  1. Slide 1: Responsible mining for a sustainable future

    Responsible mining for a sustainable future Q3 2026 July - September Kiruna 5 November 2026

  2. Slide 2: Disclaimer

    Mining for forthe thefuture future 2 Disclaimer Forward -looking statements This presentation contains forward -looking statements, which relate to events or future performance and reflect Gruvaktiebolaget Viscaria (“Viscaria” or the “Company”) current expectations and assumptions. Such forward -loo

  3. Slide 3: Q3 2026

    Mining for the future 3 Q3 2026 • Project execution at high pace: o Viscaria Village inaugurated o Leväjärvi railyard inaugurated o WTP 1000 in ramp up and handover • Processing plant construction progressing rapidly • Agreements with Sandvik & Metso • EU Commission CRMA Strategic Project status • E

  4. Slide 4: Leväjärvi railyard inauguration

    Mining for the future 4 Leväjärvi railyard inauguration Leväjärvi railyard inauguration • Leväjärvi railyard inaugurated with 200 people attending • Connecting Viscaria to the Iron Ore Line • Access to transport routes both north and south

  5. Slide 5: Mining for the future

    Mining for the future

  6. Slide 6: Viscaria Village inauguration

    Mining for the future 6 Viscaria Village inauguration • First guests arrived in August • Inauguration in Sept​ember • 132 rooms for 264 residents on rotating 7/7 shift • Alleviating Kiruna municipality August 11 2026

  7. Slide 7: Financing update

    Mining for the future 7 Financing update • Project financing moving forward • Anticipated completion before end of January with credit approval from lead arrangers around year -end • Exceptionally rare: only ~6 –7 European mining project financings since 2016 • Even market leaders see limited volume

  8. Slide 8: Project update – overview

    Mining for the future 8 Project update – overview

  9. Slide 9: Mine

    Mining for the future 9 Mine • Open -pit development is ongoing • Weekly blasting ongoing • Dewatering according to plan • Underground rehabilitation advancing • Sandvik selected as long -term equipment partner for production drilling and loading • Mine organisation continues to scale up • Detailed

  10. Slide 10: Infrastructure & Logistics

    Mining for the future 10 Infrastructure & Logistics • Railyard inaugurated, enabling five trains per week both north and south bound • Loading hall storage capacity o 10,000 tonnes of copper concentrate o 20,000 tonnes of iron concentrate • The tailings dam construction, including clarification pond

  11. Slide 11: Processing & Water Treatment

    Mining for the future 11 Processing & Water Treatment • Processing plant construction is progressing rapidly and according to schedule • Engineering works and organisational ramp -up intensified. • Process flowsheet further refined and validated – additional metallurgical studies completed. • Procur

  12. Slide 12: Project schedule

    Mining for the future 12 Project schedule 2026 2027 2028 SO 4 treatment installation Open pit mining Mining Dewatering Underground rehabilitation Underground mining Infrastructure Permanent power installation Railyard Tailings Tailings area incl. clarification pond Processing plant weather -proof bu

  13. Slide 13: Exploration Highlights, Q3 2026: Second hole confirms high-grade Cu 700 m beyond D-Zone

    Mining for the future 13 Exploration Highlights, Q3 2026: Second hole confirms h igh -grade Cu 700 m beyond current D -Zone resource Cross -section of the Viscaria deposit’s mineralised zones 6 metres @ 1.9% copper in 2 nd major step -out in D -Zone + 750 m ➢ Drillhole VDD26007 intersects several st

  14. Slide 14: D-Zone Exploration Results, Q3: 6 metres @ 1.9% copper

    Mining for the future 14 SOUTHWEST NORTHEAST D-Zone Exploration Results, Q3: 6 metres @ 1.9% copper D-Zone Mineral Resource Cu (%) x Thickness (m) <1 w/ grade -thickness contours 1- 3 29.2 Mt @ 0.91% Cu SOUTH SHOOT Intersected 700 m beyond resource 3-5 5-7 NORTH SHOOT Confirms high -grades in VDD250

  15. Slide 15: D-Zone Exploration Results, Q3: 6 metres at 1.9% Cu in main D-Zone horizon

    Mining for the future 15 D-Zone Exploration Results, Q3: 6 metres at 1.9% Cu in main D -Zone horizon, 700 metres beyond current resource VDD26007: 1269.0 to 1274.7 m downhole depth Chalcocite blebs within massive magnetite partially replaced by hematite 0.20% Cu, 16.8% Fe 2.21% Cu, 33.7% Fe 1.78% Cu

