflect long-term vision

    Slide 53: Results reflect long-term vision

    Results reflect long-term vision Company's structure oriented towards electricity sector consolidation Operational excellence aligned with costs reduction Investment criteria defined by Strategic Plan to add value Risk management ensures reliable processes Corporate governance as a corporate value c

  54. Slide 54: Continuous improvement of our KPI

    Slide 54: Continuous improvement of our KPI

    Continuous improvement of our KPI Leverage (%) Key debt indicators (%) Debt / (Debt + Equity) 5.0 4.0 4.2 4.0 48 44 43 2.2 2.1 40 1.2 1.7 2007 2008 2009 3Q10 2007 2008 2009 3Q10 Leverage (%) Debt/Ebitda Ebitda/Interest Key performance indicators in line with Long Term Strategic Plan Earnings per sha

  55. Slide 55: Agenda

    Slide 55: Agenda

    Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 55

  56. Slide 56: Basics of our business portfolio

    Slide 56: Basics of our business portfolio

    Basics of our business portfolio • Power generation – More competitive environment • Regulated market : long term contracts with distributors sales through public auctions. • Un-regulated market : medium term contract with large clients. Contract terms bilaterally negotiated. • Power transmission –

  57. Slide 57: Power Generation: Cemig

    Slide 57: Power Generation: Cemig

    Power Generation: Cemig Installed Capacity (September/2010) Installed capacity Efective Power Plant (MW) (MW Average) São Simão 1,710 1,281 Emborcação 1,192 497 Nova Ponte 510 276 Jaguara 424 336 Miranda 408 202 Três Marias 396 239 Volta Grande 380 229 Irapé 360 206 Aimorés 162 84 Others hydro 901 9

  58. Slide 58: Power Generation: Expansion

    Slide 58: Power Generation: Expansion

    Power Generation: Expansion New generation projects: continuous growth Start Up of Baguari Hydroelectric Plant Installed Capacity: 140 MW Cemig’s Participation: 34% 120 days earlier than the initial schedule Installation of the Ceará Wind Farm system Parajuru, Morgado and Volta do Rio 100.00 MW of i

  59. Slide 59: Power Generation: Expansion

    Slide 59: Power Generation: Expansion

    Power Generation: Expansion Acquisitions: 3 wind farms – from Energimp S.A.: R$ 223 million (49%). New projects Plant Installed Cemig stake Start up date capacity (MW) (%) Cachoeirão Small Hydro Plant 27 49% 2009 Baguari Hydro Plant 140 34% 2009 Wind farms 100 49% 2009/2010 Small Hydro Plants 107 49

  60. Slide 60: Projects under study

    Slide 60: Projects under study

    Projects under study Number Installed capacity Types of project Brazil Minas Gerais Hydroelectric plants 23 5,706 MW 11 1,181 MW Small Hydro Plants 106 MW 7 6 89 MW Thermal plants (*) 3 513 MW 1 273 MW Wind farms 4 802 MW 1 400 MW Co-generation, biomass 7 401 MW 1 267 MW Total 44 7,528 MW 23 2,210 M

  61. Slide 61: Conventional Energy

    Slide 61: Conventional Energy

    GROWTH DRIVR #1 Cemig GT - Balance of supply and demand Average Ongoing negotiations Requirement details 5.500 Conventional Energy Probable renewals 550 550 5.000 550 4.500 77 875 1.197 160 329 4.000 127 163 1.741 1.620 211 223 1.722 1.581 233 590 3.500 590 240 242 3.000 2.379 590 590 590 2.440 2.28

  62. Slide 62: CEMIG GT: Power generation prices estimates

    Slide 62: CEMIG GT: Power generation prices estimates

    CEMIG GT: Power generation prices estimates Guidance for Average Prices – Cemig GT* (R$/MWh) Settlement of a large amount of secondary power at spot prices (PLD) in 2010; 150 • If excluded, the average price would be of approximately 100.00 R$/MWh 121 125 Expected contract renewals and new contracts

  63. Slide 63: Power Generation Sales Volume Estimates: CEMIG GT

    Slide 63: Power Generation Sales Volume Estimates: CEMIG GT

    Power Generation Sales Volume Estimates:CEMIG GT MARKET – TWh* 50 39.6 40 37.3 38.1 35.1 36.5 3.2 30 34.1 20 10 0 2010 2011 2012 2013 2014 Own Resources Secondary Energy 2010: Participation in the Secondary Energy Market - generation is above the physical guarantees as a result of the favorable hydr

  64. Slide 64: Brazilian National Grid

    Slide 64: Brazilian National Grid

    Brazilian National Grid Structural Energy Balance (Average MW) Additional needs Source: Sept. 2010 ONS Monthly Operational Program (PMO) and analysis by Cemig, considering a GDP growth of 5.1% from 2010 to 2019. 64

