  1. Slide 1: CAP Group Update

    CAP GROUP UPDATE Fernando Reitich President & CEO March, 2014

  2. Slide 2: Agenda

    Global industry update Financial performance Future prospects

  3. Slide 3: Ownership Structure

    Ownership Structure Source: CAP, March. 2014 2

  4. Slide 4: Integrated Operations

    Integrated Operations Mining Steel Steel Processing • Production capacity: • Production: 0,7 Mt/y • Production 15 Mt/y • Nominal capacity: 1.45 capacity:400 kt/y • Only large-scale iron Mt/y • Leading steel ore producer in Chile • Domestic market processor in Chile • On track to reach 18 • Focus on

  5. Slide 5: Los Colorados mine

    : » (RST (eS 165 Colorados mine WW pi = ge!

  6. Slide 6: Mining sites

    Mining sites El Laco Punta Totoralillo Port CAP Mining has three Cerro Negro Norte different areas of operation in Desalination Plant Copiapó the north of Chile, Magnetite Plant located around the cities of: • La Serena • Vallenar • Copiapó Los Colorados Guacolda II Port Cities Vallenar Pellets Plan

  7. Slide 7: Iron ore mining operations

    Iron ore mining operations Elqui Valley / La Serena  El Romeral Mine / 4.0 million tons  Pellet Feed, Lumps and Fines  Infrastructure: Guayacan Port (165.000 dwt) and Railroad (38 km) Huasco Valley / Vallenar  Los Colorados Mine - Pellet Plant / 7.2 million tons  Pellets, Pellet Feed, Lumps and

  8. Slide 8: Mining products

    Mining products BF and DR Pellets (Fe 65% - 66%) Lumps (Fe 62%) Pellet Feed (Fe 67% - 68%) Fines (Fe 62%) 7

  9. Slide 9: Mining Property

    Mining Property Ranking 2012 Hectares in exploration concessions - Chile N° Company Hectares % 1 BHP Chile Inc. 2.219.500 12,38 2 Codelco 969.400 5,41 3 Antofagasta Minerals S.A. 736.800 4,11 4 Teck Exploraciones Mineras Chile Ltda. 728.600 4,07 5 CAP 609.400 3,4 Ranking 2012 Hectares in exploitatio

  10. Slide 10: Resources and reserves of magnetite ore

    Resources and reserves of magnetite ore As a result of continued successful exploration campaigns, iron ore resources have increased progressively over the years, reaching 6.350 million tons in 2013 Total Mineral Resources Mine / Deposit Reserves (2) (1) Mine Location Ton Grade (% Fe) Ton Grade (% F

  11. Slide 11: Mining shipments and markets

    Mining shipments and markets Shipments 14000,0 12.246 12.086 12000,0 11.469 10.145 10.213 10000,0 8000,0 Th. MT 7.251 6000,0 4000,0 2000,0 ,0 2008 2009 2010 2011 2012 2013 Shipments by markets and products (CY 2013) Self - fluxing DR H&L Lumps, 8% pellets, 14% Indonesia, pellets, 4% Sinter feed, 8%

  12. Slide 12: Cash cost curve (2014)

    Cash cost curve (2014) Global production cost • CAP Mining is a low cost producer of high grade magnetite concentrate • Mine depletion will lead to higher CAP demand for high grade pellet feed • Environmental and economic constraints support the increased need for magnetite concentrate Pellet feed g

  13. Slide 13: Steel

  14. Slide 14: Steel - Location

    Steel - Location • Strategically located. Good logistics for raw materials, water and energy. • Pier available more than 95% of the year. • Part of an industrial area, near to universities and technical educational centers. San Vicente Bay. Talcahuano - Chile Huachipato Steel Mill 13

  15. Slide 15: Steel focus on long products only

    Steel focus on long products only • Worldwide low capacity utilization has destroyed steel producers margins in the last years • During 2013 the company shifted focus to long products only, aiming to exploit its competitive advantages • HRC: Negative margins due to oversupplied market and subsidized

  16. Slide 16: Steel products and shipments

    Steel products and shipments Shipments and prices 2.500 1.117 1.200 883 1.000 2.000 799 811 699 737 800 1.500 US$/Ton Th. tons 1.161 1.124 600 1.113 922 859 1.000 671 (1) 400 500 200 0 0 2008 2009 2010 2011 2012 2013 Shipments Prices (1) 2010 production was affected by an earthquake Product portfoli

  17. Slide 17: Steel – Key considerations

    Steel – Key considerations  Strong market position based on high quality products and good logistics that over perform foreign competitors  Independent player in Latin America Market leadership  Undisputed leadership in Chilean market, 49% share on long products target market in 2013  Iron ore a

