Apa Group · ASX:APA

Apa — Investor Day (November 2013)

22 slides from Apa's investor day presentation, Nov 14, 2013

  1. Slide 1: APA Group Investor Day: Lifecycle of pipelines

    MORE THAN THE SUM OF OUR PARTS APA Group Investor Day Lifecycle of pipelines ‐Technical presentations 14 November 2013 Sydney Disclaimer This presentation has been prepared by Australian Pipeline Limited (ACN 091 344 704) the responsible entity of the Australian Pipeline Trust (ARSN 091 678 778) and

  2. Slide 2: Agenda

    Lifecycle of pipelines Kevin Lester – Infrastructure Development Mark Fothergill – Infrastructure Development Edwin De Prinse ‐ Transmission Operations APA Group Investor Day 2013  3 Agenda  Pipeline construction – Kevin Lester – Group Executive Infrastructure Development  Pipeline expansion – Ma

  3. Slide 3: Pipeline construction

    Pipeline construction  Construction planning  Activities during construction  Special crossings  Restoration  Pipeline easements  Pipeline integrity APA Group Investor Day 2013  5 Construction planning APA Group Investor Day 2013  6

  4. Slide 4: Activities during construction

    Activities during construction APA Group Investor Day 2013  7 Activities during construction Pipe unloading Clearing Pipe stringing Pipe bending Welding Non‐destructive testing APA Group Investor Day 2013  8

  5. Slide 5: Activities during construction; Special crossings

    Activities during construction Gritblasting Joint coating Trenching Padding Lower in Backfill & Restoration Hydrotesting APA Group Investor Day 2013  9 Special crossings APA Group Investor Day 2013  10

  6. Slide 6: Restoration; Pipeline easements

    Restoration Existing Easement Construction of looped pipeline APA Group Investor Day 2013  11 Pipeline easements  Pipelines require a Pipeline Licence from relevant State regulator – Licenses only issued when key approvals and all landowner agreements in place – Ability to compulsorily acquire eas

  7. Slide 7: Pipeline integrity

    Pipeline easements APA Group Investor Day 2013  13 Pipeline integrity  Design, construction and operations to relevant standards  50 ‐ 80 year design life  Factory applied coatings  Joint coating to complement factory coating  Coating drainage tests  Weight coating and concrete slabbing  Cor

  8. Slide 8: Pipeline expansion

    Pipeline expansion Mark Fothergill General Manager Infrastructure Strategy & Engineering APA Group Investor Day 2013  15 Pipeline expansion  Capacity and project registers How to get more through your assets  Expansion options – Add compression – Increase maximum operating pressure – Looping a pi

  9. Slide 9: Capacity and project registers; Expansion - add compression

    Capacity and project registers  Identify customer requirements including level of service flexibility Maximum  Capacity determination Pressure – Pipeline modelling platforms – Validation and tuning of simulations  Project cost and schedule register – Extensive knowledge of cost and scope for pipe

  10. Slide 10: Expansion - increase pressure and looping a pipeline

    Expansion ‐ increase operating pressure  If the pipeline and associated facilities are Increase maximum operating pressure appropriately pressure rated, the 11000 operating pressure of the pipeline can be Increased Maximum 10000 increased Pressure 9000 PRESSURE (KPA) 8000 Example of increased press

  11. Slide 11: In-pipe storage; Creating a bi-directional pipe

    In‐pipe storage‐ swapping throughput to storage  In‐pipe storage is achieved by allocation Maximum of some throughput services to a storage Maximum Pressure service Pressure  Customer typically has complete flexibility over their withdrawals and in‐pipe storage level Example peaking power station:

  12. Slide 12: Benefits of the east coast grid

    Benefits of the east coast grid  Roma Brisbane pipeline converted from flow control to pressure control. – Pressure control maintains a constant high pressure at Wallumbilla which results in an increase in the firm throughput capacity of the RBP  Storage services can be relocated from congested pi

  13. Slide 13: Efficient design - VIC/NSW pipeline; Gas transmission Operations

    Efficient design – VIC / NSW pipeline MAOP upgrade Euroa compressor station APA Group Investor Day 2013  25 Gas transmission Operations Edwin De Prinse General Manager Transmission Operations APA Group Investor Day 2013  26

  14. Slide 14: Gas transmission operations: Understanding the scale

    Gas transmission operations  Scale of our operations  What it takes to manage and operate a pipeline  Operating the east coast grid APA Group Investor Day 2013  27 Understanding the scale 0.415GJ or 0.000415TJ APA Group Investor Day 2013  28

  15. Slide 15: Understanding the scale

    Understanding the scale (Dandenong LNG = 750 tankers) 0.8TJ X 2,000 1 LNG tanker = 16 tonnes APA Group Investor Day 2013  29 Understanding the scale In VIC on a cold day, up to 1,200TJ/day is transported through our pipelines As much as  1,600 LNG tankers or  3 million BBQ bottles per day APA Gro

  16. Slide 16: Understanding the scale; Compressors

    Understanding the scale In QLD on the RBP we can deliver over 220 TJ/day  over 275 LNG tankers driving into Brisbane APA Group Investor Day 2013  31 Compressors  Increase the throughput and capacity of pipelines  300 kW compressors at Iona 9,860 KW units being installed at Moomba and Wallumbilla

  17. Slide 17: Compressors; What it takes to operate a pipeline

    Compressors  Each Moomba compressor unit has the horsepower of 50 Falcons or Commodores per unit  3 new compressors at Moomba, has the combines horsepower of 150 Falcons or Commodores APA Group Investor Day 2013  33 What it takes to operate a pipeline  Capital intensive business  For every $100

  18. Slide 18: SIB capex; Maintenance

    SIB capex  Pipeline SIB budget is for – Aged or worn out components – Parts where spares are no longer available – Upgrade older control systems – Corrosion protection equipment – Plant and motor vehicles – Pigging and pipeline inspection  Typically older pipelines require more SIB capex APA Group

  19. Slide 19: Control Room; Pipeline maintenance

    Control Room  Control rooms operate and oversee the pipelines  Plant and Equipment – Start and stop compressors – Manage flows – Monitor alarms – Initiate response – Manage line pack and metering issues  Personnel – Issue Field Work Permits – Oversee travel in outback areas – Field maintenance in

  20. Slide 20: In-line inspection and repair; Emergency response

    In‐line inspection and repair  Inspection device is put into pipeline  Data is retrieved RoCD2 pig being loaded into the Moomba Sydney Pipeline  Field crews excavate live pipeline  Effect repairs “live”, no interruption to flow APA Group Investor Day 2013  39 Emergency response Two stage respon

  21. Slide 21: ...and doing it safely; Benefits of scale

    …and doing it safely  To deliver a zero harm work environment through alignment of HSE processes, mindsets and capabilities  To ensure compliance with the HSE aspects of ASX Principle 7 (Recognise and Manage Risk) – Identify, assess, monitor and manage risk – Identify material changes to the compa

  22. Slide 22: Summary; For further information contact

    Summary  Reliable operations  In‐house expertise  Benefits of scale  Key focuses – Cost effectiveness – Reliability – Safety APA Group Investor Day 2013  43 For further information contact Chris Kotsaris – Head of Delivering Australia’s Energy Investor Relations and Communications, APA Group Te

APA Group — Investor Day (November 2013) on 6ix