Manila Electric Co. · PSE:MER

Manila Electric — Q1 2017 Earnings Presentation

38 slides from Manila Electric's earnings presentation, Apr 24, 2017

  1. Slide 1: Financial and Operating Results

    FINANCIAL AND OPERATING RESULTS . ee ie dae UinVeSvoOrs: and waRAysts Briefing H ati ee Cant Teh 3 2048 = Hi i | lity Ee it ae i ih H i : _ , iil PETE HE pan 3 MERALCO

  2. Slide 2: Operations Report

    OPERATIONS REPORT Performance ended March 2017

  3. Slide 3: 1Q 2017 Operating Highlights

    1Q 2017 Operating Highlights Energy Customer Peak Net System Sales Count Demand Input (NSI) 2.6%* 4.5%* 6.0%* 2.1%* 9,317 GWh 6.11 million 6,577 MW 9,968 GWh Ave. Retail S-Factor Rates & GSL** 3.4%* Sustained Service Business P7.84/kWh Improvement Updates *vs. same period, previous year **For G

  4. Slide 4: Details

  5. Slide 5: Energy Sales: 1Q 2017

    Energy Sales: 1Q 2017  Up 2.6% vs. 2016 (+240 GWh) Share /  for 1Q 2017: 2.6% 1.2% RESIDENTIAL 9,317 9,077 29.5% 3.4% Increase in organic sales and other COMMERCIAL 12.2% factors plus new 2.3% sales 40.2% 1.7% 8,092 •Private Services 7,908 INDUSTRIAL •Gov’t. Services 7,777 30.0% •Real Estate •

  6. Slide 6: Customer Count: 1Q 2017

    Customer Count: 1Q 2017  Up 4.5% vs. 2016 (+265,217 customers) Share /  for 1Q 2017: 4.7% RESIDENTIAL 4.5% 6.107 91.7% 2.7% 3.8% 3.9% 5.842 65,180 new 3.5%\ 5.626 customers COMMERCIAL 5.417 8.0% 5.232 3,361 new INDUSTRIAL customers in Mn 0.2% customers 73 new 2.0% customers 2013 2014 2015 2016

  7. Slide 7: Ave. Temperature (°C): 1Q 2017

    Ave. Temperature(°C): 1Q 2017 30.3 30.5 29.7 29.5 29.2 29.9 28.7 28.7 28.4 28.3 28.5 28.5 28.4 28.5 28.3 27.6 28.2 27.8 27.7 27.2 27.0 26.7 26.9 2015 2016 2017 26.2 26.2 Ave 1Q Temp 25.8°C 27.4°C 26.6°C 25.0 25.6 2015 2016 2017 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2015 2016 2017 Ave Max 1

  8. Slide 8: Clark Electric (CEDC): 1Q 2017

    Clark Electric (CEDC): 1Q 2017 ENERGY SALES, in GWh CUSTOMER COUNT 126.8 6.4% 134.9 1,967 2.8% 2,023 2016 2017 CEDC’s top 5 sales contributors for March 2017 include Phoenix Semiconductor Philippines 2016 2017 Corp. (PSPC), Advent Energy (Yokohama Tire Phils), SN Aboitiz Power (Taiyo Nippon), Prem

  9. Slide 9: Net System Input (NSI) and Peak Demand: 1Q 2017

    Net System Input (NSI): 1Q 2017 Peak Demand: 1Q 2017  Up 8.9% at 6,748 MW.  Meralco Peak Demand up 6.0% at 6,577 MW. Meralco YTD, MW: 2.1% 6,748 9,968.0 2016 Peak * 6,577 9,761.3 6,206 6.0% *May 4, 2016 2016 2017 2016 2017 (March 10) (March 24) Luzon YTD Peak Demand, MW: 9,726 2016 Peak** 9,459

  10. Slide 10: Energy Sources and Fuel Mix: 1Q 2017

    Energy Sources: 1Q 2017 Fuel Mix: 1Q 2017 SOURCE 1Q 2017 Liquid Fuel, 7.1%* GWh Share Coal PSAs-Total 3,444.1 34.6% 31.2% PSA IPP SEM-Calaca 324.9 3.3% 34.6% 26.7% MPPC-Masinloc 354.6 3.6% Natural Gas Multi-fuel TLI-Pagbilao 433.7 4.3% 31.8% 29.9% SMEC-Sual + CEDC 669.9 6.7% WESM RES 15.7% SPPC-Ilij

  11. Slide 11: Average Retail Rates: 1Q 2017

    Average Retail Rates: 1Q 2017  3.4% higher than 2016 average rates (-26¢/kWh); mainly due to Generation and FIT-All charges  For 2017, Generation Charge, largest component in customer’s bill, 53.7%; Meralco 17.9%; NGCP 10.9% BILL COMPONENT 1Q 2016 Overall Ave, GenerationP/kWh 1Q 2017 Overall Ave,