  18. Slide 18: Steel processing

    LS | feat | leYe) Cc 7,3 Wn 8 eae 9 | ey S me ro) \ #; — 7 Wii ~ RE

  19. Slide 19: Steel Processing

    Steel Processing o Main flat steel importer of the Pacific coast of South America o Creates value-added solutions for the construction, industry and infrastructure sectors in Chile, Peru and Argentina o Chile is LATAM´s most intensive user of steel in construction Shipments and prices 1.300 600 1.25

  20. Slide 20: Steel Processing – Key considerations

    Steel Processing – Key considerations • CAP Steel Processing is the largest processor and seller of flat steel products in the Market Pacific coast of South America Leader • Revenues of MUS$ 365 per year, with a market share of 30%. • World class plants and equipment • From a manufacturer of steel t

  21. Slide 21: Agenda

    Company overview Financial performance Future prospects Company overview [Siobal industry update [Finencialperformence Future prospects Final remars 20

  22. Slide 22: Short-term growth in China

    Short-term growth in China o GDP growth reached 7.7% in year 2013 o Growth lead by domestic demand should continue, even though fixed assets investment slows. o This divergent development will continue in 2014 Expect 7.5% YoY GDP growth in 2014 21

  23. Slide 23: Demands of the Chinese urbanization and development process

    Demands of the chinese urbanization and development process 22

  24. Slide 24: Iron ore quality evolution

    Iron ore quality evolution • Crude iron ore grade is dropping • Mine depletion will lead to higher demand for high grade concentrates Production from key CISA Chinese iron ore producers (Mt) Magnetite concentrate 70 68 Average grade of hematite fines 66 (Pilbara, Australia) 64 62 60 58 56 1998 2000

  25. Slide 25: Preference for higher quality iron ore

    Preference for higher quality iron ore Relative price performance of ores of different grades SOURCE: Macquarie, commodities research 24

  26. Slide 26: Global steel demand growth

    Global steel demand growth o Global apparent finished steel demand will grow from 1.5 bn tons in 2014 to 1.7 bn tons by 2018 (implied 3% CAGR) (1) Other Developing includes CIS, MENA, Sub-Saharan Africa, Latin America, India, and Other Asia SOURCE: WSA; McKinsey Steel Demand Model Oliver Ramsbottom,

  27. Slide 27: Global steel capacity utilization

    Global steel capacity utilization o Nevertheless, world capacity utilization has been below 80% for the last 5 years, thereby practically destroying the margins of the steel production industry o Most of the excess capacity is concentrated in China. Current efforts to diminish this excess capacity h

  28. Slide 28: Steel market in Chile

    Steel – Key Steel considerations market in Chile 2011 steel per capita consumption (kg per capita) Steel consumption per capita 700 1.074 Finished steel consumption per capita (Kg) Japan 600 Singapore 500 400 580 Greece Australia 300 Poland 425 France Iceland Chile ('25) 295 200 New Zealand Mexico 1

  29. Slide 29: Agenda

    Agenda 28

  30. Slide 30: CAP - Financial evolution

    CAP - Financial evolution USD Million 2008 2009 2010 2011 2012 2013 Sales 1.972 1.375 1.994 2.787 2.470 2.297 EBITDA 534 128 740 1.184 764 708 EBITDA Margin 27,1% 9,3% 37,1% 42,5% 30,9% 30,8% Net Income 291 25 590 442 234 184(1) Cash 379 393 981 883 711 309 Gross Financial debt 880 907 1.001 628 719

  31. Slide 31: EBITDA contribution by business

    EBITDA contribution by business 100% 97% 98% 94% 94% 80% 77% 60% 40% 18% 20% 6% 6% 8% 5% 4% 0% 0% 2009 2010 2011 2012 2013 -3% -2% -2% -20% Iron Steel Steel Processing (1) EBITDA: Gross Margin – S&AE + Depreciation and Amortization + Dividends received in cash, over the last twelve months 30

  32. Slide 32: Agenda

    Global industry update Financial performance 31

  33. Slide 33: Mining – Future Prospects

    Mining – Future Prospects El Laco Totoralillo Port Project Production Est. Capex CNN Mt MUS$ Desalination Plant Copiapó Magnetite Plant Magnetite Plant 1 Pf 110 Expansion 6,5 Pf 1.700 Tofo 13,5 Pf 2.900 Guacolda Port Los Colorados Vallenar Pellets Plant 6 Pf 1.600 Alcaparra Alcaparra Algarrobo 135 K

  34. Slide 34: Mining – Future Prospects - Magnetite Plant expansion

    Mining – Future Prospects - Magnetite Plant expansion o The project consists in designing and building a third grinding and concentration line at the existing magnetite plant, to increase production in 1 Mt/y. o Some of the expected benefits are: • Increased volumes of preconcentrate from Los Colora

