Slide 1: Investor day November 2017
Investor day November 2017

Slide 2: Forward looking statements
Forward looking statements This presentation as well as oral statements made by officers or directors of Allegiant Travel Company, its advisors and affiliates (collectively or separately, the "Company“) will contain forward- looking statements that are only predictions and involve risks and uncertai

Slide 3: Opening comments
Opening comments • Busy year – transition year • Management • Operations • Fleet • Sunseeker • People • Strategic business overview – leisure travel company • Competition – model still strong – airline is job 1, but . . . • Want more $ from current customer wallets • Need to expand product offerings

Slide 4: Sunseeker resorts
sy INS SUNSEEKER RESORT Charlotte Plarbor

Slide 5: Addressing the skepticism
Addressing the skepticism Issue How we have addressed G4 – no experience in hotels or condos Hired world class leadership/developers Port Charlotte – not Miami or New York • Hotel room growth has lagged air travel • Opposite of Panama City • Does Miami need another resort? • Example of new destinati

Slide 6: This is the most exciting hotel resort opportunity I have come across
“This is the most exciting hotel resort opportunity I have come across, especially with the airline tie-in” – John Redmond • With the exception of Clearwater, most hotels in area are old • Lack of a true destination resort • Hotel room growth has not kept pace with air and drive-in traffic increases

Slide 7: Florida traffic and hotel room growth
Florida traffic 46.0% 35% Passenger and fare growth, 2016 vs. Hotel room vs. capacity growth 2007 30% 32.3% 23.1% Percent growth since 2009 21.6% 25% 19.3% 19.2% 15.2% 12.6% 11.7% 8.8% 20% 7.3% 4.3% 2.4% 15% Strong growth in passengers and 10% fare to Punta Gorda and Ft. Myers (10.6%) (15.6%) 5% (28

Slide 8: Hotel demand
Hotel demand G4 Hotel and air bookings by quarter • Sunseeker = additional ancillary hotel $ 33% • Las Vegas demand level exceeds 30% current Punta Gorda capacity 27% • Four Points by Sheraton, Punta Gorda: 25% 23% $200 ADR in peak season 22% 21% 19% Q1 Q2 Q3 Q4 Distribution of hotel bookings Distri

Slide 9: Potential take rates
Potential take rates Condo Hotel Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Number of Developed Rooms 583 583 583 583 583 583 % of Rooms Put Into The Inventory Pool 75% 75% 75% 75% 75% 75% Number of Available Rooms 160,000 160,000 160,000 160,000 160,000 160,000 Occupancy % 100% 100% 100% 100% 100% 1

Slide 10: Destination demand
Destination demand • Punta Gorda geocode check-in data - wide catchment area • Significant drive-in market TPA PIE Allegiant Distance Airport Annual passengers Airlines destination from resort SRQ • 2017: G4 flew 1 million PGD ✔ 15 minutes • 2018: 1.2 million Punta Gorda south projected PGD

Slide 11: Sunseeker video
Sunseeker video allegiant

Slide 12: Construction and development team
Construction and development team Paul Steelman Ben Mammina L2 Studios Steelman Partners, Concept Executive Vice President, Architects, Architect Design and Construction Production Drawings Florida Premier Contractors & Manhattan Construction Group GC Joint Venture Farr Law Firm Local counsel Greenb

Slide 13: Site overview
Site overview • Resort planned to include: • 10 condo towers dependent on deposits • 76 hotel rooms - additional 196 expansion rooms • 100+ marina slips • Resort and hotel pools • 12+ bars, restaurants, and shops • Catering/banquet facilities • Grocery/pharmacy, doctor’s office • More facilities – n

Slide 14: 14
14

Slide 15: Service)
Service) Building tan Restaurant/, Retail iiised Uso 67 15

Slide 16: Project financing
Project financing • Florida law • Sales deposits can be used for construction costs • Plan: use 20% of the 30% deposits • De-risking sales: multi-step approach • Started with expression of interest – currently at about 7,000 • Now on registration phase, taking $5K deposits • Deposit plan: up to 30%