  65. Slide 65: Level of reservoirs (%)

    Slide 65: Level of reservoirs (%)

    Level of reservoirs (%)* Level of reservoirs by region (%) 100 90 83.24 80 70 63.12 60 59.98 50 53.33 40 30 20 Northeast North South Southeast/Midwest *Source: ONS 65

  66. Slide 66: Spot Market: 2009/2010

    Slide 66: Spot Market: 2009/2010

    Spot Market: 2009/2010 Brazil: electricity spot price - monthly average (R$/MWh) 160 140 120 100 70.23 80 48.04 60 40 38.38 20 0 jul/10 jul/11 jan/10 jun/10 set/10 jan/11 jun/11 set/11 fev/10 mar/10 abr/10 mai/10 ago/10 out/10 nov/10 dez/10 fev/11 mar/11 abr/11 mai/11 ago/11 out/11 nov/11 dez/11 Mon

  67. Slide 67: Power Generation Auctions: 2010

    Slide 67: Power Generation Auctions: 2010

    Power Generation Auctions:2010 Capacity Efective Power Name Date Power Plant Price/MWh Installed(MW) (MW Average) Special Power Auctions 2010 Belo Monte (30 years long contracts) 11,233 4,571 R$ 77.97 Garibaldi 178 83 R$ 108.00 Colider 300 180 R$ 103.00 A-5 2010 Ferreira Gomes 252 150 R$ 70.00 New P

  68. Slide 68: Business Opportunities: Small Hydros Program

    Slide 68: Business Opportunities: Small Hydros Program

    Current status Business Opportunities: Small Hydros Program Short-term supply alternative Successful funding format: – 30% Equity • Cemig 49% Àrea reservada para o mapa • Private Investor 51% – 70% Debt • BNDES Current status: • Cachoeirão Small Hydro Power Plant (27 MW) in commercial operation; • P

  69. Slide 69: Business Opportunities: biomass cogeneration

    Slide 69: Business Opportunities: biomass cogeneration

    Business Opportunities: biomass cogeneration Sugar and ethanol potencial in Minas gerais Plants Quantity* Generatn. (MWa**) Surplus (MWa**) Existing 12 750 300 Expected 22 2,416 1,631 Total 34 3,166 1,931 * Just includes plants available to generate and sell power ** Average generation in 6 months o

  70. Slide 70: Brazilian hydroelectric power generation potential

    Slide 70: Brazilian hydroelectric power generation potential

    Brazilian hydroelectric power generation potential Situation as of June 2010, MW State Operation Estimated Overall AC & - 1,121 Total 1,121 AM 250 19,648 19,898 RR AP AP 68 1,839 1,907 North RO 3,547 9,342 12,889 RR 5 5,257 5,262 PA 8,455 39,990 48,445 AM PA MA TO 2,294 4,351 6,644 CE RN AL 1,582 2,

  71. Slide 71: Tapajós Complex

    Slide 71: Tapajós Complex

    Tapajós Complex Location: Tapajós Basin, PARA State 5 Hydro Power Plants Installed Capacity: 10,682 MW Assured energy: 4,581 average MW (expected) Power Plant River Installed Assured Start-up Capacity Energy -MW Avg MW São Luiz do Tapajós Tapajós 6,133 3,369 2016 Cachoeira do Caí Tapajós 802 418 201

  72. Slide 72: Teles Pires Complex

    Slide 72: Teles Pires Complex

    Teles Pires Complex Location: Teles Pires Basin, Mato Grosso State 3 Hydro Power Plants Installed Capacity: 3,027 MW Power Plant River Installed Assured Start-up Capacity -MW Energy Date Avg MW Teles Pires Teles Pires 1,820 915 2015 São Manuel Teles Pires 746 400 2015 Sinop Teles Pires 461 227 2015

  73. Slide 73: Santo Antônio hydro plant – basic information

    Slide 73: Santo Antônio hydro plant – basic information

    Santo Antônio hydro plant – basic information • 3,150 MW of installed capacity • 2,218 MWAverage of energy > Capacity Factor (CF) of 69%; • Price: R$78.87/MWh (equivalent to R$99/MWh for a traditional 55% CF Hydro Power in Brazil) • Winner consortium: – 10% Cemig – 39% Furnas – 20% FIP (Investment F

  74. Slide 74: Santo Antônio hydro plant – basic information

    Slide 74: Santo Antônio hydro plant – basic information

    Santo Antônio hydro plant – basic information • Low-fall plant (13.9 m), average estimated flow 568 m3/s, lake 271 km2, resulting in lower ratio between reservoir area and total energy generated than in other Amazon region plants: index of 0.09 – Balbina ( 250 MW, 2,360 km2 reservoir): index 9.44 –