  16. Slide 16: VDD26007: Cross-cutting chalcocite veinlets in massive magnetite

    Mining for the future 16 D-Zone Exploration Results, Q3: VDD26007: Cross -cutting chalcocite veinlets in massive magnetite( -hematite) Chalcocite ( Cu ₂S ) contains around 80 wt % copper, in comparison to chalcopyrite ( CuFeS ₂) which contains around 35 wt % copper

  17. Slide 17: D-Zone Exploration Results, Q3: 9.5 metres at 1.4% Cu

    Mining for the future 17 D-Zone Exploration Results, Q3: 9.5 metres at 1.4% Cu , incl. 5 metres at 2.4% Cu in HW metasediments VDD26007: 1243.7 to 1253.2 m downhole depth 0.04% Cu 1.35% Cu 0.06% Cu Vein -hosted assemblage of copper -rich sulphide minerals: Bornite ( Cu ₅FeS ₄), Covellite ( CuS ), Ch

  18. Slide 18: D-Zone Exploration Results, Q3: 6 metres at 1.3% Cu

    Mining for the future 18 D-Zone Exploration Results, Q3: 6 metres at 1.3% Cu , incl. 2 metres at 2.1% Cu also in HW metasediments VDD26007: 1217.1 to 1223.0 m downhole depth 0.32% Cu, 0.55 ppm Ag 2.04% Cu, 2.62 ppm Ag 2.07% Cu, 2.19 ppm Ag 1.19% Cu, 2.27 ppm Ag Bedding -concordant, elongate ‘streaks

  19. Slide 19: B-Zone Exploration Results, Q3: Further copper mineralisation confirmed

    Mining for the future 19 B -Zone Exploration Results, Q3: Further copper mineralisation confirmed beyond the current resource B -Zone Mineral Resource SOUTHWEST w/ grade -thickness contours NORTHEAST VDD25013 and VDD26005 43.9 Mt @ 0.77% Cu NEW INTERSECTION ➢ Confirms extensions of B -Zone mineralis

  20. Slide 20: Integrated geology & geophysics point to a potential feeder corridor

    Mining for the future 20 Framing the latest exploration results on the deposit -scale: Integrated geology & geophysics point to a potential feeder corridor Abundant feeder veins in B Deep, ex.VDD25013D Plan view Viscaria deposit Unconstrained MT inversion Major break in conductivity: Depth slice at

  21. Slide 21: Reflection seismic survey completed during Q3

    Mining for the future 21 Reflection seismic survey completed during Q3 High -resolution imaging of the Viscaria deposit to guide exploration Seismic surveying at Viscaria – carried out safely alongside ongoing site construction Investigating Viscaria’s depth potential • Survey completed in August wi

  22. Slide 22: Building new academic collaborations

    Mining for the future 22 Building new academic collaborations Three MSc projects to deepen our geological understanding of Viscaria Tracing metal and sulphur sources at Viscaria Rebecca Liebson , supervised by Adam Simon – University of Michigan ➢ Investigating the geochemical and isotopic fingerpri

  23. Slide 23: Recent MSc theses now available on Viscaria's website

    Mining for the future 23 Recent MSc theses now available on Viscaria’s website: viscaria.com > This is Viscaria > Academic Papers

  24. Slide 24: Looking ahead to the Q1 2027 Mineral Resource update

    Mining for the future 24 Looking ahead to the Q1 2027 Mineral Resource update Latest results reinforce Viscaria’s resource growth potential Viscaria’s Mineral Resources (Mt) through time Future potential D- and B -Zone results confirm extensions ➢ Recent drill intersections in both zones display gra

  25. Slide 25: Financial performance in summary

    Mining for the future 25 Financial performance in summary MSEK Q3 Q3 Q2 2026 2025 2026 Capitalised expenses related to exploration and evaluation assets 152 58 127 Operating profit -23 -14 -24 Net profit -21 -28 -41 Cash flow for the period 123 -24 346 Exploration and evaluation 2,207 1,571 2,055 as

  26. Slide 26: Project financing

    Mining for the future 26 Project financing • The project financing continues to progress well • Expected bank syndicate; o Lead arrangers ING and Societe Generale o 4 -6 other European commercial banks • Viscaria expect to complete the debt financing process within next quarter (90 days) • Finalize

  27. Slide 27: Viscaria is uniquely positioned

    Mining for the future 27 Viscaria is uniquely positioned  Copper prices are at historically • Record high copper demand , supported by strong fundamentals with no viable substitutes as well as record low strong levels and trending upward copper discoveries and declining ore grades leading to higher

  28. Slide 28: Thank you!

    Mining for the future 28 THANK YOU! Thank you!