Slide 17: Condominium sales
Condominium sales • Expect to begin to enter into purchase agreements in late Q1 2018 • Proceeds of sales of all units expected to be more than the total cost of construction • Utilization of Allegiant database to understand project viability • Frequency of visitation, demographics, points of origin

Slide 18: Hotel scope
Hotel scope • Large scale = greater operational efficiency • Variety of rooms and price points to drive occupancy • Food/beverage options will drive daily non-stay visitation • Synergy with airline • Potential impact on load factor/seasonality • Concentration of amenities • Target larger groups and

Slide 19: Hotel and condo-hotel demand
Hotel and condo-hotel demand • Maximum annual available room nights: • 272 hotel rooms for 99,280 room nights • 835 condo units for 466,105 room nights (if all two bedrooms rented as two units) • Over 1,500 keys • Revenue split dependent on nights made available, time of year, and advance notice • 5

Slide 20: Food and beverage opportunities
Food and beverage opportunities • 12+ bars and restaurants • Wide variety • All on waterfront • Average stay 5-6 days • Synergy between venues • Shared kitchen/staff • Decreases overhead costs Artist’s rendering 20

Slide 21: Additional ancillary revenue
Additional ancillary revenue • Marina slips • Parking • HOA fees cover share of hotel amenities cost • Banquet hall/catering for weddings, corporate functions • Early check-in charge • Airport shuttle • Cleaning service • Short term car rental • Compare resort offerings to hotel brands such as Four

Slide 22: Estimated timeline
Estimated timeline • November 2017: asked for expressions of interest – almost 7,000 • End of 2017: all required land transactions closed • Late Q1 2018: expect to enter into purchase agreements • Late Q2 2018: expect construction of resort to start • December 2019: construction completed, unit clos

Slide 23: Operations
Operations allegiant

Slide 24: Operations – Where to focus first?
Operations – Where to focus first? • Summer operations = priority #1 Day 1 • Controllable cancellations had increased 26% YOY through 2Q17 • Cancellation drivers = increased AOS AC + increased AOS Hours • Leadership – substantial changes in most workgroups Mid August • Materials planning & support –

Slide 25: Operations – Day 1
Operations – Day 1 Avg Daily AC AOS Total AOS Hours 25 6,005 5,005 20 4,005 15 3,005 2,005 10 1,005 5 5 Jan 17 Feb 17 Mar 17 Apr 17 May 17 Jun 17 Jul 17 Aug 17 Sep 17 Oct 17 Jan 17 Feb 17Mar 17 Apr 17 May Jun 17 Jul 17 Aug 17Sep 17 Oct 17 17 2017 2016 2017 2016 Controllable Cancellations % of Custom

Slide 26: Completion factor - attacking the critical issue
Completion factor - attacking the critical issue Controllable Completion - Rolling 30 Days 100% 99% 98% 97% 96% 2017 2016 26

Slide 27: Focus on critical issues
Focus on critical issues • Change the line MX culture • New leadership in most large bases (SFB, LAS, PIE) • Eliminated line maintenance contractors • Delayed training events during summer peak – more techs on the line • Dedicated AOS recovery team • Additional Airbus reps in MX control AOS hours pe

Slide 28: Reduction in IROP costs
Reduction in IROP costs – aggressive but achievable Controllable IROPs Cost Trends $20,000 60% 49.5% $18.9M $18,000 40% $16,000 $14,000 14.0% 20% $13.0M Cost of IROPs $12,000 Cancellations $11.1M - $10,000 $9.8M $8.3M (20%) $8,000 (34.8%) $6,000 $5.5M $5.6M $5.1M (40%) $4.3M $4,000 $3.0M $2.4M $2.3M

