  1. Slide 1: Transmission Access Review - further analytical work

    Transmission Access Review - further analytical work Presentation to National Grid Seminar 10 April 2008 Robert Hull Director, Transmission

  2. Slide 2: Agenda

    Agenda • Background • Introducing further independent analytical work • Moving forward 2

  3. Slide 3: Transmission Access - Challenges

    Transmission Access - Challenges • Existing transmission system connects c80GW of generation to meet around 60- 65GW peak demand • To meet 2020 targets, an additional 25GW+ of renewable capacity: – Plus thermal (fossil) back up plant given intermittency – Plus circa 20GW of existing generation is ex

  4. Slide 4: Transmission Access – the key issues

    Transmission Access – the key issues • Current network is designed for large scale conventional generation connection and planning standards reflect this – Current planning standards say build more capacity for renewables, nuclear as they connect • Building new infrastructure capacity – Expensive -

  5. Slide 5: TAR initial conclusions - the barriers to effective transmission access

    TAR initial conclusions - the barriers to effective transmission access • Funding not the issue: GEMA has made the necessary transmission investment funding available. But planning constraints for generation and transmission are slowing investment • Existing ‘first come first served’ connection appr

  6. Slide 6: TAR initial conclusions - potential improvements

    TAR initial conclusions - potential improvements Access reform • NG should manage the queue and allocate available capacity to projects able to make use of it • NG should improve connection information provided to generators (where there is spare capacity) so that their siting decisions are better i

  7. Slide 7: NG’s role and incentives

    NG’s role and incentives • Getting the right commercial incentives on NG (and SP and SHETL) is vital in improving transmission access – NG under SO incentives exposed to short term system constraint costs – NG, SP and SHETL do not provide firm connection dates or compensation if delayed. They have l

  8. Slide 8: Ofgem’s current thinking

    Ofgem’s current thinking • Protecting customers’ interests through reform is vital – Long term user commitment from generators to underpin new investment is non- negotiable to avoid significant transfer of stranding risk to customers – Industry shouldn’t waste time developing models that shift all o

  9. Slide 9: Ofgem’s vision for transmission access arrangements

    Ofgem’s vision for transmission access arrangements Transmission investment would be delivered faster if NG had more reliable information about future transmission demand • Access arrangements should be based on : – User commitment: generators make financial commitments to NG and signal their needs

  10. Slide 10: Further analytical work since Interim Report

    Further analytical work since Interim Report • The Interim Report set out a holistic approach for assessing models of access reform – breaking down into constituent features or “building blocks” including: – Nature of access rights – Allocation – Pricing – Secondary trading • Poyry and IPA commissio

  11. Slide 11: Moving Forward

    Moving Forward • The purpose of producing this analysis is to: – Inform industry discussion on transmission access models; and – Inform our development of the final recommendations • Analysis ultimately represents our consultants’ independent views • We are not bound to recommending one particular s