Slide 1: CESC Limited Investor Update – Q3 FY11
CESC Limited Investor Update –Q3 FY11 1
Slide 2: Performance Summary – Q3 FY11
Performance Summary –Q3 FY`11 Components Q3 FY`11 Q3 FY`10 % Change Generation (MU) 2147 1873 14.6% Sales (MU) 1941 1813 7.1% Sales (Rs Cr.) 939 797 17.8% EBIDTA (Rs Cr.) 275 214 28.5% Net profit (Rs Cr.) 110 102 7.8% CESC`s Budge Budge power plant has been awarded “Best Environmental Performance Po
Slide 3: Performance Summary – YTD 9M FY11
Performance Summary – YTD 9M FY`11 Components YTD 9M FY`11 YTD 9M FY`10 % Change Generation (MU) 6932 5886 17.7% Sales (MU) 6480 5975 8.4% Sales (Rs Cr.) 3140 2581 21.6% EBIDTA (Rs Cr.) 881 678 29.9% Net profit (Rs Cr.) 375 333 12.6% 3
Slide 4: Operational Highlights – Q3 FY11
Operational Highlights- Q3 FY`11 Plant wise break-up of generation Generation (MU) 1411 2147 1084 1873 420 442 232 264 Q3 FY`11 Q3 FY`10 Budge Budge Southern Titagarh Q3 FY`11 Q3 FY`10 4
Slide 5: Plant load factor (PLF) – Q3 FY11
Plant load factor (PLF) – Q3 FY`11 PLF (%) – (excl NCGS ) Plant wise PLF is given below 92.6% 83.1% PLF % Q3 FY`11 Q3 FY`10 Budge Budge 85.2 97.1 Titagarh 79.3 83.3 Southern 77.8 88.7 Q3 FY`11 Q3 FY`10 NCGS** 38 37.5 **Old Station 5
Slide 6: T&D Loss & Power Purchase
T&D Loss & Power Purchase T&D Loss (Provisional) Power Purchase (MU) 13.9% 366 13.6% 229 9M FY`11 9M FY`10 Q3 FY`11 Q3 FY`10 6
Slide 7: Status of Projects Under Implementation
Status of Projects Under Implementation Haldia Phase 1 (600MW) Financial closure has been achieved ICB has been completed In principal approval received from WBERC Dhariwal Infrastructure Ltd, setting up 2X300 MW coal based power station in Maharashtra The project is under construction s
Slide 8: Status of Projects Under Implementation
Status of Projects Under Implementation Jharkhand power project (600 MW) Joint allocation of coal block (110 MT) obtained in Jharkhand for setting up a 1,000 MW plant The company has obtained a prospecting license for the mine Land acquisition process has been initiated for the main power pl
Slide 9: RPG
RPG l
Slide 10: Spencer's Footprint – January 2010
Spencer’s Footprint – January 2010 Super Hype TA s Dailies Regions States rs SAS TOTAL (‘000) 3k - <3k • TA Hypers – 431 K sft >15 k 15k WB 131 4 1 12 0 17 • TA Supers – 64 K sft East TOTAL 131 4 1 12 0 17 • TA Small stores – 339 K sft Maharashtra 68 1 0 12 3 16 • SAS - 22 K sft West Gujarat 24 1 0
Slide 11: Hyper & Super footprint – January 2011
Hyper & Super footprint – January 2011 Hypers Supers NCR 18 Hypers – 431K sqft Hypers : Ghaziabad, Gurgaon Super : Faridabad 10 Supers – 64K sqft Luckno w Gorakhpur Durgapur Vadodara Aurangabad Kolkata Hypers : South City, Mani Square, Rash Behari Mumbai Warangal Super : Avisar (Malad) Vizag Hyderab
Slide 12: Highlights
Highlights Stores opened in this quarter 2 supers launched in the quarter - Indirapuram Super (Oct’10) and Allahabad Super (Dec’10) Mark Ecko – 1 store launched in Punjab in Oct’10 Improvement in Sales Sales have increased from Rs.854/sqft in Dec 2009 Rs.1048/sqft in Dec 2010 Store EBI
Slide 13: Cautionary Statement
Cautionary Statement Statement in this “ Management Discussion and Analysis” describing the company’s objectives, projections, estimates, expectations or predictions may be “ forward looking statements” within the meaning of applicable securities law and regulations. Actual results could differ mate
Slide 14: Thank You
ORPG J Thank You 14