  12. Slide 12: System Loss Performance: March 2017, 12-MMA

    System Loss Performance: March 2017, 12-MMA  12-MMA ending March 2017 at 6.23% • Improved by 0.30%pt vs. March 2016’s 6.53% • Lower by 2.27% vs. SL cap of 8.5% 8.5% SL CAP, 2010-PRESENT Apr 2015 -Mar 2016 Apr 2016 - Mar 2017 2.27% 6.59 6.65 6.51 6.53 6.55 6.19* 6.21 6.23 Apr May Jun Jul Aug Sept Oc

  13. Slide 13: S-Factor & GSL Performance: 1Q 2017 & RY2017

    S-Factor & GSL Performance: 1Q 2017 & RY2017 (for GSL)  Sustained service improvements vs. past levels* SAIFI, Forced and PAI (Times) GSL1 : Customer experiencing a cumulative duration of Ave. Time to Process App. (Days) sustained service interruptions in a Regulatory Year that REWARDS DEADBAND PEN

  14. Slide 14: Business Updates

    iy) °@) atenso&

  15. Slide 15: Business Updates: Strengthening the Core Business

    Business Updates: Strengthening the Core Business (via CapEx for Enhanced Capacity & Power Quality) Voltage Improvement in Pasay and Makati Area  Replacement of Malibay Power Transformer Bank No. 1 March 29, 2017 Old 100 MVA Osaka Transformer New 83 MVA ABB Transformer •The new transformer is equip

  16. Slide 16: Business Updates: Significant Events/Customer Initiatives & Programs

    Business Updates: Significant Events/ Customer Initiatives & Programs Meralco Launches SPECTRUM, its Renewable Energy Subsidiary Meralco Celebrates 25th Listing Anniversary  January 13, 2017, the launch signals Meralco’s ERC Visits Meralco’s Meter Laboratory  January 10, 2017 at the Philippine Sto

  17. Slide 17: Luminaries 2017

    Business Updates: Significant Events/ Customer Initiatives & Programs Luminaries 2017 (Celebrating Customer success) LGU Luminaries: Malabon, Pasay, BIZ Luminaries: Eng Bee Tin, Ever Imus represented by Mayor Len-Len Bilena, RDF Foods, Livestock and Oreta, Mayor Antonino Calixto, Mayor Feeds, Inc. r

  18. Slide 18: Business Updates: Significant Events/Customer Initiatives & Programs

    Business Updates: Significant Events/ Customer Initiatives & Programs DOE invited Meralco to help craft INFO DRIVE ON RATES National Smart Grid Policy (DOE USec. Wimpy Fuentebella visit – Mar 21) 49,825 ACTIVATED 4,386 incremental (all time high) KLoad in Eat Bulaga’s “Juan for All, All for Juan” 

  19. Slide 19: Customer Engagements

    Business Updates: Significant Events/ Customer Initiatives & Programs Customer Engagements

  20. Slide 20: Meralco Bagged 12 Anvil Awards

    Business Updates: Significant Events/ Customer Initiatives & Programs Meralco bagged a total of 12 Anvil Awards including Public Relations (PR) Team of the Year PR Team of the Year GOLD (7) SILVER (4)  Meralco & Workplace: Changing the Way We Work  Meralco Election 2016 Preparedness Program  7 Da

  21. Slide 21: Project Updates

    The information as contained herein may neither be reproduced nor used, in whole or in part, for any other purpose nor furnished to any person(s) without express written permission from MERALCO PowerGen Corporation PROJECT UPDATES 24 April 2017

  22. Slide 22: San Buenaventura Power Limited Co. (SBPL)

    San Buenaventura Power Limited Co. (SBPL) 22 455MW (net) Supercritical Coal-Fired Power Plant in Mauban, Quezon  Construction of the power project is now on its 17th month and on schedule for commercial operations in mid 2019. Pulverizer and Boiler Area Control Building and STG Area

  23. Slide 23: Redondo Peninsula Energy, Inc. (RP Energy)

    Redondo Peninsula Energy, Inc. (RP Energy) 23 2x300 MW CFB Coal-Fired Power Plant in Subic, Zambales  Power plant site is ready for major construction activities starting off with the first phase (300 MW) which is targeted to be completed in 2020.  The second phase (300 MW) shall follow within 12

  24. Slide 24: Redondo Peninsula Energy, Inc. (RP Energy)

    Redondo Peninsula Energy, Inc. (RP Energy) 24 2x300 MW CFB Coal-Fired Power Plant in Subic, Zambales  Power supply agreements (PSA) for the first 300 MW have been signed with Meralco (225 MW) and Aboitiz Energy Solutions, Inc. (75 MW) in April 2016  The ERC approval of the PSA is expected to be se