Slide 29: Post summer – aggressive management restructuring
Post summer – aggressive management restructuring • ~65% of management changed/realigned in Maintenance, Stations, OCC, and Procurement departments 30 25 20 14 6 15 2 5 10 1 1 4 3 12 3 5 1 6 6 1 3 - MX Stations OCC Procurement Manager Director VP Unchanged Positions 29

Slide 30: Materials planning – getting in front of the issue
Materials planning – getting in front of the issue • Previous approach = reactive and disjointed • Little to no predictive analysis • Modeling failed to keep up with ALGT fleet growth and complexity • Change in philosophy • Turn unscheduled MX events into shorter, planned events • Reduced AC sparing

Slide 31: Fleet transition – solid execution, the end in sight
Fleet transition – solid execution, the end in sight • Unprecedented fleet transition in less than 2 years • Single mixed base by summer 2018 – SFB • Enhanced induction work scope – 1st max pax A320 1Q18, drives complexity • AC sparing levels – potentially impacted by AC damage, unscheduled power pl

Slide 32: 2016 Fleet deployment – peak complexity
2016 Fleet deployment – peak complexity 2016 Aircraft 85 Bases 14 Fleet Types 3 32

Slide 33: 2017 Fleet deployment – mid transition
2017 Fleet deployment – mid transition 2017 Aircraft 89 Bases* 15 Fleet Types 2 * Added Destin and Indianapolis, removed Honolulu 33

Slide 34: 2018 Fleet deployment – summer strategy
2018 Fleet deployment – summer strategy 2018 Aircraft 82 Bases 15 Fleet Types* 2 * Concentrate MD80s in SFB 34

Slide 35: Pilot staffing – elevated levels but improving
Pilot staffing – elevated levels but improving 300 30% 250 25% 200 20% 150 15% 100 10% 50 5% - - Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 MD80 Training Airbus Training Airbus Excess MD80 Excess Linear (Inefficiency (% Line

Slide 36: Pilots per AC – returning to normalized levels
Pilots per AC – returning to normalized levels Pilots per AC 0.7 9.8 10.0 (1.1) 1.1 9.0 (0.7) 0.3 (0.4) 8.0 0.5 7.6 1.5 7.0 6.0 5.8 5.0 4.0 3.0 2.0 1.0 - 2012 Actual AC Utilization Part 117 Pilot Contract Training Overstaffing 2018 Forecast Training Overstaffing Single Fleet 2020 Forecast Pilots/AC

Slide 37: Fleet & Treasury
Fleet & Treasury allegiant

Slide 38: Fleet transition – 2018
Fleet transition – 2018 1 All Airbus fleet by November 2018 a Current MD80 bases LAS & SFB; in May 2018 all MD80s based in SFB b MD80 NBV - $38 million as of November 2018 (includes expendables) MD80 series¹ Airbus series¹ 40 37 90 82 35 18 32 80 76 73 30 16 27 70 59 32 25 60 31 27 52 31 19 50 20 25

Slide 39: Airbus – 186 seat modification
Airbus – 186 seat modification 1 21 fewer A320s to be modified to 186 seats due to current restraints¹ EBIT Contribution-$m 3 Original 2020E Update 2020 Comments 186 seat modification $27 $17 Expecting annual EBIT contribution per used aircraft modification ~$500k Aircraft w/186 seats at YE² 80 69 7

Slide 40: Fleet growth
Fleet growth 1 Since 2013, we have sourced¹ 98 airbus A320 series aircraft Worldwide A320 aircraft as of October 2017 a To opportunistically source 12 additional used A320 by YE 2020 ~12,800 A320 Family Aircraft produced or on order ~7,300 Sourced Airbus aircraft A320 Family Aircraft (CEO & NEO) pro

Slide 41: Fleet plan
Fleet plan 1 Estimated aircraft at end of year Aircraft by seat count 120 110 + 30 airbus ac 100 100 48 89 38 82 10 80 20 27 60 22 25 25 23 40 37 37 37 32 20 0 2017E 2018E 2019E 2020E MD80 (166 seats) A319 (156 seats) A320 (177 seats) A320 (186 seats) 41