  75. Slide 75: Wind power potential in Minas Gerais

    Slide 75: Wind power potential in Minas Gerais

    Wind power potential in Minas Gerais Cemig is one of the pioneer companies in terms of wind generation in Brazil through the Morro do Camelinho plant, which was connected to the grid in 1992. Wind power map of Brazil: Brazil has a theoretical wind power generation potential of 143.5 GW, estimated at

  76. Slide 76: Power Transmission Capacity (Km)

    Slide 76: Power Transmission Capacity (Km)

    Power Transmission Capacity (Km) 2005 2006 2007 2008 2009 Sep/10 525-Kv lines 0 0 0 51 77 101 500-kV lines 2,165 2,592 2,488 2,788 3,594 4,421 345-kV lines 1,976 1,969 2,001 2,001 2,167 2,358 230-kV lines 751 803 824 915 1,668 1,888 Total 4,892 5,364 5,313 5,755 7,506 8,768 • Charrúa – Nueva Temuco

  77. Slide 77: Transmission: Present all over Brazil

    Slide 77: Transmission: Present all over Brazil

    Transmission: Present all over Brazil ETEP and ERTE NOVATRANS Cemig is now Brazil’s third largest transmission group: GTESA EATE and ENTE Total lines: 8,768 Km PATESA Consolidated Permitted MA RN PA Annual Revenue (RAP): R$1.2 PE billion, including Transchile PB TO Present in 13 States of Brazil MT

  78. Slide 78: Power Transmission: Expansion

    Slide 78: Power Transmission: Expansion

    Power Transmission: Expansion Acquisitions in 2009: Taesa (formerly Terna): R$ 1.90 billion for a 56.7% stake Increased interest in TBE: R$ 505 million Acquisitions in 2010 Increased interest in TBE: R$ 100 million. Current stake of 40% approximately. ASSETS RAP (Permitted Annual Cemig stake (%) Sta

  79. Slide 79: Start up in Chile: First international step

    Slide 79: Start up in Chile: First international step

    Start up in Chile: First international step Charrúa–Nueva Temuco Transmission Line Chile •Voltage: 2x 220kV •Length: 205 km •Concession period: 20 years •Stake: 49% •Total investment: US$88 million •Annual Revenue: US$65 million Transchile •Financing: 63% of the investment •Capital from Cemig : U$20

  80. Slide 80: Power Transmission auctions 2010

    Slide 80: Power Transmission auctions 2010

    Power Transmission auctions • 2010 Auctions June, 11th December, 09th 9 lots totaling 700 Km of lines 8 lots totaling 555 Km of lines These assets will be built in 7 states These assets will be built in 6 states 30 years contracts and estimated total capex of R$700 million 30 years contracts and est

  81. Slide 81: The 1st Transmission Tariff Review

    Slide 81: The 1st Transmission Tariff Review

    The 1st Transmission Tariff Review This cyclical review is related just with old assets hold by Cemig GT • Taesa and TBE are not entitled to this type of review The criteria of this Tariff Review were set by Aneel Normative Resolution 257/07, the principal ones being: a. WACC: 9.18% p.a. b. Operatio

  82. Slide 82: Electricity Distribution Capacity

    Slide 82: Electricity Distribution Capacity

    Electricity Distribution Capacity Network in km 2007 2008 2009 Sep/10 SUB-TRANSMISSION 16,676 16,810 16,959 17,096 161-kV lines 55 55 55 55 138-kV lines 11,145 11,254 11,442 11,491 69-kV lines 4,510 4,535 4,508 4,595 Lines below 69 kV 966 966 954 955 DISTRIBUTION 429,560 442,749 450,316 457,463 Urba

  83. Slide 83: Distribution: Expansion

    Slide 83: Distribution: Expansion

    Distribution: Expansion Acquisitions in 2009: Increase of stake in Light • R$ 785 million for each block of 13.03% in Light • AG’s stake in Light was already paid by Cemig • Currently Cemig holds a direct interest in Light of 25.53% Light announces new Executive Board Leadership of Gerson Kelman ens

  84. Slide 84: Cemig D: sales by category on September 30, 2010

    Slide 84: Cemig D: sales by category on September 30, 2010

    Cemig D: sales by category on September 30, 2010 Sales by category - GWh Electricity sold – GWh: Changes, 3Q10 TYPE 3Q10 3Q09 Change % +11% Residential 6.301 2,201 1,951 4% Industrial 1,209 1,220 -1% +11% 5.669 Commercial 1,117 1,102 1% +3% Rural 746 675 10% Other 748 718 4% Clients 5,841 5,666 3% +

  85. Slide 85: Electricity Distribution tariff review

    Slide 85: Electricity Distribution tariff review

    Electricity Distribution tariff review • Allowed return on asset approach: – Benchmark WACC: was 11.26% in 1st cycle (2003) – Tariff review: WACC of 9.95% in 2nd cycle (2008) • New Tariff Review methodology: – Reference company model disclosed: – Black box opened. – Asset base review every 10 years

