  1. Slide 1: Park Elektrik Üretim Madencilik Sanayi ve Ticaret A.Ş.

    Slide 1: Park Elektrik Üretim Madencilik Sanayi ve Ticaret A.Ş.

    Park Elektrik Üretim Madencilik Sanayi ve Ticaret A.Ş. January 25, 2013

  2. Slide 2: Contents

    Slide 2: Contents

    Contents I. Park Elektrik Overview 3 II. Ciner Group in Brief 7 III. Operations 10 IV. Reserves 13 V. Planned Investments 20 VI. Financial Structure 24 VII. Evaluation of The Latest Financial Tables 33 VIII. Corporate Governance Rating 39 Park Elektrik Madencilik January 2013 2

  3. Slide 3: I. Park Elektrik Overview

    Slide 3: I. Park Elektrik Overview

    I. Park Elektrik Overview Park Elektrik Madencilik January 2013 3

  4. Slide 4: The Company

    Slide 4: The Company

    The Company  Initially offered to public in 1997, Park Elektrik is the sole copper mining company on the ISE. The company currently operates two mines namely; a copper mine in Siirt and an asphaltite (a kind of hydrocarbon) mine in Sırnak.  Park Elektrik took over operational rights of copper mine

  5. Slide 5: Ownership Structure

    Slide 5: Ownership Structure

    Ownership Structure Others 32% Park Holding 61% Turgay Ciner 7% Park Elektrik Madencilik January 2013 5

  6. Slide 6: Participation, Park Termik

    Slide 6: Participation, Park Termik

    Participation, Park Termik  Park Elektrik has 10% stake in Park Termik Elektrik San. ve Tic. A.S., a Ciner Group company which is involved in thermal power generation in Çayırhan, Ankara.  Park Termik operates Çayırhan Thermal Power Plant which has a total production capacity of 620 MW, in four un

  7. Slide 7: II. Ciner Group in Brief

    Slide 7: II. Ciner Group in Brief

    II. Ciner Group in Brief Park Elektrik Madencilik January 2013 7

  8. Slide 8: Ciner Group, Main Line of Businesses

    Slide 8: Ciner Group, Main Line of Businesses

    Ciner Group, Main Line of Businesses Ciner Group Park Holding Ciner Yayın Holding Energy & Mining Commerce, Media Group Industry & Group Services Group Major Companies Major Companies Major Companies Park Elektrik, Park Ciner Marine, & Brands Termik, Silopi Elektrik, Ciner Aviation, Haberturk Newspa

  9. Slide 9: Ciner Group, Introduction

    Slide 9: Ciner Group, Introduction

    Ciner Group, Introduction  Park Holding, the main shareholder of Park Elektrik with 61% share, is solely owned by Mr. Turgay Ciner.  Ranking among the largest Groups of Turkey, Ciner Group’s history goes back to 1978 when it was founded. The Group has a diversified business portfolio. However, the

  10. Slide 10: III. Operations

    Slide 10: III. Operations

    III. Operations Park Elektrik Madencilik January 2013 10

  11. Slide 11: Park Elektrik's Existing & Planned Facilities

    Slide 11: Park Elektrik's Existing & Planned Facilities

    Park Elektrik’s Existing & Planned Facilities Natural Gas Power Plant Edirne Copper Mine Siirt HPP Natural Gas Diyarbakı Asphaltite Power Plant r Mine Adana Sırnak Park Elektrik Madencilik January 2013 11

  12. Slide 12: I) Madenköy Copper Zone

    Slide 12: I) Madenköy Copper Zone

    I) Madenköy Copper Zone  Park Elektrik acquired operation license of Madenkoy copper mine in 2004 from Eti Holding, a state-owned entity engaged in mining businesses, for TL9.4 mn.  Mine operations started in late 2006 in the copper zone. So far, around 5.1 mn tons of ore was extracted in the copp

  13. Slide 13: Micromine Reserve Report Based On JORC

    Slide 13: Micromine Reserve Report Based On JORC

    Micromine Reserve Report Based On JORC  According to a JORC (Joint Ore Resources Code) compliant reserve report issued by Micromine Consulting Services in November 2011, based on the drilling and sampling works by Eti Holding (1981), Preussag AG Metall (1988) and Park Elektrik, the total reserves o

  14. Slide 14: Capacity Expansion & Condemnation

    Slide 14: Capacity Expansion & Condemnation

    Capacity Expansion & Condemnation Concentration Facility 2011 2012 2013 Ore Processing Capacity (ton) 750,000 1,200,000 1,800,000 * Capacity increase to 1,2 mn tons was realized in October 2011.  In parallel with growing reserves in the Madenkoy copper zone, the company increased its concentration

  15. Slide 15: 2012 Production Targets & Realizations by 9M12

    Slide 15: 2012 Production Targets & Realizations by 9M12

    2012 Production Targets & Realizations by 9M12 JAN. FEB. MAR. APR. MAY JUNE JULY AUG. SEP. OCT. NOV. DEC. TOTAL Actual Actual Actual Actual Actual Actual Actual Actual Actual Target Target Target Target Ore (wmt) 100,191 84,912 96,148 102,127 104,014 102,232 91,266 75,655 95,524 94,000 93,000 106,00

