  1. Slide 1: Maintaining a social license to operate

    Maintaining a social license to operate Credit Suisse – 2013 Coal Seam Gas Conference Rebecca Pickering, General Manager Strategic Planning & Development, Origin| 13 November 2013 Commercial in confidence

  2. Slide 2: Delivering energy needs via sustainable developments

    Delivering energy needs via sustainable developments • Origin is delivering today’s energy needs and searching and innovating to create tomorrow’s tomorrow s energy solutions • We are targeting sustainable development of lower carbon fuels, fuels in particular coal seam gas (CSG) and renewable energ

  3. Slide 3: Our Social Licence to Operate – How does it work?

    Our Social Licence to Operate – How does it work? • Australia’s pre-eminent CSG to LNG project based on Australia Australia’ss largest 2P CSG reserves • Areas of operation stretch from the gas fields of the Western Downs of Queensland along a 530km pipeline up to the LNG facility on Curtis Island •

  4. Slide 4: Respecting and resolving community fears

    Respecting and resolving community fears In the air On the land Under the ground 4|

  5. Slide 5: Respecting and resolving community fears – In the air

    Respecting and resolving community fears In the air • Carbon emissions • Noise • Visual impact 5|

  6. Slide 6: Respecting and resolving community fears – On the land

    Respecting and resolving community fears On the land • Change of land use from rural to co-existence • Will it be intrusive? • Can we really co co-exist? exist? • Will it undermine or contaminate food production? p • Will I get enough compensation? • How big will the footprint be on my land? • How w

  7. Slide 7: Respecting and resolving community fears – Under the ground

    Respecting and resolving community fears Under the ground • Will you take away/reduce our water supply? • Will yyou contaminate our water supply with chemicals(fraccing)? • Will you cause gas to be in our water supply? 7|

  8. Slide 8: Respecting and resolving community fears

    Respecting and resolving community fears • We need community support to deliver our projects • Support comes from respecting and addressing community: • Recognising the attachment l dh ld landholders h have to their h lland d • Respecting the communities in which we live and work; and • Implementing

  9. Slide 9: Driving positive change through engagement

    Driving positive change through engagement • The support of the regional communities is recognised as a key success factor in terms of delivering our projects • Effective engagement requires the community to have access to ways to express their views and provide feedback 9|

  10. Slide 10: Securing our social licence to operate

    Securing our social licence to operate We listen to communities, working with them to deliver locally relevant solutions Local concern Response Youth driving on regional roads CARS driver training program – to develop driving skills Skills drain & local kids leaving Community Skills Scholarship Prog

  11. Slide 11: Social license to operate must be earned through trust and respect

    Social license to operate cannot be taken for granted and must be earned through the trust and respect of the community 11 |

  12. Slide 12: Thank you

    Thank you y

  13. Slide 13: Coal Seam Gas Water Management

    Coal Seam Gas Water Management Credit Suisse – 2013 Coal Seam Gas Conference Andrew Moser, Groundwater Manager, Origin on behalf of Australia Pacific LNG I 13 November 2013 The Australia Pacific LNG Project is a coal seam gas (CSG) to liquefied natural gas (LNG) project delivering a cleaner, greener

  14. Slide 14: The Big Picture

    The Big Picture • The Th Queensland Q l d CSG iindustry d t operates t in two of the most iconic hydrological systems in the world – The Great Artesian Basin and the Murray Darling Basin. • It imposes new stresses, but also new management opportunities for these • CSG water management is essentially

  15. Slide 15: Groundwater Impact Assessment

    Groundwater Impact Assessment 15 |

  16. Slide 16: Predicted Groundwater Impacts – CSG

    Predicted Groundwater Impacts – CSG • Office of Groundwater Impact Assessment modelling estimates 528 bores exceeding 5m drawdown ((make g good assessment trigger) gg ) over life of projects, 80% in the coal target formation. • This is 2.5% of bores in the management area assuming all 4 CSG to LNG p

  17. Slide 17: Predicted Impacts – Holistic

    Predicted Impacts – Holistic

  18. Slide 18: Groundwater Impact Monitoring

    Groundwater Impact Monitoring 18 |

  19. Slide 19: Groundwater Monitoring – Landholder Bore Baseline Surveying

    Groundwater Monitoring – Landholder Bore Baseline Surveying y g • Approximately 950 Australia Pacific LNG landholders. • Took over 3 years, commenced before Environmental Impact Statement approval and a year prior to guidelines being implemented. • Construction details, water level, water use and ex

  20. Slide 20: Groundwater Monitoring Bore Network

    Groundwater Monitoring Bore Network • Monitoring requirements legislated by multiple state and federal regulators for groundwater and springs. • Current state requirement in excess of 500 monitoring bores/zones for Surat/Southern Bowen CSG operators. • Approximately 200 bores to be monitored – 160 b

  21. Slide 21: Springs Monitoring Network

    Springs Monitoring Network • Monitoring of 122 spring vents, mainly off lease, up to 100km from leases. • Includes I l d spring i water pressures, fl flows, quality, flora and fauna. • Integrated with several research programs. 21 |

  22. Slide 22: Groundwater Impact Mitigation

    Groundwater Impact Mitigation 22 |

  23. Slide 23: Aquifer Injection

    Aquifer Injection • Spring Gully • Reedy Creek • Approved 8.1 ML/d aquifer injection • Proposed 30 ML/d aquifer injection scheme targeting g g the Precipice p scheme targeting the Precipice Aquifer Aquifer • 2 Primary Injection Bores and 1 • 20 Primary Injection Bores secondary • 8 in-field monitori

  24. Slide 24: Make Good

    Make Good • Pro-active provision of alternatives for groundwater supplies which are materially impacted by CSG production. • Assessed over upcoming 3 year period through Underground Water Impact Report Immediately Impacted Area. • Make Good Measure must be agreed by both landholder and operator and

  25. Slide 25: Produced Water Management and Monitoring

    Produced Water Management and Monitoring 25 |

  26. Slide 26: From 'Waste' to Resource - Managing Produced Water

    From ‘Waste’ to Resource - Managing g g Produced Water • Varying climatic, land use, hydrological and hydrogeological conditions necessitate a variety of water management solutions • With the th exception ti off some untreated t t d water t used for construction purposes, all CSG water is treated us

  27. Slide 27: Irrigation

    Irrigation • Spring Gully - Drip irrigation of 300ha of bio-fuel plantation (Pongamia) Distribution network between 2 sites for up to 4300ha of new and existing landholder irrigation. • Proposed beneficial use scheme to supply treated water from Condabri and Talinga g to support pp a landholder irri