  86. Slide 86: Cemig D 2009 readjustment and Impact on Tariff

    Slide 86: Cemig D 2009 readjustment and Impact on Tariff

    Cemig D 2009 readjustment and Impact on Tariff 2009 IMPACT to CONSUMERS Financial Components 2008 + CVA R$ 442.300.746 Financial Components + CVA ANEX II (IRT) R$ 682.427.357 REQUIRED Appendix Appendix Appendix REVENUE I I VERIFIED II REVENUE Appendix R$ 7.622.802.110 II R$ 6.124.630.949 Appendix I:

  87. Slide 87: Cemig D 2010 readjustment and Impact on Tariff

    Slide 87: Cemig D 2010 readjustment and Impact on Tariff

    Cemig D 2010 readjustment and Impact on Tariff 2010 IMPACT to CONSUMERS Financial Components 2009 + CVA R$ 332,792,812 Financial Components + CVA ANEX II (IRT) R$ 442,300,746 REQUIRED Appendix Appendix Appendix REVENUE I I VERIFIED II REVENUE Appendix R$ 7,974,659,463 II R$ 7,622,802,110 Appendix I:

  88. Slide 88: 1st Tariff Review 2003 vs 2nd Tariff Review 2008/2009

    Slide 88: 1st Tariff Review 2003 vs 2nd Tariff Review 2008/2009

    1st Tariff Review 2003 vs 2nd Tariff Review 2008/2009 2nd Tariff Review 2009 1st Tariff Review 2003 2nd Tariff Review 2008 Final • Regulatory Ebitda • Regulatory Ebitda • Regulatory Ebitda Margin: 21.2% Margin: 21% Margin: 21% • Losses coverage: • Losses coverage: • Losses coverage: inadequate suffi

  89. Slide 89: Aneel's Proposal for the 3rd Cycle: WACC

    Slide 89: Aneel's Proposal for the 3rd Cycle: WACC

    Aneel’s Proposal for the 3rd Cycle: WACC Regulatory Proposal WACC 2nd Cycle ( Final) 3rd Cycle (Aneel’s Proposal) Debt Cost of Debt (Rd) 14.97% 11.50% Taxes (t) 34.00% 34.00% Debt-to-Capital (D/D+E) 57.16% 60.00% WAC of debt 5.65% 4.55% Equity Risk free Rate (Rf) 5.32% 4.96% Market Premium (Rm – Rf)

  90. Slide 90: Aneel's Proposal for the 3rd Cycle: Main Changes

    Slide 90: Aneel's Proposal for the 3rd Cycle: Main Changes

    Aneel’s Proposal for the 3rd Cycle: Main Changes Opex: • Two stages: o Reference Company model of the 2nd Cycle (2008) adjusted to inflation and productivity gains and sales volume increase – First Stage o Benchmarking with peers in order to verify Stage 1 and produce component (T) – Second Stage; C

  91. Slide 91: Aneel's Proposal for the 3rd Cycle: Main Changes

    Slide 91: Aneel's Proposal for the 3rd Cycle: Main Changes

    Aneel’s Proposal for the 3rd Cycle: Main Changes Energy Losses: Regulatory energy losses will be defined according to the complexity of each concession area • Companies ranked and then grouped. In a ranking from more to less complexity, to deal with electricity losses, Cemig was considered 24th and

  92. Slide 92: Natural Gas Distribution - Gasmig

    Slide 92: Natural Gas Distribution - Gasmig

    Natural Gas Distribution - Gasmig 287 Clients (conventional), 2 Thermal power plants 28 municipalities served 222 employees 794 km of networks Concession area: 586,523 km² Major works: Sul de Minas Project – Completed Vale do Aço project Market*: –completed Sales volume: 668,441,993 m³ Average:: 2,4

  93. Slide 93: Natural Gas Expansion: Cemig's consortium wins Brazilian Oil and Gas Bids

    Slide 93: Natural Gas Expansion: Cemig's consortium wins Brazilian Oil and Gas Bids

    Natural Gas Expantion: Cemig´s consortium wins Brazilian Oil and Gas Bids in December 2008 Strategic initiative seeks means to ensure supply of natural gas for distribution, through Gasmig, and for thermal power generation Consortium Structure Winning Bid Cemig´s stake in the consortium of 24.5% Sig

  94. Slide 94: Agenda

    Slide 94: Agenda

    Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 94

  95. Slide 95: Acquisitions leverage results

    Slide 95: Acquisitions leverage results

    Aquisitions leverage results Assets 2004 2005 2006 2007 2008 2009 Total Value invested in acquisitions R$ Million Total Rosal 136.7 136.7 TBE 349.3 3.6 3.6 356.6 Light 174.6 174.6 Total 136.7 - 523.9 3.6 3.6 667.8 Contribution to net income Rosal (5.6) 18.9 18.7 18.9 120.5 23.4 TBE 24.7 28.9 36.4 79