  16. Slide 16: Production Targets

    Slide 16: Production Targets

    Production Targets 2011A 2012E 2013E Ore (tons) 949,731 1,200,000 1,500,000 Growth - 27% 25% Concentrated Copper (wmt) 77,510 90,000 105,000 Growth - 17% 17% Park Elektrik Madencilik January 2013 16

  17. Slide 17: Shift To Open Pit Mining & Stripping Expenses

    Slide 17: Shift To Open Pit Mining & Stripping Expenses

    Shift To Open Pit Mining & Stripping Expenses  Park Elektrik plans to shift its copper mining operations from underground to open-pit mining by the mid of 2013, while until mid of the year underground mining will continue.  Based on projections, production through open pit mining will continue unt

  18. Slide 18: 2013 Estimated Capex In Copper Zone

    Slide 18: 2013 Estimated Capex In Copper Zone

    2013 Estimated Capex In Copper Zone CAPEX TL mn ORE PRODUCTION 88 - Stripping 82 - Others 6 FACILITY 30 OTHER 26 TOTAL 144 Park Elektrik Madencilik January 2013 18

  19. Slide 19: II) Silopi Asphaltite Zone

    Slide 19: II) Silopi Asphaltite Zone

    II) Silopi Asphaltite Zone  Asphaltite is a petroleum-origin hydrocarbon with a thermal value of 5,500-5,800 kcal/kg.  Park Elektrik has the operational rights of Silopi asphaltite mine until 2033. Estimated asphaltite reserve in Silopi is around 35 mn tons based on Turkish Coal Enterprise (TKI) r

  20. Slide 20: Open-Pit Mining in Silopi

    Slide 20: Open-Pit Mining in Silopi

    Open-Pit Mining in Silopi Park Elektrik Madencilik January 2013 20

  21. Slide 21: IV. Planned Investments

    Slide 21: IV. Planned Investments

    IV. Planned Investments Park Elektrik Madencilik January 2013 21

  22. Slide 22: Diyarbakır HPP

    Slide 22: Diyarbakır HPP

    Diyarbakır HPP  Installed capacity will be 50.5 MW.  Production license is valid for 49 years.  According to recent feasibility studies, estimated investment amount is US$ 100 mn.  The compay plans to start HPP investment in the second half of 2013 with an estimated investment amount of TL27mn f

  23. Slide 23: Ceyhan Natural Gas Power Plant

    Slide 23: Ceyhan Natural Gas Power Plant

    Ceyhan Natural Gas Power Plant  Park Elektrik applied to Energy Market Regulatory Authority for a license to establish a NGPP in Ceyhan, Adana.  Installed capacity will be 423 MW*.  Production license will be valid for 49 years.  Estimated investment amount is Euro 250 mn. *The technological adv

  24. Slide 24: Edirne Natural Gas Power Plant

    Slide 24: Edirne Natural Gas Power Plant

    Edirne Natural Gas Power Plant  Park Elektrik applied to Energy Market Regulatory Authority for a license to establish a NGPP in Edirne.  Installed capacity will be 423 MW.  Estimated investment amount is Euro 250 mn. Park Elektrik Madencilik January 2013 24

  25. Slide 25: V. Financial Structure

    Slide 25: V. Financial Structure

    V. Financial Structure Park Elektrik Madencilik January 2013 25

  26. Slide 26: Annual Concentrated Copper Production (wmt)

    Slide 26: Annual Concentrated Copper Production (wmt)

    Annual Concentrated Copper Production (wmt) * Annual production declined due to production halt of four-month in 2010. Park Elektrik Madencilik January 2013 26

  27. Slide 27: Annual Con. Copper (dmt) & Cathode (ton) Sales

    Slide 27: Annual Con. Copper (dmt) & Cathode (ton) Sales

    Annual Con. Copper (dmt) & Cathode (ton) Sales 60,931 59,163 55,054 47,417 32,239 9,271 1,210 2006 2007 2008 2009 2010 2011 * In 2010, there was a production halt of four months. ** 6,613 wmt of concentrated copper were used to produce 1,210 mt copper cathode. This pushes 2011 total sales up to 61,6

  28. Slide 28: Annual Asphaltite Sales (ton)

    Slide 28: Annual Asphaltite Sales (ton)

    Annual Asphaltite Sales (ton) 476.899 434.333 204,856* 2009 2010 2011 * Asphaltite operations started in mid 2009. Park Elektrik Madencilik January 2013 28

  29. Slide 29: Total Sales Revenues (TL)

    Slide 29: Total Sales Revenues (TL)

    Total Sales Revenues (TL) copper asphaltite 19,709,514 151,135,664 110,713,833 80,040,645 8,211,605 19,314,397 69,857,081 64,191,660 2007 2008 2009 2010 2011* * Revenues from other sales is 1,616,016. Park Elektrik Madencilik January 2013 29

  30. Slide 30: Net Earnings (TL mn)

    Slide 30: Net Earnings (TL mn)