Slide 42: Capital expenditures
Capital expenditures 1 Placeholder aircraft included in Aircraft capex amounts in 2019 and 2020 2 Sunseeker development costs excluded as expected to be funded via condo sales and short term financing Capital expenditures ($ millions) $700 $665 35 $600 35 75 $500 $390 $395 $400 $335 90 125 $300 45 5

Slide 43: Debt
Debt 1 Debt balances and borrowing capacity based on current commitments and reflect year-end amounts a Revolver of $56 million currently drawn – assumes pay down in 2018 b Maturity of unsecured debt in July 2019 – assumes to refinance as unsecured debt Debt balances ($ millions) Borrowing capacity

Slide 44: Return to shareholders
Return to shareholders Oustanding Shares (millions) 30% reduction 25 1 Share-repurchases cumulative - $605 million 20 23 15 a Current authority - $100 million 16 10 2 Dividends cumulative - $260 million 5 0 a Quarterly dividend - $0.70 per share Total shares issued Current - O/S Shares Shareholder r

Slide 45: Let's talk about costs
Let’s talk about costs allegiant

Slide 46: 2017 guidance
2017 guidance Adj. FY 2017 Guidance: +14.5% - 15.5% *** 6.9 FY 2017 0.25 6.86 Guidance: FY 2017 +11% - 12% ** 0.04 Guidance: 6.7 6.65 +5% - 9% * 0.19 6.5 6.47 0.05 0.04 0.03 0.08 US Cents 6.3 0.06 0.06 0.26 6.1 5.94 5.9 5.7 2016 CASM Pilot Contract Accel Dep Add'l AC Dep Heavy Mtx MD80 Heavy 2017E C

Slide 47: 2018 costs
2018 costs ASMs per gallon 80 77.5 – 79.5 Fuel Expense 75 72.5 – 73.0 71.6 69.4 70.2 • Accelerated MD80 retirements & Airbus utilization 70 increases ASMs per gallon 65 • Current forward curve ~ $2.17 / gallon 2014 2015 2016 2017E 2018E Maintenance /Aircraft / Month ($000s) 112.0 110.7 105 - 110 Mai

Slide 48: 2018 costs
2018 costs Salaries & Benefits Expenses Crew productivity 95% • Flight Attendant Tentative Agreement: • 5 year contract 77% 78% 77% 78% 80% 75% • Estimated 2018 ~ $8M • Estimated 5 year impact ~ $57M 65% 60% 59% • Voting complete by end of December 53% 54% 51% Rate Increases 2018 2019 2020 2021 2022

Slide 49: Cost per passenger ($)
Cost per passenger ($) Ex fuel costs = $72 Ex fuel costs = $76 Ex fuel costs = $69 Fuel cost = $30 Fuel cost = $24 Fuel cost = $23 Total Total MD-80 = $102 Total A319 = $100 Total A320 = $92 $23 $24 $21 Other $49 $53 $48 $26 $29 $26 $13 $7 $7 $9 $15 Aircraft $53 $14 $47 $44 $30 $24 $23 Assumptions M

Slide 50: Estimated 2020 CASM ex-fuel
Estimated 2020 CASM ex-fuel 7.0 0.35 6.8 6.43 midpoint of 6.6 FY17 CASM ex guidance (ex CC 0.14 Surcharge)* 6.4 6.28 US Cents 0.29 0.31 6.2 5.99 6.0 0.33 5.8 5.6 2017E CASM ex- AC/Hvy Mtx MD80 Heavy Mtx Pilot Productivity Other Efficiencies 2020E CASM (¢) Credit Card Adj 2020E CASM Fuel (¢) Deprecia

