Slide 1: Peak/New Cobar CCC Presentation
Peak/New Cobar CCC Presentation 25 May 2026 ASX Code: AMI
Slide 2: Acknowledgement of Country
Acknowledgement of Country • Aurelia Metals Ltd respectfully acknowledges the Ngiyampaa Nation as the Traditional Custodians of this land – both past and present. • We know this land has history, custodians and stories, spanning tens of thousands of years, that endure to this day. • We pay our respe
Slide 3: July – September 2025
July – September 2025 data CCC Presentation
Slide 4: Safety is at the core of our business
Safety is at the core of our business Work, Health and Safety January – March 2026 Peak has had 1 recordable injury this quarter 1 x arm injury in March which required surgical intervention. Behavioral safety program commenced and was well received by the workforce. Next quarter will have a high foc
Slide 5: Environment & Community
Environment & Community January – March 2026 ASX Code: AMI
Slide 6: Community Stakeholder Engagement Strategy
COMMUNITY STAKEHOLDER ENGAGMENT STRATEGY We are preparing the Community Stakeholder Engagement Plan based on existing community involvement . The Strategy must be submitted to DPHI by 10 October 2026. • Based on positive and negative social impacts identified in the EIS Social Impact Assessment. • E
Slide 7: Engagement Activities
ENGAGEMENT ACTIVITIES Opportunities to talk face-to-face, share what’s going on at the mines, ask questions, share job information. Aurelia is available through: • Community Consultative Committee • Six monthly community meetings • Aurelia Community Hub – 23 Marshall Street • Community Events (eg. C
Slide 8: Supporting a Sustainable Cobar Community
SUPPORTING A SUSTAINABLE COBAR COMMUNITY Aurelia provides direct financial support through the Community Grants program and Cobar Shire Council Planning Agreement Contributions • Every community grant application will also be assessed on the following guiding principles: • Is the operation located w
Slide 9: Local Participation and Procurement Program
LOCAL PARTICIPATION AND PROCUREMENT PROGRAM • Our procurement policy evaluates contracts on several factors including safety, scalability and ability to deliver a quality product • Local businesses are invited to participate in tendering • Cobar based business are considered to have an advantage wit
Slide 10: Training Skills and Enhancement Opportunities
TRAINING SKILLS AND ENHANCEMENT OPPORTUNITIES Aurelia participates in developing the skills of locals through the following: • Work experience opportunities • Apprenticeships targeted at residential applicants • Supporting Schools with the Science and Engineering Challenge • School based traineeship
Slide 11: Peak Mines Environmental Incidents, Complaints & Initiatives
Peak Mines Environmental Incidents, Complaints & Initiatives January – March 2026 • 5 blast complaints received January – March 2026 data CCC Presentation
Slide 12: January - March 2026 Blast Vibration
mm/s 0 1 2 3 4 5 6 7 8 9 10 3/01/2026 5/01/2026 7/01/2026 9/01/2026 11/01/2026 13/01/2026 15/01/2026 October – December 2025 data CCC Presentation 17/01/2026 19/01/2026 21/01/2026 New Occ 23/01/2026 25/01/2026 Open Cut - West 27/01/2026 29/01/2026 31/01/2026 2/02/2026 Fort Bourke 4/02/2026 Great Cob
Slide 13: October – December 2025
October – December 2025 data CCC Presentation
Slide 14: Dust Deposition Gauges (EPL)
Dust Deposition Gauges (EPL) 7 6 5 Insoluble Solids (g/m2/month) 4 3 2 1 0 Apr-25 May-25 Jun-25 Jul-25 Aug-25 Sep-25 Oct-25 Nov-25 Dec-25 Jan-26 Feb-26 Mar-26 Axis Title DM1 DM2 DM3 DM4 Bimbimbie Dellavale DM1 annual Ave DM2 Annual Ave DM3 Annual Ave DM4 Annual Ave Bimbimbie Annual Ave Dellvale Annu
Slide 15: Dust Deposition Gauges
Dust Deposition Gauges 4.5 4 3.5 3 Insoluble solids (g/m2/month) 2.5 2 1.5 1 0.5 0 Apr-25 May-25 Jun-25 Jul-25 Aug-25 Sep-25 Oct-25 Nov-25 Dec-25 Jan-26 Feb-26 Mar-26 GC1 GC2 GC3 GC4 GC1 annual Ave GC2 Annual Ave GC3 Annual Ave GC4 Annual Ave October – December 2025 data CCC Presentation
Slide 16: Projects Update
Projects Update ASX Code: AMI
Slide 17: Projects: Great Cobar Development
Projects Great Cobar Development
Slide 18: Projects: Optimisation – Tails Thickener
Projects Optimisation –Tails Thickener
Slide 19: Projects: Historic Dewatering
Projects Historic Dewatering • Pipeline has been commissioned and running raw water • Electrical connection with Essential Energy in progress • Electrical Pump and control panel for historic shaft will be installed in June.
Slide 20: Projects: HV Access – Peak Way & Intersections
Projects HV Access – Peak Way & Intersections • Design & Engineering – final review by tfNSW roads • Construction has commenced and will transition to include the internal truck access widening • Signage is on main road to Peak access. • Proprietary road will commence at the completion of the Peak a
Slide 21: July – September 2025
July – September 2025 data CCC Presentation
Slide 22: July – September 2025
July – September 2025 data CCC Presentation