  35. Slide 35: Mining – Future Prospects - Tofo

    Mining – Future Prospects - Tofo 297 297 500 298 500 000 298 000 E E E E Investment (E) : 1,700 – 2,900 MUS$ N 6765000 • Greenfield N 6764500 Production: 6.5-13,5 Mt/y of pellet feed N 6764000 SIMBOLOGY S Waste 10≤Fe%<15 N 15≤Fe%<26 Stage: Conceptual engineering 6763500 26≤Fe%<45 NIVEL 1110 Fe% ≥ 45

  36. Slide 36: Mining – Future Prospects - Alcaparra Iron/Copper

    Mining – Future Prospects - Alcaparra Iron/Copper Iron ore body Investment (E): 1,600 + 300 MUS$ Simbology Production: 6 Mt/y of pellet feed Topography 135 kt/y of copper concentrate Drilling Fe% ≥ 45 Stage: Advanced exploration 25 ≥ Fe% < 45 15 ≥ Fe% < 25 Exploratory metallurgy 10 ≥ Fe% < 15 Núcleo

  37. Slide 37: Mining – Future Prospects – Colorados Expansion

    Mining – Future Prospects – Colorados Expansion Investment : 500 MUS$ • Brownfield Production: 4 Mt/y of fines Stage: Basic engineering Resources Volume Fe Actual final pit LEYENDA 2012 [Mt] [%] Topografía Nov-13 SIMBOLOGY Pit Final 2008 Measured 694 31,5 Actual level Pit Final 2013 Final pit Indica

  38. Slide 38: Future prospects - Infrastructure – Desalination Plant

    Future prospects - Infrastructure – Desalination Plant Totoralillo Port Desalination Plant Phase 3 under discussion S/S Totoralillo with Pucobre: up to 130 l/s S/S CNN CNN Photovoltaic Plant Amanecer Solar CAP CNN Aqueduct 120 lt/s CAP transmission line Copiapó Cardones node Tierra Amarilla Aqueduct

  39. Slide 39: Future prospects - Infrastructure - Desalination Plant

    Future prospects - Infrastructure - Desalination Plant • Desalination Plant and CNN Aqueduct is operating from Feb 2014 and will provide 120 l/s to CNN • Tierra Amarilla Aqueduct will be completed in April 2014 and will transport: • 80 l/s to CMP s magnetite plant • 170 l/s to Caserones mine • CAP(5

  40. Slide 40: Future prospects - Infrastructure - Ports

    Future prospects - Infrastructure - Ports CAP Ports Punta Totoralillo: Guayacán: • 29 km north of Caldera • Herradura bay, Coquimbo • Iron ore shipping • Iron ore shipping • 200,000 dwt • 165,000 dwt Guacolda II: Huachipato: • Located in Huasco City • Talcahuano bay • Iron ore shipping • Unloading c

  41. Slide 41: Infrastructure – Providing services to third parties

    Future prospects - Infrastructure – Providing services to third parties CAP Mining Totoralillo Port • Third-party iron ore loading and storage capacity at Totoralillo port is 3 Mt/y • Loaded tonnages: 2 Mt in 2013 and 2,5 Mt in 2014 • EBITDA generation: 20 MUS$ in 2013 and 22 MUS$ in 2014 • With the

  42. Slide 42: Future prospects - Infrastructure – Solar Energy

    Future prospects - Infrastructure – Solar Energy Totoralillo Port Desalination Plant S/S Totoralillo S/S CNN CNN Photovoltaic Plant Amanecer Solar CAP CNN Aqueduct 120 lt/s CAP transmission line Copiapó Cardones node Tierra Amarilla Aqueduct Caserones 170 lt/s Magnetite Plant 80 lt/s 41

  43. Slide 43: Future prospects – Infrastructure - Solar Energy

    Future prospects – Infrastructure - Solar Energy • 100 MW Photovoltaic power plant fully committed to CAP (PPA) • Located nearby CNN Mine • CAP retains call option for up to 40% of the equity • Financial hedge • Compliance with NCRE law • Connected to a 142 km long 220 kv transmission line owned by

  44. Slide 44: Agenda

    Agenda 43

  45. Slide 45: Final remarks

    Final remarks • CAP is advancing through sustainable development based on competitive advantages • Concurrently, cost reduction initiatives and productivity improvements will be at the center of management efforts • CAP Mining: operational improvements; achievement of overcapacity; … • CAP Steel: op

  46. Slide 46: Final remarks

    Final remarks • CAP Mining • On track for expansion of 50% production capacity to 18 Mt/y • Ample portfolio of future prospects based on abundant reserves; further expansion to be defined in 2014 • Global environmental and economic constraints support the growing need for CAP´s magnetite concentrate

  47. Slide 47: CAP Group Update