Slide 51: Commercial update
Commercial update allegiant

Slide 52: Commercial initiatives
Commercial initiatives Flexible network and capacity plans based on macro environment Network Off-peak flying accretive to EPS, headwind to TRASM Long network runway Co-brand credit card acquisition ahead of schedule Co-brand & eCommerce project revenue impact eCommerce A/B website test results New

Slide 53: Network
Network allegiant

Slide 54: 2018 capacity guidance
2018 capacity guidance • 2018 YoY ASM growth expected to be between 11 to 15% • Ability to grow despite decline in frames in part due to Airbus efficiency over MD80s • 4th Quarter 2018 will see least amount of growth as we end transition quickly 85 Average lines of flying 80 75 70 65 1Q 2Q 3Q 4Q 201

Slide 55: Network and capacity flexibility
Network and capacity flexibility 40% % of previous year same store ASMs reduced / not flown • Continue to be flexible [Fuel spike] with macro environment 35% and oil price 30% • Ability to manage 25% [Fuel spike] capacity on a single round-trip basis 20% 15% [Consistent high fuel] 10% [Low fuel] 5%

Slide 56: Destination city size
Future capacity growth Representative Cities Tiny Origination: Grand Island, NE Small Origination: Syracuse, NY Destination city size Mid-size Origination: Cincinnati, OH Large Origination: Atlanta, GA Small Small Destination: Savannah, GA Mid-size Destination: Austin, TX Medium Large Destination: L

Slide 57: Fleet comparison: MD80 vs Airbus
Fleet comparison: MD80 vs Airbus Projected profitability & utilization of a 100 aircraft single fleet 8.0 8.0 7.0 7.0 Utilization (Block Hours / Aircraft Day) 6.0 6.0 EBIT / Aircraft (in $millions) 5.0 5.0 4.0 4.0 3.0 3.0 2.0 2.0 1.0 1.0 ‐ ‐ MD80 Utilization Airbus Utilization MD80 EBIT / Aircraft A

Slide 58: Off-peak growth impact
Off-peak growth impact Percent off-peak ASMs • Off-peak defined as 35% 30% Tuesday, Wednesday, 25% Saturday flying 20% 15% • Growth in off-peak 10% driven by lower fuel 5% 0% prices in 2015/16 and 2014 2015 2016 2017 2018 Airbus margin profile vs. MD80 Year / year impact of incremental off-peak flyi

Slide 59: Co-branded credit card & eCommerce
Co-branded credit card & eCommerce

Slide 60: Co-branded credit card
Co-branded credit card • Strong, sustaining customer demand for the co- Account acquisition vs branded card benefited by projections • Robust and unique value proposition • Closed distribution • Small cities • Future tailwinds from • Cardholder acquisition optimization • Additional destinations from

Slide 61: eCommerce: 2017 projects
eCommerce: 2017 projects Purchase Path Amex Payment Platform Optimization Mobile App Self Service In-App Booking 3rd Party Booking Loyalty Credit Card Promotion Codes Improved Merchandising Experiments A/B Testing Original Updated Projected annual earnings impact 1 2020E 2017E 2017E eCommerce Increm

Slide 62: A/B Test: select bags page
A/B Test: select bags page Revenue per passenger 15% 10.5% 10% 5% 1.3% 0% -2.6% -5% -4.9% -10% Bags Rev Priority Boarding Rev Pre-Launch Post-Launch 62

Slide 63: Revenue
Revenue allegiant

Slide 64: Next-Gen revenue management system
Next-Gen revenue management system ASM's on Next-Gen RM System • Testing on next-generation RM system began on 100% flights in Aug 2016 • Slower than expected ASM rollout due to several 80% major programming changes through 2017 60% • System utilizes advances in data science to: 1. Improve flight fo

Slide 65: Flight clustering example
Flight clustering example First-Gen Allegiant system: Next-Gen Allegiant system: Aggregate flight demand Aggregate flight demand into based on regions and haul best-fit clusters 65

