  1. Slide 1: Macquarie o & g explorers

    Macquarie o & g explorers January 2014 John Gerstenlauer, COO

  2. Slide 2: - Company overview - Licencing status - operational evolution & technical challenges

    - Company overview - Licencing status - operational evolution & technical challenges - contractual & commercial environment - looking forward

  3. Slide 3: World class assets

    World class assets 3 • 5 discoveries in the Kurdistan Region of Iraq • Share of estimated 19 billion barrels of gross oil-in-place • 20 wells drilled in 4 years across 4 blocks • Shaikan is a major oilfield with 40,000 barrels per day production capacity in 2014 • Assets de-risked by extensive drill

  4. Slide 4: Demonstrated drilling success

    Demonstrated drilling success 4 Shaikan-1 Shaikan-3 Bijell-1 Shaikan-2 Shaikan-4 Shaikan-5 Sheikh Adi-2 Bakrman-1 Ber Bahr-1 Spud Spud Spud Spud Spud Spud Spud Spud Spud Apr-09 Sep-10 Dec-09 Dec-10 May-11 Oct-11 May-12 May-12 Oct-11 Discovery Appraisal Discovery Appraisal Appraisal Appraisal Discove

  5. Slide 5: 2007-2014 Constant evolution

    2007-2014 Constant evolution 5 Shaikan Field Commercial Shaikan crude export Development Plan production from sales and revenue approved Shaikan commenced generation Regional export pipeline to Turkey Exceptional local completed, exports relationships – Move from AIM to the to commence in Q1 essenti

  6. Slide 6: Licencing status in the Kurdistan region of Iraq

    Licencing status in the Kurdistan region of Iraq

  7. Slide 7: Fully Licensed

    Fully Licensed 7 2008 2013 Turkey Turkey Tawk e Iran Iran Taq Taq Khurmala Dome Licenced Licenced Unlicenced Unlicenced Pending negotiation Relinquished

  8. Slide 8: Operational evolution & technical challenges

    operational evolution & technical challenges

  9. Slide 9: Operating timeline

    Operating timeline 9 Key PSC Milestones Key Operating Milestones 2007 Nov: Awarded Shaikan and Akri-Bijeel PSCs Headcount: c.6 2008 Feb/Jun: Acquired 2D seismic on Shaikan and Akri-Bijeel Capex: $10m(1) blocks Headcount: c.44 Nov: Began construction of Shaikan-1 (SH-1) location 2009 Mar: Spudded SH-

  10. Slide 10: Operating timeline

    Operating timeline 10 Key PSC Milestones Key Operating Milestones 2010 Jan: Start the EWT facility Mar: Bijell-1 Discovery Capex: $144m May/Dec: Acquired 3D seismic Headcount: c.132 on Shaikan and Sheikh Adi May: Spud Sheikh Adi-1 Sep: Finish the EWT facility Sep: Spud SH-3 Dec: Spud SH-2 2011 Mar:

  11. Slide 11: Operating timeline

    Operating timeline 11 Key PSC Milestones Key Operating Milestones 2012 Jan: Spud Bijell-3 Apr: Construction of PF-1 Capex: $215m May: Spud Sheikh Adi-2 Headcount: c.162 May: Spud Bakrman-1 Aug: Submitted the Shaikan Jul: Spud Gulak-1 Declaration of Commercial Aug: Spud SH-8 Discovery to the MNR Sep:

  12. Slide 12: Operating timeline

    Operating timeline 12 Key PSC Milestones Key Operating Milestones 2013 May: Ber Bahr-1 discovery (continued) Jun: Approval of the Shaikan Jun: Completed the Capex: $200m Development Plan by the MNR construction of Shaikan PF-1 Headcount: c.202 Jun: Spud SH-7 Jul: First commercial Jul: Spud SH-10 pro

  13. Slide 13: Technical challenges

    technical challenges 13 Drilling in Kurdistan is difficult and occasionally very difficult • Highly indurated carbonates from surface (tophole ROPs are limited) • Time sensitive clastics with substantial mechanical sloughing • Carbonate formations are often intensely fractured, total losses are comm

  14. Slide 14: Contractual & commercial environment

    contractual & commercial environment

  15. Slide 15: Kurdistan Rig market: major changes

    Kurdistan Rig market: major changes 15 On GKP’s entry to the regional rig market in 2008 there were 4 players • Weatherford, AOS, Great Wall, Romfor By early 2014 the regional rig market changed significantly • 29 rig companies on the Ministry of Natural Resources approved list of suppliers • 24-25

