  1. Slide 1: Mount Thorley Warkworth (MTW) Community Consultative Committee (CCC)

    Mount Thorley Warkworth (MTW) Community Consultative Committee (CCC) Monday 14 May 2018 Time: 2pm – 3:30pm Location: Warkworth Office Boardroom Independent Chairperson: Col Gellatly Minutes: Sarah Purser 14 May 2018

  2. Slide 2: Acknowledgement of Country

    Acknowledgement of Country We acknowledge the traditional owners, the Wonnarua people, of the land where we meet today and pay respect to Elders, past, present and future. 2

  3. Slide 3: Agenda

    Agenda 1. Welcome (Col) • Welcome New E&C manager Gary Mulhearn 2. Apologies (Col) 3. Declaration of pecuniary interests / conflicts of interest (Col) 4. Correspondence (Col) 5. Confirmation of the previous meeting’s minutes (Col) 6. Matters arising from previous meeting (MTW) • Items actioned/addre

  4. Slide 4: 1. Welcome

    Warkworth Mining Limited COAL EMERGENCY EVACUATION PROCEDURES LIED ACTION TO BE TAKEN ON DISCOVERING ACTION TO BE TAKEN TO EVACUATE THE BUILDING. | APIRE OR OTHER EMERGENCY 1, FOLLOW INSTRUCTIONS OF THE WARDENS. | 1. ALERT PERSONS NEARBY OF THE SITUATION. 2, CLOSE YOUR OFFICE DOOR AND TAKE THIS SIGN

  5. Slide 5: 2. Apologies

    2. Apologies ▪ Ian Hedley ▪ Andrew Hodge – Observer ▪ Bill Baxter – Observer/Technical Expert 5 14 May 2018 5

  6. Slide 6: 3. Declaration of pecuniary interests / conflicts of interest

    3. Declaration of pecuniary interests / conflicts of interest All members must declare interests. Source: Community consultative committees Guidelines (State Significant Projects), November 2016. 6 14 May 2018 6

  7. Slide 7: Agenda

    Agenda 1. Welcome (Col) • Welcome New E/C manager Gary Mulhearn 2. Apologies (Col) 3. Declaration of pecuniary interests / conflicts of interest (Col) 4. Correspondence (Col) 5. Confirmation of the previous meeting’s minutes (Col) 6. Matters arising from previous meeting (MTW) • Items actioned/addre

  8. Slide 8: 4. Correspondence

    4. Correspondence ▪ 2017 Disturbance Query and Dust Downtime (email 27/02/2018) ▪ Previous Minutes (email 10/04/2018) ▪ Agenda & Business Papers (26/04/2018) 8 14 May 2018 8

  9. Slide 9: Agenda

    Agenda 1. Welcome (Col) • Welcome New E/C manager Gary Mulhearn 2. Apologies (Col) 3. Declaration of pecuniary interests / conflicts of interest (Col) 4. Correspondence (Col) 5. Confirmation of the previous meeting’s minutes (Col) 6. Matters arising from previous meeting (MTW) • Items actioned/addre

  10. Slide 10: 5. Confirmation of the Minutes

    5. Confirmation of the Minutes ▪ Chairperson to confirm previous meeting’s minutes 10 14 May 2018 10

  11. Slide 11: Agenda

    Agenda 1. Welcome (Col) • Welcome New E/C manager Gary Mulhearn 2. Apologies (Col) 3. Declaration of pecuniary interests / conflicts of interest (Col) 4. Correspondence (Col) 5. Confirmation of the previous meeting’s minutes (Col) 6. Matters arising from previous meeting (MTW) • Items actioned/addre

  12. Slide 12: 6. Matters arising from previous meetings

    6. Matters arising from previous meetings Action No. Actions 1 Yancoal to look into replacing Australian Flag at the Cockfighter Tavern to improve visual amenity. [HF to organise – Update: new flag has been ordered] 2 Clarify the day in which MTW Blast notification system insinuated 3 hour road clos

  13. Slide 13: 6. Matters arising from previous meetings

    6. Matters arising from previous meetings Items Addressed Post Meeting (Actioned Post Meeting) Provide January disturbance maps to Ian. 4 [Followed up: Email from Hayley on 27/02/2018] Provide Ian contact at RMS to address further speed zone enforcements at Putty 5 Road. [Complete: AS followed up wi

  14. Slide 14: 6. Matters arising from previous meetings

    6. Matters arising from previous meetings Actions – Ongoing Action 17 MTW to keep the CCC up to date in matters pertaining to C&A's (May 2017 application to Singleton Council to close Wallaby Scrub Road, either CCC) at a meeting, or out of session should there be any update outside of two weeks prio

  15. Slide 15: Agenda

    Agenda 1. Welcome (Col) • Welcome New E/C manager Gary Mulhearn 2. Apologies (Col) 3. Declaration of pecuniary interests / conflicts of interest (Col) 4. Correspondence (Col) 5. Confirmation of the previous meeting’s minutes (Col) 6. Matters arising from previous meeting (MTW) • Items actioned/addre

  16. Slide 16: 6. Company Update

    6. Company Update 17 14 May 2018 17

  17. Slide 17: Safety Snapshot

    Safety Snapshot ▪ April TRIFR below MTW TRIFR Target (0.00 v 6.62) ▪ April injuries 0 ▪ YTD TRIFR above MTW TRIFR Target (7.00 v 6.62) ▪ There has been 2 x LTI, 3 x RWI and 2 x MTI in 2018 16.00 16.00 14.00 14.00 12.00 12.00 10.00 10.00 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 0.00 0.00 TRIFR LTIFR T

