Slide 1: Silverton Wind Farm Community Consultative Committee
Silverton Wind Farm Community Consultative Committee Meeting No.CCC-031 Thursday, 21 February 2019
Slide 2: Agenda
Agenda 1 2 3 4 5 6 Welcome Previous Project update Community Topics of Other minutes • Overview relations interest business • Wind Farm Works update • Wholesale Electricity Market • Commissioning Volatility • Silverton Wind Forecast • Progressive Rehabilitation • Proposed SA- Silverton Wind Farm | 2
Slide 3: 1. Welcome
co) = fe) 2) O® =
Slide 4: 2. Previous minutes
2. Previous minutes
Slide 5: Previous minutes action items
2. Previous minutes Action items Item Action Status Who 3.23.16 AGL to contact Rod Grenfell in relation to erecting a fence along Daydream Mine Road near the Open AGL – 12/18 Umberumberka pipeline access. 4.25.07 AGL to progress the 20m monopole with Telstra and Crown as part of the mobile reception
Slide 6: 3. Project update
• Overview • Wind Farm Works • Connection Works 3. Project update
Slide 7: Silverton Wind Farm
3. Project update Silverton Wind Farm Silverton Wind Farm • Located in the Barrier Ranges approximately 5km north of the Silverton township • Owned by the Powering Australian Renewable Fund (PARF) • Generation capacity of 200 MW • Wind turbines: 58 x GE 3.43-130 • Annual Energy Production (AEP) - ~7
Slide 8: Scope of works
3. Project update Silverton Wind Farm Scope of works • Silverton Wind Farm consists of two main scope of work: - Wind Farm Works (GE-CATCON) - Connection Works (TransGrid) • AGL has prepared an Overview Environmental Management Strategy (OEMS) in accordance with the project approval • Overview activ
Slide 9: Wind Farm Works
3. Project update Silverton Wind Farm Wind Farm Works • GE-CATCON (joint venture) has been engaged to deliver the wind farm works - Engineer, Procure, Construct (EPC) Contract • Scope of works, includes - 58 x GE 3.43-130 wind turbines - 33kV electrical reticulation (underground and overhead) and 33
Slide 10: Connection Works
3. Project update Silverton Wind Farm Connection Works • TransGrid has achieved Practical Completion on 20 February 2018 - Existing Broken Hill 220kV substation (connection point) - 220kV transmission line - Wind farm 220kV substation • Connection works were successfully energised on 23 Feb 2018. •
Slide 11: Construction works
3. Project update Wind Farm Works Construction works • Wind turbines erection: - WTG erection complete: 57/58 (~98%) - WTG mechanical completion: 50/58 (~86%) - WTG commissioning: 41/58 (~71%) • Wind turbines commissioning: - WTG commissioned: 46/58 (~79%) Sarens LR1650 (650 tonne crane) is currentl
Slide 12: Construction works – Progress photos
3. Project update Wind Farm Works Construction works – Progress photos Silverton Wind Farm | 21 February 2019 12
Slide 13: Wind Turbine Commissioning
3. Project update Wind Farm Works Wind Turbine Commissioning • The wind farm is currently being commissioned in accordance with the AEMO commissioning plan which involves coordination with AEMO and TransGrid (NSP). - AEMO – Australian Energy Market Operator - NSP – Network Service Provider • Commiss
Slide 14: Wind Turbine GE 3.43-130
3. Project update Wind Farm Works Wind Turbine GE 3.43-130 • GE 3.43-130 Power Curve - Cut in wind speed – 3 m/s - Rated wind speed – 13 m/s - Cut out wind speed – 25 m/s Silverton Wind Farm | 21 February 2019 14
Slide 15: First Generation
3. Project update Wind Farm Works First Generation • First generation occurred from the Silverton Wind Farm (STWF) on Saturday, 12 May 2018 at 23:30 hrs • Generation from the Silverton Wind Farm (STWF) as at Tuesday, 19 February 2019. - 142,000 MWh - Already powering approximately 25,000 average Aus
Slide 16: Local Industry Participation
3. Project update Wind Farm Works Local Industry Participation • Currently ~50 construction workers with approximately 20% from the local area. - Significant reduction in the number of construction workers is forecast in the coming weeks. - Local component mainly associated with the operation and ma
Slide 17: Local suppliers
3. Project update Wind Farm Works Local suppliers • Delivery of the Silverton Wind Farm to date has involved the following local suppliers / contractors - Attards Transport - Interhealth Broken Hill - Barrier Daily Truth - Judd Plumbing - Boss Construction - Lawrence Engineering - Broken Hill City C
Slide 18: 4. Community relations update
4. Community relations update
Slide 19: Community Enhancement Program