  96. Slide 96: Holdings acquired add net income to Cemig's results

    Slide 96: Holdings acquired add net income to Cemig's results

    Holdings acquired add net income to Cemig’s results TBE(1) +R$ 78 MM TAESA(1) +R$ 94 MM LIGHT(1) +R$ 74 MM + R$246million/year of Net Income up to September 2010 (1) 2010 numbers include the increased stake in Light (from 13% to 26%) and TBE (from 17% to 39%), and also consider a 56.70% stake in Tae

  97. Slide 97: Cemig Group grows through management of assets

    Slide 97: Cemig Group grows through management of assets

    Cemig Group grows through management of assets As well as operators, we have become managers of assets, in all segments of electricity: 8,648 Power Generation 6.896 1.752 Installed capacity (MW) 64,144 Cemig Electricity Distributed consolidated 48,765 15,379 Annual Sales(GWh)* 12,408 Management for

  98. Slide 98: Acquisition of Brookfield's shares in TBE (Transmission)

    Slide 98: Acquisition of Brookfield's shares in TBE (Transmission)

    Acquisition of Brookfield’s shares in TBE (Transmission) In 2006 Cemig acquired a Stake in TBE Cemig increased its stake in TBE: R$505M paid in 2009 Stakes before the acquisition EATE ECTE ENTE ERTE ETEP CEMIG 17.68% 7.50% 18.35% 18.35% 19.67% Eletrobrás 29.30% 0% 0% 0% 21.33% Other partners 53.02%

  99. Slide 99: Acquisition of MDU's Shares in TBE (Transmission)

    Slide 99: Acquisition of MDU's Shares in TBE (Transmission)

    Acquisition of MDU’s Shares in TBE (Transmission) The acquisition of equity interests held by MDU in the companies of the TBE group was completed on November 12, 2010. Cemig’s stakes were increased to the following: COMPANY % OF TOTAL CAPITAL Empresa Norte de Transmissão de Energia S.A. (ENTE) 13.30

  100. Slide 100: Description of TBE – Power transmission group

    Slide 100: Description of TBE – Power transmission group

    Description of TBE – Power transmission group Length Company Line/Substation Capacity(kV) Start-up (Km) EATE Tucuruí (PA) a Presidente Dutra (MA) 927 500 mar/03 ECTE Blumenau (SC) a Campos Novos (SC) 253 525 mar/02 ENTE Tucuruí (PA) a Açailândia (MA) 458 500 fev/05 ERTE Vila do Conde (PA) a Santa Ma

  101. Slide 101: Acquisition of holdings in wind farms: The Transaction

    Slide 101: Acquisition of holdings in wind farms: The Transaction

    Acquisition of holdings in wind farms: The Transaction Resulting stockholding structure The Transaction • Acquisition of 49% stockholdings in three wind farms (99.6MW) in the Brazilian State of Ceará, currently owned by Energimp S.A. (IMPSA). • Price paid for the shares: R$ 223 million, to be paid (

  102. Slide 102: Acquisition of holdings in wind farms: The Assets

    Slide 102: Acquisition of holdings in wind farms: The Assets

    Acquisition of holdings in wind farms: The Assets Locations Volta do Rio Wind Power Plant Volta do Rio Morgado • Location: Acaraú (240km from Fortaleza), Ceará Fortaleza • Equipment: 28 rotors of 1,500KW each Parajurú • Installed capacity: 42.0MW • Load factor : >45% • Energy contracted: 161.2GWh /

  103. Slide 103: Terna (now named TAESA) acquisition - Transaction Summary

    Slide 103: Terna (now named TAESA) acquisition - Transaction Summary

    Terna (now named TAESA) acquisition - Transaction Summary Power Transmission Company with 3,753 km of lines in 11 Brazilian States Acquisition in partnership with Equity Investment Fund - FIP Coliseu Largest FIP created to invest in the Brazilian electricity sector: R$ 1.33 billion o Attractive to i

  104. Slide 104: Rationale of model for Taesa acquisition (with FIP)

    Slide 104: Rationale of model for Taesa acquisition (with FIP)

    Rationale of model for Taesa acquisition (with FIP) In line with the Long-term Strategic Plan Vehicle for growth in the transmission sector Synergies with Cemig’s transmission assets, including TBE Operational and corporate gains Possibility of improving Ebitda margin Partnership with an FIP reduces