  18. Slide 18: Company Update: Third crossing has been completed

    6. Company Update ▪ Third crossing has been completed! 19 14 May 2018 19

  19. Slide 19: Agenda

    Agenda 1. Welcome (Col) • Welcome New E/C manager Gary Mulhearn 2. Apologies (Col) 3. Declaration of pecuniary interests / conflicts of interest (Col) 4. Correspondence (Col) 5. Confirmation of the previous meeting’s minutes (Col) 6. Matters arising from previous meeting (MTW) • Items actioned/addre

  20. Slide 20: Operational Downtime YTD

    Operational Downtime YTD Truck Shovel RT Dozer Equipment Type Grader Front End Loader Excavator Drill Dragline Dozer 0 100 200 300 400 500 600 Downtime (Hours) YTD Noise YTD Dust MTW Noise Monitoring YTD # CRO # Individual assessment # Nights above trigger Assessments above trigger 2018 YTD 2121 13

  21. Slide 21: MTW Rehabilitation

    MTW Rehabilitation Rehabilitation target for 2018 = 100 ha seeded (outlined in red) Works completed so far in 2018: • 53.1 ha bulk shaped • 15.4 ha topsoiled • 20.5 ha composted • 9.3 ha seeded Key works for Quarter 2 2018 (April-June): Seeing works on Visual Bund (WML West Pit South) Seeding at Nor

  22. Slide 22: Vertebrate Pest Management

    Vertebrate Pest Management Summary of Vertebrate Pest Management 2018: 1080 Baiting Trapping Shooting 2018 YTD Total Lethal Takes by Takes by Wild Dog Feral Pig Hares Fox Baits Laid Wild Dog Fox MTW 120 60 4 1 8 8 - MTW 120 78 3 - 4 6 3 BA 23 14 May 2018 23

  23. Slide 23: Grinding Grooves Relocation

    Grinding Grooves Relocation ▪ The need for removal of grinding grooves site had been known for almost a decade, so the program had long been socialised with the Registered Aboriginal Parties (RAPs). ▪ The methodology for removal was developed with the RAPs & technical consultants over the course of

  24. Slide 24: Hydraulic splitters 1.8m dia. rock saw

    Hydraulic splitters 1.8m dia. rock saw 25 14 May 2018 25

  25. Slide 25: Proposed Final Location for Site M Grinding Grooves

    PROPOSED FINAL LOCATION FOR SITE M GRINDING GROOVES 26 14 May 2018 26

  26. Slide 26: Community Relations update

    Community Relations update Near Neighbour Amenity Resource In 2018 MTW have offered installation of under sink filters for residential properties surrounding our operation • 32 properties have had filter systems installed Community Investment MTW site donations program is now accepting applications

  27. Slide 27: Agenda

    Agenda 1. Welcome (Col) • Welcome New E/C manager Gary Mulhearn 2. Apologies (Col) 3. Declaration of pecuniary interests / conflicts of interest (Col) 4. Correspondence (Col) 5. Confirmation of the previous meeting’s minutes (Col) 6. Matters arising from previous meeting (MTW) • Items actioned/addre

  28. Slide 28: 9.0 Feedback From Community Reps

    9.0 Feedback From Community Reps Any other feedback via Community reps? 29 14 May 2018 29

  29. Slide 29: Agenda

    Agenda 1. Welcome (Col) • Welcome New E/C manager Gary Mulhearn 2. Apologies (Col) 3. Declaration of pecuniary interests / conflicts of interest (Col) 4. Correspondence (Col) 5. Confirmation of the previous meeting’s minutes (Col) 6. Matters arising from previous meeting (MTW) • Items actioned/addre

  30. Slide 30: 10.0 General Business & Future Dates

    10.0 General Business & Future Dates ▪ Cockfighter Tavern update: Broker has been engaged to find suitable tenant. No further update. ▪ Wallaby Scrub Road Update today 31 14 May 2018 31

  31. Slide 31: MTW Offset Management

    MTW Offset Management ▪ Stuart requested information on UNE report for Warkworth Sands Reestablishment. ▪ Development consent DA-300-9-2002-i (superceded by SSD-6464) required a detailed research program for the Warkworth Sands Woodland (WSW) Community (Schedule 4 Cond.3) ▪ UNE was engaged to meet t

  32. Slide 32: Dust update 5-8 May 2018

    Dust update 5-8 May 2018 ▪ Response to Ian Hedley Dust enquiry Wallaby Date North Warkworth Bulga Boundary Conveyor/ MTIE Dagline Loop Heavy Bridge Warkworth Bulga Scrub Road 5/05/2018 0:00 4 4 8 20 8 22.6 9.8 26.2 6/05/2018 0:00 4 4 8 20 8 31.9 8.6 24.1 7/05/2018 0:00 1.4 1.4 2.9 7.2 2.9 17.7 8.6 3

  33. Slide 33: MTW Exploration License Application

    MTW Exploration License Application ▪ Yancoal have submitted an Exploration License Application (ELA) within our existing operations to investigate whether deeper seams are prospective. ▪ The ELA will be advertised in the Singleton Argus, and The Land newspapers (likely in late May 2018). 34 14 May

  34. Slide 34: Exploration tenement map

    TaDOR OVATE ONE TENEMENT BOUNDARY CADASTRAL BOUNDARY MTW LAND PROPOSED CORE HOLE PROPOSED ROTARY HOLE

  35. Slide 35: Other General Business & Future Dates

    Other General Business & Future Dates Other General Business? Next Meeting Date 13 August 2018 – MTW Board Room 36 14 May 2018 36

  36. Slide 36: 11.0 Meeting Close

    11.0 Meeting Close Thank you. Please travel safely. 37 14 May 2018 37

Yancoal Australia — Corporate Update (May 2018) on 6ix