Slide 1: Seventh Annual Conference on Carbon Capture & Sequestration
Seventh Annual Conference on Carbon Capture & Sequestration Post Combustion/Retrofit Systems Recent Initiatives and the Current Status of MHI’s Post Combustion CO2 Recovery Process; Aiming to Realize the Rapid Commercial Application of CCS Masaki Iijima & Ronald Mitchell May 5 – 8, 2008 • Sheraton S
Slide 2: Contents
CONTENTS 1. MHI’s Commercial Achievements 2. MHI’s Long Term 10 t/d CO2 Capture Demonstration Tests from a Coal Fired Boiler 3. MHI’s CO2 Recovery Technology: Process Improvements & Heat Integration 4. Phased Approach to Commercialization for Coal Application 5. MHI’s Scope in a CCS Project 6. Concl
Slide 3: MHI's Operating Commercial CO2 Capture Plants
1. MHI’s Commercial Achievements MHI’s Operating Commercial CO2 Capture Plants Malaysia India Client: Petoronas Client: IFFCO Start-up: 1999~ Location: Aonla CO2 Source: Start-up: Dec 2006~ Nat. Gas Reformer CO2 Source: Capacity: 200 t/d Nat. Gas Reformer Product: Urea Capacity: 450 t/d Product: Ure
Slide 4: MHI's Recently Awarded Commercial Projects
1. MHI’s Commercial Achievements MHI’s Recently Awarded Commercial Projects OTHER Abu PROJECTS India Bahrain ‘Asia’ China Dhabi Under Under Under Project FEED Project Status Construction Construction Construction Complete Awarded Flue Gas Nat. Gas. Nat. Gas. Nat. Gas. Nat. Gas. Nat. Gas. Source Refo
Slide 5: Coal Fired Long Term Demonstration Plant
2. MHI’s long term 10 t/d CO2 capture demonstration tests from a coal fired boiler Coal Fired Long Term Demonstration Plant Plant Outline Solvent : KS-1 Capacity : 10 T/D Feed Gas : Coal Fired Boiler (14.1 v% CO2) Start-up : July 2006 Location : Nagasaki, Japan Operational experiences Increased un
Slide 6: Coal Fired Long Term Demonstration Plant - Results
2. MHI’s long term 10 t/d CO2 capture demonstration tests from a coal fired boiler Coal Fired Long Term Demonstration Plant - Results Test Item Result • Achieve long term stable operation 9 >5000 hours of near continuous operation • Confirm effect of various impurities on CO2 9 Advanced know-how of
Slide 7: Process Flow for Amine Absorption
3. MHI’s CO2 Recovery Technology: Process Improvements & Heat Integration Process Flow for Amine Absorption Boiler DeNOx Particulate Flue Gas Capture FGD Facility Stack Outlet CO2 Purity 99.9 % Flue Treated Flue Gas Gas CO2 CO2 Compression Product Capture & Dehydration ABSORBER STRIPPER C.W. (Regene
Slide 8: MHI's Flue Gas CO2 Recovery Improved Process
3. MHI’s CO2 Recovery Technology: Process Improvements & Heat Integration MHI’s Flue Gas CO2 Recovery Improved Process Recovered CO2 15% steam consumption reduction over MHI’s conventional process Heat Recovery & Stripper Advanced process demonstrated at MHI’s Solvent Nanko Pilot Plant & Commerc
Slide 9: MHI Heat Integration Concept (Base Case)
3. MHI’s CO2 Recovery Technology: Process Improvements & Heat Integration MHI Heat integration Concept(Base Case) ① LP Steam extraction from the LP Turbine ② Recovery of overhead condenser heat LP Turbine HP/MP Turbine Air Heater ESP Boiler ① ② Condenser Reboiler Regenerator Condenser Boiler Feed Wa
Slide 10: MHI Heat Integration Concept
3. MHI’s CO2 Recovery Technology: Process Improvements & Heat Integration MHI Heat integration Concept MP Turbine 900 C HP Turbine 800 A D Extraction to Reboiler G 700 Enthalpy B Power loss of (kcal/kg) LP Turbine steam turbine 600 E Steam Condensing E Curve Utilize this heat for 500 the reboiler Wa
Slide 11: CO2 Recovery Plant Power Output Penalty and Heat Integration Options
3. MHI’s CO2 Recovery Technology: Process Improvements & Heat Integration CO2 Recovery Plant Power Output Penalty Assessment and Heat Integration Options; 1) Base Case + 2) Recovery of Compression Heat 3) Recovery of Flue Gas Heat Power output penalty of CO2 capture and Net output improvement with h
Slide 12: Multi-Pollutant Test Plant (FGD & CO2 Capture)
3. MHI’s CO2 Recovery Technology: Process Improvements & Heat Integration Multi-Pollutant Test Plant (FGD & CO2 Capture) Absorber 1 by 1 Scale Test Facility (400 MW equivalent) Absorber Spray pipes Fan 32 m Recirculation Pumps Commercial Scale Tests • Q1 2008 – Extensive Liquid Distribution Tests •
Slide 13: Phased approach to commercialization for Coal application
4. Phased approach to commercialization for Coal application MHI’s Operating Experience • Pilot plants (1-2 t/d) • Small scale demonstration plant (10 t/d) • Commercial plants (200-450 t/d) • Experience with natural gas and coal Full scale commercial PCC Demo US PCC Demo Germany 1 t/d 2 10 200 330 4
Slide 14: Phased approach: 100 tpd and 500 tpd PCC plants
4. Phased approach to commercialization for Coal application •100 tpd PCC pilot plant with E.ON Energie in Germany •500 tpd PCC demo plant in US (details announced later this year) Year 03 04 05 06 07 08 09 10 11 12 13 14 15 16 1 MTPD PCC Pilot Plant 10 MTPD PCC Pilot Plant 100 MTPD PCC Pilot Plant
Slide 15: MHI Can Supply All Technology – Advanced Integration
5. MHI’s Scope in a CCS Project Steam Turbine FGD CO2 CO2 CO2 Boiler SCR EP Capture Compression Transport NOx Dust SOx CO2 Centrifugal Compressors Coal Fired Power Station FGD CO2 Capture Plant AB S O RB E R STRIPPER CO O L E R DCFS MHI Can Supply All Technology – Advanced Integration
Slide 16: Advantages of Post Combustion CO2 Capture
6. Conclusions Advantages of Post Combustion CO2 Capture ① Is applicable for the current, global PC fleet ② Offers high degree of flexibility – is adaptable and cost competitive with other technologies ③ Operation at atmospheric pressure – safe and does not require exotic materials ④ Produces highly
Slide 17: Strength of MHI in the emerging CCS industry
6. Conclusions Strength of MHI in the emerging CCS industry 9 Extensive PCC R&D History - >18 years 9 Ongoing and long term solvent development - >200 solvents 9 CO2 capture experience from natural gas boiler, natural gas turbine, natural gas steam reformer and coal fired boiler flue gas 9 Multiple
Slide 18: Need for Carbon Capture & Storage
6. Conclusions Need for Carbon Capture & Storage ① Coal will remain a dominant fuel for electric power generation ② Coal with CCS technology can play an important part in CO2 mitigation ③ Governments must continue to support CCS - regulatory certainty and incentives for first stage commercial CCS pl