NorthWestern Energy Group, Inc. · NASDAQ:NWE
NorthWestern Energy — Corporate Update (March 2024)
14 slides from NorthWestern Energy's corporate update, Mar 27, 2024
Slide 1: NorthWestern Energy - Electric Technical Advisory Committee
NorthWestern Energy - Electric Technical Advisory Committee 2025 Planning Cycle Meeting 2 – 27 March 2024
Slide 2: About our company
About our company KALISPELL MEDEA Peiliines — Nature 7 wind Farm & Hydro Facilities HEL Thermal Generating Plants WYOM A Peaking Plants IG aaron NORTH PLATTEO GRAND ISLAND KEARNEY \
Slide 3: About our company
About our company 775,300 Customers 1,573 Employees 337 communities in Montana and South Dakota with electric service 202 communities in Montana, South Dakota and Nebraska with gas service 3
Slide 4: About our company: 2023 Electric Generation Portfolio
"About our company NORTHWESTERN ENERGY 2023 ELECTRIC GENERATION PORTFOLIO BASED ON MWH OF OWNED AND LONG-TERM CONTRACTED RESOURCES ne teq Wind Owned ted N\ ntracted nox Wind Contractec 17.3% = 55% N .,Carbon-Free a, Natural 92° Gas/Other Contracted 13% ¥ Natural Gas/Other Owned 7.9% ao Coal Owned oy
Slide 5: Thank you
Thank you MT PSC Presentation
Slide 6: 2025 MT IRP Workplan Draft
2025 MT IRP Workplan Draft • Review of Workplan • Workplan Draft • ETAC • Proposed meeting topics • Proposed meeting dates • Stakeholder Engagement • Proposed structure • Proposed topics
Slide 7: PowerSimm Modeling and ETAC
PowerSimm Modeling and ETAC • Plan for ETAC access and review • Initially provide stochastic outputs and training on what they are/how they play into the model • Once the base case is complete, ETAC will receive a detailed workbook with information to be input into PowerSimm for modeling • ETAC will
Slide 8: Capacity Position
NorthWestern Energy Capacity Position Valid as of 3/21/2024
Slide 9: Capacity Position
NorthWestern Energy Capacity Position Valid as of 3/21/2024
Slide 10: Capacity Position
NorthWestern Energy Capacity Position Valid as of 3/21/2024
Slide 11: Capacity Position
NorthWestern Energy Capacity Position Valid as of 3/21/2024
Slide 12: Website Navigation
NorthWestern Energy Website Navigation • Integrated Resource Planning • https://www.northwesternenergy.com/about-us/gas-electric/montana-electric-supply- planning/ • Qualifying Facilities • https://www.northwesternenergy.com/about-us/gas-electric/montana-electric-supply- planning/qualifying-faciliti
Slide 13: Thank you
Thank you Next Meeting: 25 June 2024
Slide 14: Questions?
Questions?