Slide 1: First Quarter 2016 Earnings Conference Call
First Quarter 2016 Earnings Conference Call May 4, 2016
Slide 2: Safe Harbor Statement
A A A A Safe Harbor Statement This presentation includes statements that may constitute forward-looking statements made pursuant to the safe harbor provisions within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amend
Slide 3: Recent Highlights
Recent Highlights 3 A A A Montana Power Station (MPS) Unit 3 was placed in service on May 3, 2016 and will be available for summer peak Construction of MPS Unit 4 is ahead of schedule and is now anticipated to be placed in service in September 2016 Texas rate case settlement was filed with PUC
Slide 4: Texas Rate Case Update (Docket No. 44941)
A A A A A A a 4 Texas Rate Case Update (Docket No. 44941) In March, a majority of the parties filed a non-unanimous settlement. Key terms include: A non-fuel base rate increase of $37mm The potential for an additional rate base increase of $8mm related to Four Corners costs Lower annual depr
Slide 5: Texas Procedural Schedule
5 Texas Procedural Schedule Administrative Law Judges held a prehearing conference on April 21, 2016 A scheduling order was issued on April 22, 2016 setting the following procedural schedule After a final order is issued, new rates will relate back to January 12, 2016 Event Deadline Staff dire
Slide 6: New Mexico Regulatory Update (Case No. 15-00127-UT)
A A A a New Mexico Regulatory Update (Case No. 15-00127-UT) 6 Originally filed for a non-fuel base rate increase of $8.6mm, which was later revised to $6.4mm Hearing Examiner recommended a $640 thousand increase in non-fuel base rates which includes: Treating a significant portion of the pensi
Slide 7: Potential Timeline - Next Rate Cases
A A A A Potential Timeline - Next Rate Cases 7 (1) NM Rate Case filing would use a historical test year ended September 2016 and via a “post test year adjustment” include MPS units 3 & 4 in requested rate base. (2) Section 36.112 of the TX Utilities Code, which was added by the recent House Bill 153
Slide 8: 1st Quarter Financial Results
1st Quarter Financial Results 1st Quarter 2016 net loss of $5.8mm (or $0.14 per share), compared to 1st Quarter 2015 net income of $3.5mm (or $0.09 per share) 8
Slide 9: 1st Quarter Key Earnings Drivers
A A A A 9 1st Quarter Key Earnings Drivers Basic EPS Description March 31, 2015 0.09$ Changes In: Allowance for funds used during construction (0.06) Decreased due to lower construction work in progress balances due to MPS Units 1 & 2 and the Eastside Operations Center (EOC) being placed in service
Slide 10: Historical Weather Summary
10 Historical Weather Summary 1,288 1,191 1,030 1,396 1,265 1,159 1,338 958 1,153 1,054 0 200 400 600 800 1,000 1,200 1,400 1,600 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 March YTD HDD’s March YTD 2016 HDD’s 10.9% Below 10-Yr Average March YTD 2016 HDD’s 8.6% Below March YTD 2015 10-Yr
Slide 11: 1st Quarter Retail Revenues and Sales
Non-Fuel Base Revenues (000's) Percent Change * MWH Percent Change * Residential 47,743$ 1.7% 569,085 1.3% C&I Small 32,140 0.5% 500,226 2.1% C&I Large 8,093 (1.9%) 244,926 (3.2%) Public Authorities 17,400 0.8% 346,235 0.9% Total Retail 105,376$ 0.9% 1,660,472 0.8% Heating Degree Days (HDD's) 1,054
Slide 12: Capital Requirements & Liquidity
A A A Expended $52.7mm for additions to utility plant for the three months ended March 31, 2016 EE made $11.9mm in dividend payments for the three months ended March 31, 2016 At March 31, 2016, EE had liquidity of $253.7mm including a cash balance of $41.3mm and unused capacity under the revol
Slide 13: 2016 Earnings Drivers
13 2016 Earnings Drivers We will provide 2016 guidance after the final outcome of our rate cases is more certain In Texas, new rates will ultimately relate back to January 12, 2016; however, revenues will not be recognized until a resolution is reached, which may cause Q2 to be a challenge. YOY Impa