  105. Slide 105: FIP Coliseu: Efficient vehicle for growth in Transmission

    Slide 105: FIP Coliseu: Efficient vehicle for growth in Transmission

    FIP Coliseu: Efficient vehicle for growth in Transmission On November 4th, 2009, Cemig GT, jointly with FIP Coliseu, acquired 65.85% of Terna Participações S.A., through Transmissora do Atlântico de Energia Elétrica S.A. Atlântico was split, creating Transmissora Alterosa, which will be responsible

  106. Slide 106: Public offer for shares in Taesa

    Slide 106: Public offer for shares in Taesa

    Public offer for shares in Taesa 86% of minority shareholders accepted Updated price per share: R$ 12.91 (R$ 38.73 per Unit) Total investment in this offer: R$ 831 million TAESA: Structure after public offer Settlement: May 11th Cemig’s final interest: • 56.7% - total capital • 48.0% - ON shares • 8

  107. Slide 107: TAESA - Overview

    Slide 107: TAESA - Overview

    TAESA - Transmissora Aliança de Energia Elétrica S.A - Overview Geographic Footprint NVT 1,278km / 500kV Overview of Concessions RAP:R$312.6MM Start-up Concession GTESA Line Date Term 51km / 230kV RAP:R$5.3MM TSN abr-03 dez-30 GTESA jul-03 jan-32 PATESA 135km / 230kV PATESA mar-04 dez-32 RAP:R$12.5M

  108. Slide 108: Distribution: Increasing stake in Light in 2010 creates new opportunities

    Slide 108: Distribution: Increasing stake in Light in 2010 creates new opportunities

    Distribution: Increasing stake in Light in 2010 creates new opportunities A 13.03% stake was bought for R$172M in 2006 (with full payback in 2 years) Cemig D and Light represent almost 16% of electricity distributed in Brazil in 2008 • Tradition and experience in Light and Cemig brought closer • Opp

  109. Slide 109: Summary of the transaction

    Slide 109: Summary of the transaction

    Summary of the transaction • Restructuring of the controlling shareholding block of Light − AG Concessões and PCP (Equatorial) will sell their stakes in Light − Equatorial will undergo a shareholding reorganization − Cemig will be a minority shareholder in a Special-purpose Company (SPC) constituted

  110. Slide 110: Increasing stake in Light marks the beginning of a new era

    Slide 110: Increasing stake in Light marks the beginning of a new era

    Increasing stake in Light marks the beginning of a new era The increase of Cemig’s stake marks the beginning of a second stage in Light’s history • With the selling of the financial partners’ stakes it will be possible to increase the synergy between Cemig and Light • Corporate Governance structure

  111. Slide 111: Agenda

    Slide 111: Agenda

    Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 111

  112. Slide 112: CAPEX Investment program

    Slide 112: CAPEX Investment program

    CAPEX(R$ Million) Investment program Planned(*) Activity Up to Sep/10 2010 2011 2012 Basic program (1) 400 916 1,167 885 Generation 18 63 126 74 Transmission 10 30 40 16 Cemig D 372 822 1,001 793 Cemig H - 1 - 2 Expasion(2) 156 319 263 252 Light for Everyone Program 340 444 (42) - Light for Everyone

  113. Slide 113: Planned expansion

    Slide 113: Planned expansion

    Planned expansion Power Generation Expansion Capacity, MW CEMIG % 2009 2010 2011 2012 2013 Santo Antônio Hydro Plant 10 3,150 Pipoca PCH 49 20 Senhora do Porto PCH 49 12 Dores de Guanhães PCH 49 14 Jacaré JCH 49 9 Fortuna II PCH 49 9 Itaocara 49 194 Paracambi 49 25 Lajes 49 18 Capacity under constru

  114. Slide 114: Large Growth in Cash Flow

    Slide 114: Large Growth in Cash Flow

    Large Growth in Cash Flow Cash Flow Statement (consolidated) Up to Up to 3Q10 3Q09 Change% Change% (Values in R$ million) Sep/10 Sep/09 Cash at start of period 3,755.0 2,251 67 4,425 2,284 94 Cash from operations 1,147.0 1,363 (16) 3,033 2,671 14 Net income 553.0 567 (2) 1,263 1,427 (11) Depreciatio

  115. Slide 115: Consolidated net revenue

    Slide 115: Consolidated net revenue

    Consolidated net revenue Growth in net revenue reflects business diversification, and positive effects of acquisitions (RME/Light S.A., TAESA and TBE companies) Operating Revenues (consolidated) Up to Up to 3Q10 3Q09 Change% Change% (Values in R$ million) Sep/10 Sep/09 Sales to end consumers 3,391 3

  116. Slide 116: Operating Expenses

    Slide 116: Operating Expenses

    Operating Expenses Operating Expenses (consolidated) Up to Up to 3Q10 3Q09 Change% Change% (Values in R$ million) Sep/10 Sep/09 Personnel/Administrators/Councillors 265 278 (5) 858 1,024 (16) Forluz – Post-Retirement Employee Benefits 41 37 9 126 106 20 Materials 31 27 13 89 79 12 Raw material for p

