    TSX:GMIN | OTCQX:GMINF 2024: A Year of Execution BUY. BUILD. OPERATE. Q4 & Year-End 2024 Earnings Call March 28, 2025 All figures are in U.S. dollars unless otherwise noted.

  2. Slide 2: Cautionary Statements

    Cautionary Statements Generally, forward-looking information can be identified by use of words such as “outlook”, “objective”, “may”, “could”, “would” , “will” ,“expect”, “intend”, “estimate”, “forecasts”, “project”, “s eek”, “anticipate”, “believes”, “should”, “plans ” “pro forma”, or “continue”, a

  3. Slide 3: Agenda and Speakers

    Agenda and Speakers 01 Corporate Highlights 02 Operational Performance 03 Health & Safety Achievements 04 Financial Results 05 2025 Catalysts & Outlook Louis-Pierre Gignac Julie Lafleur President & CEO, Director CFO and VP, Finance 06 Q&A TSX:GMIN 3

  4. Slide 4: Buy, Build, Operate: Our Strategy in Action

    Buy, Build, Operate: Our Strategy in Action Who We Are: GMIN is anchored by its Tocantinzinho Gold Mine in Brazil, supported by the Gurupi Project in Brazil and the Oko West Gold Project in Guyana — all with significant exploration upside and located in Oko West Gold Project, Guyana Gold | Developme

  5. Slide 5: 2024: A Transformational Year

    2024: A Transformational Year Acquisition of 05 CentroGold Strong Operational Performance Underpinning Robust Financial Results Driving Balance 04 Oko West PEA Reliable Production Sheet Strength Commercial Production at 03 Tocantinzinho Merger with Reunion Gold 02 Acquisition of Oko West Strategic A

  6. Slide 6: Operational and Financial Highlights

    Operational and Financial Highlights Q4 2024 YE 2024 40,147 oz 63,566 oz Gold Production Gold Production $862/oz $972/oz AISC(1,2) AISC(1,2) Continued Execution $2,560/oz $2,545/oz Realized Gold Price(1) Realized Gold Price(1) Robust Cash Generation $58 million l $0.26/share $71 million l $0.44/shar

  7. Slide 7: Operational Performance

    Operational Performance

  8. Slide 8: Tocantinzinho Operational Results

    Tocantinzinho Operational Results Q4 2024 YE 2024 Construction completed on time and on budget. TZ Gold Mine Mining First gold pour completed in July 2024. Ramp-up focused on testing processing circuits with nameplate ore Ore Tonnage Mined kt 2,164 6,406 feeds. Total Tonnage Mined kt 4,269 14,293 Mu

  9. Slide 9: Operating Cost Breakdown

    Operating Cost Breakdown Q4 2024 YE 2024 $US’000, except as otherwise noted Operating Expenses $19,327 $33,698 A newly built gold mine with Royalties $3,732 $4,439 industry leading cost profile. Total Cash Costs $23,059 $38,137 Plus: Sustaining Capital and ARO(1) $7,517 $10,768 Site Level AISC $30,5

  10. Slide 10: TZ Mine – Peer Leading Cost Profile to Drive Cash Flow

    TZ Mine – Peer Leading Cost Profile to Drive Cash Flow Global Gold Mines l All-In-Sustaining Cost Curve $4,000 $3,500 All in Sustaining Costs (US$/oz of Gold Sold) $3,000 $2,500 Q4-24 AISC $2,000 $862 per ounce sold $1,500 $1,000 $500 $- 1st Quartile 2nd Quartile 3rd Quartile 4th Quartile Source: S&

  11. Slide 11: Health & Safety Achievements

    Health & Safety Achievements

  12. Slide 12: 2024 Health & Safety Highlights

    2024 Health & Safety Highlights GMIN remains committed to responsible mining, minimizing impact, empowering communities, and upholding international best practices Strong safety performance to deliver TZ Mine: Operations team currently includes: ✓ 2.5 million person-hours worked ✓ 1,055 employees an

