Slide 1: Procurement Strategy
Procurement Strategy Rod Schier DFS Project Manager
Slide 2: Procurement Strategy: Scope, Vendor Pre-qualification, Database
Procurement Strategy n Scope u Commence Procurement activities - second quarter 2004 u Equipment $60 m u Bulk materials $80 m u Number of Packages 180 + n Vendor Pre-qualification Process u Technical u Quality Assurance u Commercial u Industrial Supplies Office Coordination n Vendor Database u Roche
Slide 3: Procurement Strategy: Tender Process and Evaluation Criteria
Procurement Strategy n Tender Process u Procurement Plan « Competitive tendering u Sealed tender protocol n Tender Evaluation Criteria u Technical conformance to specifications u Quality u Commercial « Price « Terms and conditions
Slide 4: Implementation Strategy
Implementation Strategy [ADNIBON OF OOWNER EDI UNSTED
Slide 5: Construction Scope of Work
Construction Scope of Work n On Site u Site Preparation u Temporary Facilities u Power generation u Utilities and Interconnections n Off Site u Accommodation of Construction Personnel u Fabrication of plant structures, plate work and piping u Fabrication of process equipment
Slide 6: Construction Quantities
Construction Quantities ---------------------------------------------------------------- Commodity Quantity ---------------------------------------------------------------- n Site preparation 300,000 m3 n Steel 4,000 t n Pipe 500 t n Concrete 6,000 m3 n Equip (Total) 480 ea n Tanks 20 ea
Slide 7: Construction Strategy Key Project Objectives
Construction Strategy Key Project Objectives n To ensure the health safety and welfare of the construction workforce n To protect the well-being of workforce personnel and assets n Be judged by Hamilton and Horsham communities as welcome guests u Attract highest calibre of construction workforce u H
Slide 8: Construction Execution Strategy
Construction Execution Strategy n On site works u Earthworks and civil contracts tendered local and regional u Fabrication contracts tendered local and regional u Utilise specialist Erection Contractors to execute the work « Direct work packages horizontal and vertical scope « Major contractors iden