  117. Slide 117: Consolidated operational expenses

    Slide 117: Consolidated operational expenses

    Consolidated operational expenses 3Q10 expenses R$ million +8% Consolidated Expenses Changes 3Q10/3Q09 64 58 39 3 4 10 18 18 2,090 2,208 (13) (4) (4) (75) 3Q09 3Q10 Operational efficiency program begins to generate results Reduction of personnel expenses (from 3Q09 to 3Q10) is over R$ 15 mn Higher e

  118. Slide 118: Expansion of consolidated net income in the year

    Slide 118: Expansion of consolidated net income in the year

    Expansion of consolidated net income in the year Result shows growth consistent with solid fundamentals • Growing productivity in all areas • Continuous improvement in operational margins • Diversification of the risk inherent to each business through integrated structure Statement of Results (Conso

  119. Slide 119: Cemig Distribuição

    Slide 119: Cemig Distribuição

    Cemig Distribuição Statement of Results - CEMIG D Up to Up to 3Q10 3Q09 Change% Change% (Values in R$ million) Sep/10 Sep/09 Net Revenue 1,673 1,761 (5) 5,086 4,537 12 Operating Expenses 1,485 1,520 (2) 4,684 4,148 13 EBIT 188 241 (22) 402 389 3 EBITDA 284 321 (12) 686 632 9 Financial Result (35) 43

  120. Slide 120: Cemig Geração e Transmissão

    Slide 120: Cemig Geração e Transmissão

    Cemig Geração e Transmissão Statement of Results - CEMIG GT Up to Up to 3Q10 3Q09 Change% Change% (Values in R$ million) Sep/10 Sep/09 Net Revenue 991 843 18 2,685 2,612 3 Operating Expenses (404) (330) 22 (1,179) (996) 18 EBIT 587 513 14 1,506 1,616 (7) EBITDA 666 570 17 1,728 1,786 - Financial Res

  121. Slide 121: Agenda

    Slide 121: Agenda

    Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 121

  122. Slide 122: Market Recognition

    Slide 122: Market Recognition

    Market Recognition Included in the DJSI for the 11th year running. Included in Bovespa Corporate Sustainability Index. Included in The Global Dow Index as the only Latin American electricity company in this 150- company index, and one of the 10 selected to represent emerging markets. Prêmio Anefac T

  123. Slide 123: Appendix

    Slide 123: Appendix

    Appendix •Regulatory Framework •Others 123

  124. Slide 124: Power Generators are the most exposed to risks

    Slide 124: Power Generators are the most exposed to risks

    Power Generators are the most exposed to risks • Regulated market – Concessions granted based on the least price approach. – Power purchase contract: • Auctions organized by a Federal agency: – Final buyer : Electricity Distributors. • New capacity : longer term, no market risk, inflation adjusted;

  125. Slide 125: Power Generation Price Trend

    Slide 125: Power Generation Price Trend

    Power Generation Price Trend • Price will behave differently according to the nature of the contract to be auctioned by ANEEL: – Existing capacity (so called “old energy”) contracts: • power to be supplied in a year from now; • Term of 8 years; (can be from 3 to 15 years) • Imply distributor ‘s fore

  126. Slide 126: Generation Wholesale prices resulting from auctions

    Slide 126: Generation Wholesale prices resulting from auctions

    Brazil’s electricity markets Generation • Wholesale prices resulting • Freely negotiated wholesale from auctions prices Regulated Market Free Consumers Distribution Companies Free Market (“ACR”) Special Consumers (“ACL”) Traders Generators Co-existence of two markets: competitive, and regulated 126

  127. Slide 127: Types of contracting in the Regulated Market

    Slide 127: Types of contracting in the Regulated Market

    Types of contracting in the Regulated Market A–5 A–3 A–1 Adjustment Local Generation New New Energy Existing Auctions Auctions (Distribution Energy Auctions Generation Company Option) Auctions Auctions Objective Expansion Expansion Existing load Adjustment of Existing load current situation Duration

  128. Slide 128: Reserve Auctions

    Slide 128: Reserve Auctions

    Reserve Auctions Objective: To further increase the security of the System by diversifying supply sources Energy sources: So far specific auctions for Small Hydro Plants (“PCHs”) and plants generating from wind energy and biomass. Contract periods: • Hydro: 30 years • Biomass:15 years • Wind: 20 yea

  129. Slide 129: Power Generation – Brazil's Installed Capacity

    Slide 129: Power Generation – Brazil's Installed Capacity

    Power Generation – Brazil’s Installed Capacity (% in 2009) Eletrobras Eletronuclear EDP Energias do Brasil 3% 2% Duke Energy CPFL Eletrobrás Chesf 3% 3% 14% AES 4% Copel 6% Eletrobras Furnas 12% Petrobras 6% Tractebel 7% Eletrobras Eletronorte 12% Cemig 9% Source: Cemig Cesp Excludes Itaipu Itaipu 1