4. Community relations update Community enhancement program Community Enhancement Program The Community Enhancement Program for the Silverton Wind Farm is progressing, in accordance with condition 18 (schedule 2) of the project approval. We are implementing the program to give effect to the commitme
Slide 20: Silverton Solar Program
4. Community relations update Community enhancement program Silverton Solar Program • To date, AGL has provided solar panels to 30 property owners and 23 of these properties have received their smart meters. Installers will return to Silverton on 28 Feb and 1 Mar 2019 in order to complete the remain
Slide 21: Water Tank Program
4. Community relations update Community enhancement program Water Tank Program • AGL has started work on the supply, installation and connection of a domestic sized water tank (10,000L) - Water tank supply Landmark - Installation and connection Broken Hill Plumbing Services • Rolling installatio
Slide 22: Mobile Reception Program – Next Steps
4. Community relations update Community enhancement program Mobile Reception Program – Next Steps • Prepare an Environmental Assessment to assess potential impacts of the proposal on the existing environment and recommend safeguards to mitigate any environmental risks. - This will commence shortly a
Slide 23: Mobile Reception Program
4. Community relations update Community enhancement program Mobile Reception Program • AGL has a draft Enterprise Work Agreement (EWA) with Telstra in relation to the proposed 4GX solution developed with Telstra for the mobile reception program - Installation of a 20m monopole at Telstra’s Silverton
Slide 24: Mobile Reception Program coverage predictions
4. Community relations update Community enhancement program Mobile Reception Program • The coverage predications below provide and indicative view of the coverage the proposed 4GX small cell would provide - Proposed 4GX solution would require a 4G 700 MHz compatible device to benefit from the improv
Slide 25: Visual Impact Mitigation
4. Community relations update Visual impact mitigation Visual Impact Mitigation AGL issued notification to the Silverton residents in accordance with condition 2 (schedule 3) of the project approval in relation to the visual impact mitigation measures outlined in condition 1 (schedule 3). • Owners w
Slide 26: Community events
4. Community relations update Community events Silverton Wind Farm | 21 February 2019 26
Slide 27: Community information
4. Community relations update Community engagement Community information AGL contact details for community and project information are shown below: • P: 1800-039-600 • E: [email protected] • W: agl.com.au/silverton Construction information GE-CATCON will provide contact details on the project
Slide 28: 5. Topics of interest
• Wholesale Electricity Market Volatility • Silverton Wind Forecast • Progressive Rehabilitation • Proposed SA-NSW Interconnector 5. Topics of interest
Slide 29: Wholesale Electricity Market Volatility
5. Topics of interest Wholesale Electricity Market Volatility Pricing Volatility • Graph shows that spike in wholesale electricity prices on Tuesday, 29 January 2019 in the PM peak. • NSW wholesale pricing which has typically been ~$80 / MWh spiked to $4,600 / MWh Silverton Wind Farm | 21 February 2
Slide 30: Silverton Wind Forecast
5. Topics of interest Silverton Wind Forecast Silverton Wind Forecast • Currently forecasting erection of the final blade set on Monday, 25 February 2019. Silverton Wind Farm | 21 February 2019 30
Slide 31: Progressive Rehabilitation
5. Topics of interest Progressive Rehabilitation Wind Farm Works • GE-CATCON is completing progressive rehabilitation in accordance with condition 36 (schedule 4) of the project approval. • Works are being undertaken in accordance with the construction phase rehabilitation management plan specific t
Slide 32: Installation of Permanent Drainage Works
5. Topics of interest Progressive Rehabilitation Installation of Permanent Drainage Works (Above) Installed spoon drains (Right) Installed cross drain (Far Right) Installed spoon drains Silverton Wind Farm | 21 February 2019 32
Slide 33: Proposed SA-NSW Interconnector
5. Topics of interest Proposed SA-NSW Interconnector SA Energy Transformation RIT-T • ElectraNet released the Project Assessment Conclusions Reports on 13 February 2019 (https://www.electranet.com.au/wp-content/uploads/projects/2016/11/SA-Energy-Transformation- PACR.pdf). • ElectraNet is proposing t
Slide 34: 6. Other business
6. Other business
Slide 35: Next meeting
Silverton Wind Farm Community Consultative Committee (CCC) • Next meeting (TBC) - Thursday, 23 May 2019 - Time: 3pm - Silverton Municipal Chambers, Silverton Next meeting