  16. Slide 16: Looking forward

    Looking forward

  17. Slide 17: Shaikan: a giant

    Shaikan: a giant 17 • Largest discovery in Kurdistan to date • 30% of 45 billion barrels of discovered resources in Kurdistan • 1,000 meter total Jurassic oil column 3 x London Shard c.300m Approximate area of Brent Field, NNS Shaikan Field, Kurdistan Region of Iraq Source: GKP

  18. Slide 18: Shaikan FDP approval

    Shaikan fdp approval 18 PRODUCTION • 40,000 bopd – short-term production target • 100,000 bopd – Phase 1 production target to be achieved 18 months from date of consistent oil sales; will require additional production facilities DRILLING • Multi-rig development and production well drilling programme

  19. Slide 19: Shaikan FDP concept

    Shaikan fdp concept 19 Source: GKP

  20. Slide 20: First production facility complete

    First production facility complete 20 PF-1 • Complete and commissioned • Commercial production commenced in Jul 2013 and export sales in Jan 2014 • Production capacity to increase to 20,000 bopd in the near term • Export quality crude using gas stripping PF-1 Shaikan 1 Shaikan 3 Shaikan 4 Source: GK

  21. Slide 21: Second production facility nearing completion

    Second production facility nearing completion 21 PF-2 • Modular design similar to PF-1 • Efficiency savings in design & installation • Production capacity of additional 20,000 bopd • Located 15 km from the export pipeline to which it will be linked PF-2 Shaikan 2 Shaikan 5 Shaikan 10 Source: GKP

  22. Slide 22: Exploration continues

    Exploration continues 22 • Successful side track of the Ber Bahr-1 • 5 additional appraisal exploration well flowed • Field Development Plan wells, Bijell-2, -4, -5, -6 & at 2,100 bopd from the approved -7 Jurassic • Shaikan-7, a deep • 3D seismic acquisition • Further well planned in exploration we

  23. Slide 23: Shaikan deep exploration upside

    Shaikan deep exploration upside 23 • Major reservoirs are prognosed beneath the deepest current horizon • Deeper resources are being targeted with Shaikan-7 • The deep Triassic is a commercial reservoir • Potential for significant quantities of light oil in the Triassic • Further potential occurs in

  24. Slide 24: Operator's task is

    Operator’s task is to deliver exploration success and production capacity, while contributing to the economic development of the Kurdistan Region of Iraq

  25. Slide 25: Thank you

    GULF KEYSTONE PETROLEUM LTD. THANK YOU

  26. Slide 26: Disclaimers

    disclaimers 26 The contents of these presentation materials and the accompanying verbal presentation (“Presentation 85 FSMA. These Presentation Materials are exempt from the general restriction set out in section 21 FSMA on the Materials”) has not been approved by an authorised person within the mea

  27. Slide 27: Disclaimers

    disclaimers 27 Investing in any shares of Gulf Keystone Petroleum Limited (“the Company”) involves significant risks, and is suitable only The exploration for and production of oil and gas resources is a capital intensive business. The Company will need to for sophisticated investors who fully under

  28. Slide 28: Disclaimers

    disclaimers 28 Prospects in Kurdistan As an international operator, the Company’s business transactions may not be denominated in the same currencies. To Various international oil and gas companies have explored prospects throughout Kurdistan with varying degrees of the extent that the Company’s bus

  29. Slide 29: Disclaimers

    disclaimers 29 Tax treatment The oil and gas industry historically has experienced periods of rapid cost increases. Increases in the cost of exploration Under current Bermuda law, the Company is not subject to tax on its income or capital gains, and its dividend payments and development would affect

  30. Slide 30: Disclaimers

    disclaimers 30 Oil and gas pricing and demand consequences of any terrorist attacks or any armed conflicts which may result are unpredictable, and the Company The price of and demand for oil and gas is highly dependent on a number of factors, including both domestic and may not be able to foresee ev

  31. Slide 31: Disclaimers

    disclaimers 31 Environmental regulation The Company’s interests and business are subject to the risk of litigation The Group’s operations are subject to environmental regulations promulgated by the Algerian and Kurdistan From time to time, the Company may be subject to litigation relating to its int

  32. Slide 32: Disclaimers

    disclaimers 32 Such factors may negatively affect the market price of the shares. In addition, the risks described elsewhere in this Risk Factors section could materially and adversely affect the price of the shares. AIM is less liquid and more volatile than other major exchanges. The sole trading m

  33. Slide 33: Macquarie o & g explorers

    Macquarie o & g explorers 13 January 2014