  13. Slide 13: Financial Highlights

    ‘eat Financial Highlights a

  14. Slide 14: Q4 & Full-Year 2024 Financial Highlights

    Q4 & Full-Year 2024 Financial Highlights Q4 2024 YE 2024 $US’000, except as otherwise noted Gold Ounces Sold 39,938 57,082 Realized Gold Price $2,560 $2,545 Revenue $102,254 $145,251 Profitability Net Income $47,597 $62,005 Adjusted Net Income(1) $57,976 $71,084 EBITDA(1) $77,932 $93,993 Adjusted EB

  15. Slide 15: Statement of Cash Flow

    Statement of Cash Flow Q4 2024 YE 2024 $US’000, except as otherwise noted Operating Activities before Changes in Net Working Capital $73,181 $91,313 Net Change in Working Capital ($29,780) ($62,821) Operating Activities $43,401 $28,492 Investing Activities ($26,181) ($119,826) Financing Activities $

  16. Slide 16: Free Cash Flow Summary

    Free Cash Flow Summary(1) Q4 2024 YE 2024 $US’000, except as otherwise noted Operating Activities before Changes in Net Working Capital $73,181 $91,313 Investment in Long Term Inventories $16,953 $16,953 Net Change in Working Capital ($29,780) ($62,821) Sustaining Capital Expenditures inclusive of C

  17. Slide 17: Q4 Cash Position Bridge

    Q4 Cash Position Bridge Figures in USD Millions Free Cash Flow $53 million $200 $17 ($30) $180 $73 ($7) $160 $158 ($36) $6 $140 $13 $141 $120 $100 $105 $80 $60 $40 $20 $0 Cash Balance Cash Flow Investment in Long Changes in Sustaining Starting Cash Non-Sustaining Net Financing FX Adjustments Cash Ba

  18. Slide 18: 2025 Catalysts & Outlook

    2025 Catalysts & Outlook

  19. Slide 19: 2025 Production and Cost Guidance

    2025 Production and Cost Guidance Operational Estimates Unit 2025E 2025 Outlook by Half Ore Tonnes Mined kt 6,600 Total Tonnes Mined kt 23,100 Slightly lower strip Ore Tonnes Mined 47% 53% ratio in H2 Strip Ratio W:O 2.50 Total Tonnes Processed kt 4,300 Mining rate increased Total Tonnes Mined 39% 6

  20. Slide 20: Oko West – Development Update

    Oko West – Development Update PEA HIGHLIGHTS Region 7 100% owned PEA o Planned average gold production 353,000 pa at $986 AISC for 13 years o After-tax NPV5% of $2.5 billion and IRR of 31% at $2,500/oz gold price Guyana 6.5% NSR Royalty held by Government(1) Q3-24 o Startup capital cost of $936 mill

  21. Slide 21: Oko West - Accelerated Timeline to Production

    Oko West - Accelerated Timeline to Production 2024 2025 2026 2027 2028 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 PEA ESIA Permitting Continue to pursue exploration upside and Early works opportunities to enhance value Feasibility Study Detailed Engineering Construction Sign Grinding Open

  22. Slide 22: 2025 Exploration Strategy

    2025 Exploration Strategy Tocantinzinho Mine 688 km2 Land Package Reserve replacement: o Year-end reserves remain at 2Moz after processing 73kozs in 2024. Exploration strategy: o Focused on extending 10-year mine life by targeting near-mine discoveries within 15km of the plant Near mine exploration

  23. Slide 23: 2025 Exploration Strategy Continued

    2025 Exploration Strategy Continued Oko West Project Near Pit Exploration budget: $8 million o Expanding the MRE to improve future mine plans and extend the LOM o Exploring UG mineralization in Blocks 5 and 6 NW Extension o Evaluating additional mineralized saprolite material o Identifying new depos