  25. Slide 25: Atimonan One Energy, Inc. (A1E)

    Atimonan One Energy, Inc. (A1E) 25 2x600 MW Ultra Supercritical Coal-Fired Power Plant in Atimonan, Quezon  Environmental Compliance Certificate (ECC) obtained in October 2015  Grid Interconnection approved by the ERC in January 2017; Connection Agreement with NGCP executed in January 2017  Evalu

  26. Slide 26: Atimonan One Energy, Inc. (A1E)

    Atimonan One Energy, Inc. (A1E) 26 2x600 MW Ultra Supercritical Coal-Fired Power Plant in Atimonan, Quezon  Turnover of resettlement housing for the affected families was completed last March 8.  In April 2016, A1E signed a PSA with Meralco for the full output of the plant. The PSA is still subjec

  27. Slide 27: St. Raphael Power Generation Corporation (SRPGC)

    St. Raphael Power Generation Corporation (SRPGC) 27 2x350 MW Pulverized Coal-Fired Power Plant in Calaca, Batangas  MGen and Semirara Mining and Power Corp. entered a Joint Venture Agreement for a 50-50 stake in the planned 2x350 MW coal power plant in Calaca, Batangas in 2016.  A Power Supply Agr

  28. Slide 28: St. Raphael Power Generation Corporation (SRPGC)

    St. Raphael Power Generation Corporation (SRPGC) 28 2x350 MW Pulverized Coal-Fired Power Plant in Calaca, Batangas  Development activities for the project are ongoing.  An Environmental Compliance Certificate (ECC) for the project was issued in September 2015.  Grid Impact Study for the proposed

  29. Slide 29: Other Investments

    Other Investments 29 PROJECTS IN OPERATION GLOBAL BUSINESS POWER CORPORATION (GBPC)  MGen holds 14% equity interest in GBPC, the largest independent power producer in the Visayas with an existing portfolio totaling 854 MW (coal and diesel plants). PACIFICLIGHT POWER PTE LTD (PLP)  PLP has been ope

  30. Slide 30: Financial Highlights

    FINANCIAL HIGHLIGHTS Qi 2017

  31. Slide 31: Electricity Revenues

    66,576 60,173 1,852 2,322 Electricity Revenues = 64,724 Electricity Revenues = 57,851 51,699 45,050 12,801 13,025 Q1 2016 Q1 2017 Distribution Revenues Generation & Other Pass-through Charges Non-Electricity Revenues

  32. Slide 32: Costs and Expenses and Capital Expenditures

    1,737 1,004 6,150 3% 10% 2% Costs and Expenses 51,621 85% Purchased Power Operating Expenses Depreciation & Amortization Other Expenses 2,670 Capital Expenditures 45.4% 1,836 Q1 2016 Q1 2017

  33. Slide 33: EBITDA, Net Income and Margins

    8,151 8,151 7,922 7,922 4,817 4,590 4,598 4,547 13.5% 11.9% 13.5% 11.9%  Margins  7.6% 7.6% 7.2% 6.9% Core EBITDA Reported EBITDA Core Net Income Reported Net Income Q1 2016 Q1 2017

  34. Slide 34: Earnings Per Share

    Earnings Per Share Core Earnings Per Share 4.274 4.034 4.073 4.080 1 Q1 2016 Q1 2017 Q1 2016 Q1 2017

  35. Slide 35: Total Debt and Loan Repayment Schedule

    TOTAL DEBT (in Million PhP) 40,071 (in Million PhP, except ratios) Q1 2016 Q1 2017 29,875 24,620 Cash 45,949 49,430 27,004 15,451 Gross Debt 29,875 40,071 2,871 Net Debt (16,074) (9,359) Q1 2016 Q1 2017 Current Portion Non-current Portion Gross Debt/EBITDA 0.92 1.26 LOAN REPAYMENT SCHEDULE (in Milli

  36. Slide 36: Cash and Cash Equivalents

    95,073 89,070 9,757 16,683 35,886 26,438 45,949 49,430 Q1 2016 Q1 2017 Cash and Cash Equivalents Held-to-maturity investments Available-for-sale investments

  37. Slide 37: CIS Bayad Center and Densan System Partnership

    CIS Bayad Center, Inc. and Densan System Co., Ltd. Partnership BAYAD CENTER A — 7,4|5°7-\ ere) COMPANY TT

  38. Slide 38: Cautionary Statements

    Cautionary Statements This presentation is prepared for the participants of the MERALCO Investors and Analysts Briefing & Teleconference held on April 24, 2017. This presentation has consequential limitations and is not a comprehensive discussion about Manila Electric Company and Subsidiaries (MERAL