Slide 66: Clustering leads to improved accuracy
Clustering leads to improved accuracy First-Gen Booking days out accuracy of best fit booking curve 80% 70% 60% Percent of flights 50% 40% 30% Next-Gen 20% 10% 0% <-25% -20% -10% 0% 10% 20% >25% % Error First-Gen Next-Gen 66

Slide 67: Unconstrained demand
Unconstrained demand • Next-Gen system forecasts how flights would sell if they had not sold out • Unconstrained demand is used when calculating the optimal fare 120% $200 $180 100% $160 Expected Load Factor $140 80% $120 Fare $100 60% $80 40% $60 $40 20% $20 $0 0% 0 1 2 3 4 5 6 7 8 0 1 2 3 4 5 6 7

Slide 68: Fixed fee revenue
Fixed fee revenue • Increased fixed fee opportunities on slack in the schedule over the past two years • International track programs contracted through 2019 • Airbus charters are commanding a revenue premium over MD-80s • More opportunities for fixed fee once international scheduled service starts

Slide 69: Revenue guidance & initiatives
Revenue guidance & initiatives

Slide 70: Commercial initiatives earnings impact ($m)
Commercial initiatives earnings impact ($m) Projected annual earnings impact 1 Original Updated Original Updated 2017E 2017E 2020E 2020E Co-brand Credit Card $10 $17 $45 $50 eCommerce Incremental Revenue $14 $10 $92 $92 Revenue Management System $7 $2 $49 $49 Fixed Fee $5 $8 $20 $20 Fleet Productivi

Slide 71: 4Q17 TRASM guidance update
4Q17 TRASM guidance update • 4Q17 YoY TRASM expected to be (1) to 1%, up from previous guide of (3) to (0.5)% • Revenue initiatives performing better than expected by 100bps • Demand stronger than expected by 75bps 71

Slide 72: 2018 guidance & initiatives update
2018 guidance & initiatives update

Slide 73: Updating how we will guide
Updating how we will guide • Will provide full year EPS • In business to maximize EPS • Aligns the long term interests of the company with the street • Will not be providing • Quarterly TRASM • Quarterly or full year CASM ex fuel 73

Slide 74: 2018 EPS guidance
2018 EPS guidance 2018 FY EPS range $8 - $10 per share Assumptions FY 2018 fuel cost $2.17 FY 2018 ASMs/Gallon 77.5 to 79.5 FY 2018 interest expense $50m to $60m FY 2018 tax rate 37% to 38% FY 2018 share count 15.9m $35m MD-80 impairment taken in 4Q17 Guidance subject to change Fuel cost as of Novem

Slide 75: Other guidance
Other guidance Item Guidance 4Q 2017 TRASM year over year change (1) To 1% FY 2017 CASM ex fuel – adjusted for impairment 14.5 to 15.5% FY 2018 scheduled ASMs 11 to 15% FY 2018 system ASMs 11 to 15% FY 2018 CAPEX $335m 1 FY 2018 depreciation/AC/mo $120k to $130k FY 2018 maintenance/AC/mo $95k to $10

Slide 76: Contribution of initiatives
Contribution of initiatives Original Update Original Update Operating earnings annual impact -$m 1 2017E 2017E 2020E 2020E Fuel benefit from ASM production $6 $6 $21 $21 Ex-fuel savings (costs) (21) (29) 73 73 Credit card program 10 17 45 50 eCommerce initiatives 14 10 92 92 Pricing engine 7 2 49 49
Source: Internet Archive copy of s203.q4cdn.com
More decks from Allegiant Travel Company
Q3 2026 Earnings Presentation72 slides · Nov 4, 2026
Q3 2026 Earnings Presentation29 slides · Nov 4, 2026
Q2 2026 Earnings Presentation27 slides · Aug 4, 2026
Q2 2026 Earnings Presentation18 slides · Aug 4, 2026
Q1 2026 Earnings Presentation22 slides · Apr 30, 2026
Q4 2025 Earnings Presentation26 slides · Feb 4, 2026