  1. Slide 1: Northwestern Energy ETAC Meeting #5, 2025 MT IRP Planning Cycle

    Northwestern Energy ETAC Meeting # 5 2025 MT IRP Planning Cycle December 9, 2024

  2. Slide 2: Modeling Inputs

    Thank you Modeling Inputs

  3. Slide 3: Base Portfolio

    Base Portfolio • NorthWestern’s current generation portfolio • Includes 222MW Avista acquisition and 370MW Puget Acquisition in Colstrip Units 3 and 4 starting January 2026 • Colstrip operates until 2042 • Does not include QF’s in the current queue as NorthWestern cannot accurately project which QFs

  4. Slide 4: Capacity Position Spreadsheet

    Depreciable life of owned assets or expiration of contracted assets • Capacity Position Spreadsheet • CAO August 2024 • https://reddi.mt.gov/prweb/PRAuth2/app/reddi/69MPqGeS_UTZWHGFH6YedHAuE3y JxESf*/!STANDARD

  5. Slide 5: Candidate Resources

    "Candidate Resources Generation Storage Duration Capability No. Resource Type Scale (MW,,.) Scale (MW.,,) fiecweai (MWh) 1 |Wind 100 - - - 2 [Wind 300 - - - 3 |Solor pv 100 4 |Solar PV 300 - - - 5 |BESS - 25 2 50 6 |BESS - 25 5 125 7 =|BESS - 50 4 200 8 |BESS* - 50 5 250 9 |BESS : 50 g 400 10 |BESS

  6. Slide 6: Forward Curves

    Forward Curves • Gas • AECO • CIG • Electric • Mid-C Heavy Load • Mid-C Light Load • Coal

  7. Slide 7: Accreditations

    Accreditations • Western Resource Adequacy Program – Qualifying Capacity Contributions • WRAP Business Practice Manuals • Primarily WRAP BPM 105-Qualifying Resources • https://www.westernpowerpool.org/private- media/documents/V1.0_BPM_105_Forward_Showing_Qualifying_Resourc es_12-07-2023.pdf

  8. Slide 8: Constraints

    Constraints • Transmission • Technology • Overbuild

  9. Slide 9: Load Forecasting

    Thank you Load Forecasting

  10. Slide 10: New Resource Cost Modeling

    Thank you New Resource Cost Modeling

  11. Slide 11: 2023 MT IRP New Resource Chart

    2023 MT IRP New Resource Chart

  12. Slide 12: Construction Timelines

    Construction Timelines General Estimating Assumptions Cost Estimate Earliest NTP Earliest In- Construction Owner's Resource Type (Year) (Year) Service (Year) Schedule (Months) Costs (%) Wind 2022 2024 2026 24 10 Solar PV 2022 2024 2025 18 10 BESS 2022 2024 2025 14 5 Wind + BESS 2022 2024 2026 24 10

  13. Slide 13: Modeling Scenarios

    Thank you Modeling Scenarios

  14. Slide 14: 2023 MT IRP Scenarios

    "023 MT IRP Scenarios No. Scenario Base Case Description NorthWestern’s current portfolio including the Colstrip 222 MW acquisition beginning Jan 1, 2026. Colstrip Retirement in 2030 Colstrip 222 MW acquisition occurs in 2026 and then Colstrip retires in 2030. The model indicates replacement resourc

  15. Slide 15: PowerSimm Access

    Thank you PowerSimm Access

  16. Slide 16: Required Information for PowerSimm Access

    Required Information for PowerSimm Access • Full Name • Email Address • Cell Phone Number • Access to authenticator app

  17. Slide 17: Questions/Comments?

    Thank you Questions/Comments?

NorthWestern Energy Group — Corporate Update (December 2024) on 6ix