  1. Slide 1: Line 3 Replacement Program

    Line 3 Replacement Program March 4, 2014 Al Monaco President & CEO Guy Jarvis President, Liquids Pipelines J. Richard Bird Executive Vice President, CFO and Corporate Development

  2. Slide 2: Presenters and Question & Answer Period

    Line 3 Replacement Program • Presenters: Al Monaco President & CEO Guy Jarvis President, Liquids Pipelines J. Richard Bird Executive Vice President, CFO and Corporate Development • Question & Answer Period 2

  3. Slide 3: Legal Notice

    Legal Notice This presentation includes certain forward looking information (FLI) to provide Enbridge shareholders and potential investors with information about Enbridge and management’s assessment of its future plans and operations, which may not be appropriate for other purposes. FLI is typically

  4. Slide 4: Overview, Commercial Terms, Return on Investment, Funding Plan, Execution

    Line 3 Replacement Program • Overview • Commercial Terms • Return on Investment • Funding Plan Update • Execution & Growth Outlook 4

  5. Slide 5: Line 3 Replacement

    Line 3 Replacement • Line 3: – Part of Enbridge Mainline System – Replacing all remaining segments • Capital Investment: – $7 billion (ENB/EEP) • Expected Completion: – 2nd Half of 2017 • 15 Year Toll Surcharge • Shipper Support: – CAPP/RSG 5

  6. Slide 6: Benefits of Line 3 Replacement

    Benefits of Line 3 Replacement • Benefits to Industry – high reliability and assurance to key markets – reduced scheduling impacts of future maintenance – increased scheduling flexibility – improved line balancing • Supports our #1 priority - safety and operational reliability • Positive investment

  7. Slide 7: Capital Costs

    Capital Costs • Preliminary unclassified estimates of CDN $4.2 billion and U.S. $2.6 billion • 2014 – 2017 integrity capital savings of CDN $1.0 billion and U.S. $0.1 billion, increasing thereafter 7

  8. Slide 8: IJT/CLT Surcharges

    Line 3 Replacement Program IJT/CLT Surcharges • U.S. $0.80 surcharge to Hardisty to Flanagan IJT benchmark toll for years 1-10, $0.75 years 11-15 • Corresponding surcharges apply to barrels moving within Western Canada under Canadian Local Toll • Applies to all volumes • Distance adjusted for longer

  9. Slide 9: U.S. FSM Surcharge

    Line 3 Replacement Program U.S. FSM Surcharge • Incremental U.S. capital included in existing Facilities Surcharge Mechanism surcharge • Fixed 10.75% cost-of-service return on 55% equity applying standard 154B methodology 9

  10. Slide 10: Capacity Implications

    Capacity Implications • Ex-Gretna annual operating capacity rises to 2,850 kbpd following Alberta Clipper expansions – System in balance ex-Superior • Line 3 Replacement Program will not increase effective system capacity ex-Gretna • Capacity of 2,850 kbpd will accommodate expected late decade throu

  11. Slide 11: Returns and Profile

    Line 3 Replacement Program Returns and Profile • U.S. capital is low double digits full life return on equity on incremental capital, slightly tilted profile • Canadian capital is low double digits full life return on incremental equity at 2,600 kbpd, tilted return profile – Varies by up to a couple

  12. Slide 12: 2013 – 2017 Funding Requirements

    2013 – 2017 Funding Requirements Excluding Sponsored Investments • Enbridge joint funding of Sandpiper eliminated by Marathon Petroleum funding • Assumes Enbridge funds 50% of U.S. Line 3 program • $2 billion of discretionary unsecured growth capital deferred beyond 2017 Maintenance Capital 5.6 Secu

  13. Slide 13: Cost of Equity Optimization and Flexibility

    Cost of Equity Optimization and Flexibility 2013 – 2017 Remaining Requirement $2.7 Billion: $ Billions Preferred Shares $1.8 Sponsored Vehicle Drop Downs $2.0 New U.S. Co-Funding Vehicle $1.0 TOTAL $4.8 ENB Public Equity ~ 13

  14. Slide 14: Project Execution

    Project Execution Proven Execution Record Disciplined Project Execution Capital Placed In Service 2008 - 2013 • Successful Alberta Clipper team to execute Line 3 $17 B • Well-known construction corridor • Relationships with landowners and communities along Line 3 Portfolio completed at 1% under tota

  15. Slide 15: Enterprise Wide Growth Capital Program

    Enterprise Wide* Growth Capital Program (By In-service Date) - Unsecured - Commercially Secured $41 B $35 B $36 B $36 B $5 B $7 B $10 B $17 B $36 B $29 B $26 B $18 B Enbridge Day 2012 Enbridge Day 2013 Q4 2013 Earnings Call Current** (2012 – 2016) (2013 – 2017) (2013 – 2017) (2013 – 2017) * Includes

  16. Slide 16: Industry Leading EPS Outlook

    Industry Leading EPS Outlook Secured Capital 2013 – 2017 by An Industry Leading EPS* Return Profile Growth Outlook (but lumpy) Flat Tilted ($ Billions) ($ Billions) Liquids Pipelines $3.8 $2.2 – Alberta Regional Liquids Pipelines • Tilted Return $7.5 $9.7 – Market Access Initiatives Projects - $7B L

  17. Slide 17: Summary

    Line 3 Replacement Program Summary • Provides enhanced ability to reliably accommodate shipper throughput requirements • Significant incremental capital investment opportunity for ENB and EEP on attractive commercial terms • Additional funding requirements are modest and manageable • Major Projects

  18. Slide 18: Q&A

    Line 3 Replacement Program March 4, 2014 Q&A