  24. Slide 24: 2025 Exploration Strategy Continued

    2025 Exploration Strategy Continued Gurupi Project Updated resources of the three known deposits o 44Mt at 1.31 g/t Au for 1.8Moz of indicated resources o 19Mt at 1.29 g/t Au for 0.8 Moz of inferred resources Exploration budget: $2 million to $4 million o Focusing on data compilation and interpretat

  25. Slide 25: 2025 Catalysts & Outlook

    2025 Catalysts & Outlook Upcoming Milestones Gurupi Oko West Tocantinzinho Oko West Oko West Oko West All Assets Published 43-101 Starte of Early Reach Nameplate Feasibility Study Project Financing Continuation of Greenfield and Resource Update Works Construction Capacity Final Environmental Constru

  26. Slide 26: Questions?

    Thank you for joining us today! TSX:GMIN | OTCQX:GMINF Questions? INVESTOR RELATIONS Jessie Liu-Ernsting VP, Investor Relations & Communications Phone: 647.728.4176 Email: [email protected] FOLLOW US: TSX:GMIN 26

  27. Slide 27: Appendix – Additional Information

    Appendix – Additional Information

  28. Slide 28: Q4-24 AISC to Cost of Sales Reconciliation

    Q4-24 l AISC to Cost of Sales Reconciliation Figures in USD Millions $45.0 $40.0 $39.5 $35.0 $34.4 ($7.4) $16.4 $30.0 ($0.1) $25.0 $27.0 $26.9 ($3.9) $23.0 $23.1 $20.0 $15.0 $10.0 $5.0 $0.0 All-In-Sustaining Cost Sustaining Capital Accretion to General and Depreciation Cost of Goods Sold Rehabilitat

  29. Slide 29: Q4-24 AISC to Real Cost Reconciliation

    Q4-24 l AISC to Real Cost Reconciliation Q4-24 Per oz Sold $US’000, except as otherwise noted Operating Expenses $19,327 $484 Royalties $3,732 $93 Total Cash Costs $23,059 $577 Plus: Sustaining Capital and ARO(1) $7,517 $188 Site Level AISC $30,576 $766 Plus: General and Administrative Costs $3,865

  30. Slide 30: 2024 ESG Highlights

    2024 ESG Highlights Environmental Stewardship Social Impact Governance & Human Rights ✓ All operating licenses secured at TZ, including Tailings ✓ R$ 505K+ in social projects: school upgrades, ✓ Human Rights Impact Assessment underway Pond 2 expansion (operational end-2025) healthcare support, commu

  31. Slide 31: Appendix – MRMR Assumptions

    Appendix – MRMR Assumptions

  32. Slide 32: YOY Growth in Mineral Reserves and Resources

    YOY Growth in Mineral Reserves and Resources M&I Resources of 8.3 Moz @ 1.57 g/t, Inferred Resources of 2.4 Moz @ 1.92 g/t M&I Resources Inferred Resources Long Life Assets Tonnes Grade Ounces Tonnes Grade Ounces +10 years of mine life Project Kt g/t Au koz Au kt g/t Au koz Au TZ 55,767 1.22 2,181 7

  33. Slide 33: Mineral Reserves and Resources Assumptions and Notes

    Mineral Reserves and Resources Assumptions and Notes 1. The Mineral Resources described above have been prepared in accordance with the standards of the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") (2014) and the best practices described by CIM (2019). 2. Rounding of values to the

  34. Slide 34: Mineral Reserves and Resources Assumptions and Notes

    Mineral Reserves and Resources Assumptions and Notes Project specific MRMR disclosures continued: 15. The effective date of the Tocantinzinho Mineral Resource Estimate is December 31, 2024. 16. The ore modelling was completed using a numeric estimation in Leapfrog using a cut-off grade of 0.3 g/t Au

  35. Slide 35: Graduation to TSX

    Graduation to TSX TSX:GMIN 35