Slide 1: Ganaraska Wind Farm Community Liaison Committee Meeting #2
Ganaraska Wind Farm Community Liaison Committee Meeting #2 May 2, 2017, 6:30-8:30 pm, Orono Arena and Community Centre
Slide 2: Agenda
Agenda 1. Welcome 2. Presentation by NRSI on Post-construction Bird & Bat Monitoring Program 3. Project update o Operations/Maintenance o Complaints o Community Engagement 4. Community Enhancement Fund Update o Recent Initiatives o Upcoming 2017 Initiatives 5. Open Public Forum (20 minutes) 6. Closi
Slide 3: Welcome
CAPSTONE POWER CORP. Welcome
Slide 4: Presentation by NRSI on Post-Construction Bird & Bat Monitoring Program
2 Presentation by NRSI on Post-Construction Bird & Bat Monitoring Program
Slide 5: Project Update
CAPSTONE POWER CORP. Project Update
Slide 6: Operations and Maintenance
Operations and Maintenance ‣ Welcome to Steve Rankin, Site Manager Mobile: (519) 939-8154 Email: [email protected] ‣ Performance to Date in 2017 January February March April Totals Target YTD 2017 % of target Production (Mwh) 4,902 5,041 6,397 5,698 22,039 20,048 109.9% # of Homes 5,521 5,67
Slide 7: Complaints
Complaints ‣ Complaint Response Protocol on project website ‣ Since COD, the project has received a total of five complaints which have been filed with the MOECC: ‣ four noise complaints ‣ one complaint about brownouts ‣ Additional concerns have been received: ‣ Bird, bat and species at risk mortali
Slide 8: Ganaraska Wind Farm site map
Ps j 418 CAPSTONE POWER CORP. Projection: NAD 1983 UTM Zone 17 Ganaraska Wind Farm Municipality of Clarington Orono, Ontario “€ — Unlit Turbine ~¢ Lit Turbine @ = Substation —— Electrical Line ——— Access Road [Point of Common Coupling (PCC) —— Highway —— Existing Road = Building Participating Proper
Slide 9: Community Engagement
Community Engagement Willie Woo (Clarington Regional Councillor Wards 3 & 4), David Eva (Capstone CEO) and Doug Kennedy (Green Side Up landscaping) during November tree plant ‣ Presentation to Durham Environmental Advisory Committee on April 13, 2017 ‣ Upcoming participation at Doors Open Clarington
Slide 10: Community Enhancement Fund Update
4 Community Enhancement Fund Update
Slide 11: Recent Initiatives
Recent Initiatives ‣ On April 1, 2017, the Ganaraska Region Conservation Authority (GRCA) hosted a Maple Syrup Festival for the community. Capstone participated as a sponsor under the Community Enhancement Fund. 11
Slide 12: Upcoming 2017 Initiatives
Upcoming 2017 Initiatives ‣ All 2017 funds have been distributed ‣ Doors Open Clarington o Capstone as event sponsor o Ganarska Wind Farm as a tour site - June 10 from 10-4 o Visit www.doorsopenclarington.com ‣ Other approved 2017 initiatives include: o Orono Crown Land Trust – Trail Enhancement o C
Slide 13: Open Public Forum
CAPSTONE POWER CORP. Open Public Forum
Slide 14: Closing
CAPSTONE POWER CORP. Closing