National Grid Plc · LSE:NG.

National Grid — Investor Presentation (October 2004)

8 slides from National Grid's investor presentation, Oct 29, 2004

  1. Slide 1: BETTA: Transition of Connection and Use of System Agreements

    BETTA: Transition of Connection and Use of System Agreements Guy Phillips CUSC Panel 29th October 2004

  2. Slide 2: Transitional Licence Obligations

    Transitional Licence Obligations • Section E, Condition 18: • Existing User - Party with an Agreement with a TO at 1st January 2005 • GB Offer must be made by 1st February 2005 • Existing Applicant - Party who has made a valid application or has a valid outstanding unsigned offer from a TO at 1st Ja

  3. Slide 3: Transitional Licence Obligations

    Transitional Licence Obligations • GB Offer has to take in to Account: • TO Offer • Transmission Access Rights Methodology • Existing CEC and TEC values • Obligations expected to be in an Offer had it been made post Go Live • Reflect existing Ownership boundaries • Contain any such other terms as ma

  4. Slide 4: Allocation of Access Rights Methodology

    Allocation of Access Rights Methodology • Transition: • Local transmission system infrastructure works only • Non - Local and no interconnector circuit upgrades • E.g. For a connection in SP area, would take in to account SP and SSE reinforcement requirements but not Anglo-Scottish Interconnector ci

  5. Slide 5: Overview - Groups

    Overview - Groups • Group A - Parties who are, at 1st September 2004, existing Users (i.e. has accepted an Offer). • A1 - Parties with an local agreement by the 26th January 2004 • A2 - Parties who enter into an local agreement between the 27th January 2004 and the 1st September 2004 • Group B - Par

  6. Slide 6: Overview - Timeline

    Overview - Timeline Start of GB Offers Go Live Transition (A1,A2 & B1) GB Offers (B2) Group A1 Group A2 Group B1 Group B2 Group C Enduring Process 26 Jan 04 1 Aug 04 1 Sept 04 1 Oct 04 1 Nov 04 1 Dec 04 1 Jan 05 1 Feb 05 1 Mar 05 1 Apr 05

  7. Slide 7: How will this be managed?

    How will this be managed? • TO System studies • Interim SYS • GB Queue • SO-TO Code • NGC Application • TO Construction Offer/Connection Site Specification • GB Offer • User Forum • Connection Agreements Managers

  8. Slide 8: Connection Boundary and Run Off of Existing Connection Issues

    Connection Issues • Connection Boundary - “It is what it is” • Generation only spurs • Application of GB Charging Methodology, i.e. Plugs • Run Off of Existing Agreements/’Clean Break’ • Treatment of Embedded Generation • Treatment of Cascade Hydro

National Grid — Investor Presentation (October 2004) on 6ix