    Net Earnings (TL mn) 100.8 74.8 37.2 19.8 19.4 2007 2008 2009 2010 2011 Park Elektrik Madencilik January 2013 30

  31. Slide 31: Breakdown of COGS, as of YE11

    Slide 31: Breakdown of COGS, as of YE11

    Breakdown of COGS, as of YE11 Maintanence, Others, 10% 4% Machinery Rent Costs, 3% Labor Costs, 31% Depreciation, 17% Fuel & Energy, Mach. Spare 12% Part Repl. Costs, 24% Park Elektrik Madencilik January 2013 31

  32. Slide 32: Annual Margin Comparison

    Slide 32: Annual Margin Comparison

    Annual Margin Comparison (TL mn) 2007 2008 2009 2010 2011 Sales 80 111 79 84 173 Gross Profit 47 73 32 44 107 Gross Margin 59% 66% 41% 52% 62% EBITDA 43 62 24 42 112 EBITDA Margin 52% 56% 30% 50% 65% Net Earnings 20 75 19 37 101 Net Margin 25% 68% 25% 44% 58% Park Elektrik Madencilik January 2013 32

  33. Slide 33: Sources of Financing (TL mn)

    Slide 33: Sources of Financing (TL mn)

    Sources of Financing (TL mn) Shareholders' Equity Total Debt 41 33 30 60 443 66 53 343 302 8 14 223 130 143 88 100 2004 2005 2006 2007 2008 2009 2010 2011 * Park Elektrik has no financial debt. Park Elektrik Madencilik January 2013 33

  34. Slide 34: VI. Evaluation of 9M12 Financial Results

    Slide 34: VI. Evaluation of 9M12 Financial Results

    VI. Evaluation of 9M12 Financial Results Park Elektrik Madencilik January 2013 34

  35. Slide 35: Evaluation of 9M2012 Financial Results

    Slide 35: Evaluation of 9M2012 Financial Results

    Evaluation of 9M2012 Financial Results  9M12, total copper concentrate production was realized as 68,060 wmt, indicating 19% increase compared to the same period of 2011. Total sales for copper products was realized as 54,225 dmt for concentrate copper and 2,521 mt for cathode copper.  Total reven

  36. Slide 36: Production & Sales Amount

    Slide 36: Production & Sales Amount

    Production & Sales Amount Production 9M11 9M12 % Concentrated Copper (wmt) 57,355 68,060 19 Cathode Copper (MT) 1,846 902 -52 Asphaltite (ton) 318,177 226,256 -29 Sales 9M11 9M12 % Concentrated Copper (dmt) 43,044 54,225 26 Cathode Copper (MT) 1,210 2,521 109 Asphaltite (ton) 318,177 226,256 -29 Par

  37. Slide 37: Sales Breakdown (TL) & Gross Margin by Products

    Slide 37: Sales Breakdown (TL) & Gross Margin by Products

    Sales Breakdown (TL) & Gross Margin by Products 9M11 9M12 % Copper Sales 122,768,872 175,925,695 44 Gross Margin of Copper 64% 58% - Asphaltite Sales 14,087,542 18,707,416 33 Gross Margin of Asphaltite 20% 14% - Other Sales 1,283,988 4,650,991 263 Total Sales Revenues 138,140,402 199,284,102 45 Over

  38. Slide 38: Income Statement (TL)

    Slide 38: Income Statement (TL)

    Income Statement (TL) 9M11 9M12 % Sales 138,140,402 199,284,102 44% COGS -56,182,544 -95,927,254 71% Gross Profit 81,957,858 103,356,848 26% Gross Margin 59% 52% - Marketing Selling & Dist. Exp. -6,404,496 -9,689,055 51% General Adm. Expenses -11,684,286 -11,772,337 1% Other Operating Income 15,706,

  39. Slide 39: Summary Balance Sheets (TL)

    Slide 39: Summary Balance Sheets (TL)

    Summary Balance Sheets (TL) YE11 9M12 Current Assets 297,678,924 288,657,504 Fixed Assets 186,424,631 188,986,340 TOTAL ASSETS 484,103,555 477,643,844 Short Term Liabilities 34,255,807 40,499,192 Long Term Liabilities 6,391,196 5,997,811 Shareholders Equity 443,456,552 431,146,841 TOTAL LIABILITIES

  40. Slide 40: Corporate Governance Rating

    Slide 40: Corporate Governance Rating

    Corporate Governance Rating Park Elektrik was rated with 8.82 as a result of the Corporate Governance MAIN SECTIONS: Avg. 88,24 study done by SAHA Kurumsal Rating Agency. According to report done by Board Of Directors 78.77 SAHA, the rating means that the company performs “very good” in terms of Cap

  41. Slide 41: Thank You. Contacts

    Slide 41: Thank You. Contacts

    THANK Y O U. CONTACTS Yesim Bilginturan Selim Erdogan IR Manager IR Manager Phone: +90 216 531 25 33 +90 216 531 25 35 [email protected] [email protected] www.parkelektrik.com.tr www.cinergroup.com.tr Park Elektrik Madencilik January 2013 41