  130. Slide 130: Power Transmission: Brazil

    Slide 130: Power Transmission: Brazil

    Power Transmission: Brazil Transmission (% of 2009 RAP) Copel Others CEE 3% 4% 4% Abengoa 4% CEMIG 5% TBE Eletrobrás 5% 46% Plena Group 5% TAESA 7% CTEEP 17% Source: Cemig 130

  131. Slide 131: Transmission regulation is the most successful one

    Slide 131: Transmission regulation is the most successful one

    Transmission regulation is the most successful one • Competition for concession contract: – Cap price approach: annual permitted revenue; – Allowed revenue: the winner bid is the lowest revenue earned from users; – 30-year long concession. • Stable Cash flow – Guaranteed contracts signed with users:

  132. Slide 132: Transmission network expansion

    Slide 132: Transmission network expansion

    Transmission network expansion • Facilities built before 1995: – Concession will expire on July 8, 2015; – 20-year extension may be granted at ANEEL discretion; – Allowed return to be reviewed every four years • Expansion projects can be carried out in three ways: – New concessions to be granted thr

  133. Slide 133: Electricity Distribution: Brazil

    Slide 133: Electricity Distribution: Brazil

    Electricity Distribution: Brazil AES RR AP Ashmore Energy Main controlling MA Energisa (Cat-Leo) groups in Brazil CE RN Endesa AM PA PI PB EDP PE State-owned, Federal AC TO AL RO State-owned, Indiv. BA SE MT State Grupo Rede GO Equatorial Energia Brazil Numbers (2009) MG MS NeoEnergia ES Concessions

  134. Slide 134: 2009 Distribution – Transported Energy (%)

    Slide 134: 2009 Distribution – Transported Energy (%)

    2009 Distribution – Transported Energy (%) Others* 13% AES Equatorial Energia 13% 1% CEB 1% CEEE 2% Energisa CPFL 2% 13% Celg 2% Eletrobras 3% Ashmore Energy 4% Endesa Cemig 4% 10% Celesc 5% Rede Energia Neoenergia 5% 7% EDP Energias do Brasil 5% Copel Light 5% 6% Source: Cemig 134

  135. Slide 135: Electricity Distribution business is the most regulated one

    Slide 135: Electricity Distribution business is the most regulated one

    Electricity Distribution business is the most regulated one • Allowed return on asset approach: – Benchmark WACC: 9.95 (real) • Operating expenses: – Full passed through mechanism: – Energy purchase expenses under certain circumstances. – Yearly inflation adjusted; – Tracking account for offsetting

  136. Slide 136: Electricity Distribution Tariff Review Process

    Slide 136: Electricity Distribution Tariff Review Process

    Electricity Distribution Tariff Review Process PARAMETERS REVENUE FROM BILLING Special EXPENDITURES TO CONSUMERS Obligations + Reinstatement Depreciated Revenue Captive Consumers Depreciation Installment Residential Assets Rate Remuneration of 4.65% Accumulated Capital Total Assets Base Depreciation

  137. Slide 137: Appendix

    Slide 137: Appendix

    Appendix •Regulatory Framework •Others 137

  138. Slide 138: The Collective Work Agreement for 2009–2010

    Slide 138: The Collective Work Agreement for 2009–2010

    The Collective Work Agreement for 2009–2010 The conditions negotiated with the Unions took the following factors into account: • the Tariff Review of Cemig D (Cemig Distribution), which reduced its revenues by 20.81%; • the Tariff Review of Cemig GT’s (Cemig Generation and Transmission) transmission

  139. Slide 139: Glossary

    Slide 139: Glossary

    Glossary • Average outage frequency (FEC): Average number of outages suffered in a given period per consumer, in a given group of consumers. • Debt coverage index: Ebitda divided by total financial expenses in the year. This gives a figure for the company’s capacity to pay debt servicing. • Deferred

  140. Slide 140: Glossary

    Slide 140: Glossary

    Glossary • The CDE (Energy Development) Account: This is a source of subsidies to make alternative energy sources such as wind and biomass more competitive, and promote universalization of electricity services. It is funded by annual payments made by the concession holders for the use of public asse

  141. Slide 141: Investor Relations

    Slide 141: Investor Relations

    Investor Relations Telefone: (55-31) 3506-5024 Fax: (55-31) 3506-5025 Email: [email protected] Website: http://ri.cemig.com.br 141 141

  142. Slide 142: Notes

    Slide 142: Notes

    C-MIG Notes 142

  143. Slide 143: Notes

    Slide 143: Notes

    C-MIG Notes 143

Source: Internet Archive copy of ri.cemig.com.br