Parth Electricals & Engineering Limited · NSE:PARTH
Parth Electricals & Engineering — H1 FY27 Earnings Presentation
27 slides from Parth Electricals & Engineering's earnings presentation, Nov 2, 2026
Slide 1: Submission letter to NSE under Regulation 30
Date: 02nd November, 2026 To, National Stock Exchange of India Limited, Exchange Plaza, C-1, Block G, Bandra Kurla Complex, Bandra (E) Mumbai – 400051 NSE Symbol: PARTH Subject: Submission of Investor Presentation Under Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements), Regulat
Slide 2: H1 FY27 Earnings Presentation
Parth Electricals & Engineering Ltd. H1 FY27 Earnings Presentation November 2026 A renowned manufacturer and service provider in the electrical power transmission & distribution space, with in-house R&D and design capabilities. OUR PRODUCTS Watch the corporate video Watch corporate video RMU CSS / P
Slide 3: Safe Harbour Statement
DISCLAIMER Safe Harbour Statement This presentation and the accompanying slides (the “Presentation”), which have Certain matters discussed in this Presentation may contain statements regarding been prepared by Parth Electricals & Engineering Limited (the “Company”), have the Company’s market opportu
Slide 4: Contents
AGENDA Contents 01 02 03 Industry Growth Drivers Business Overview & Management Products & Manufacturing Policy push, rising power demand, clean Business overview, order book, Executive Products, Marquee projects, Clients & Facility energy and data centres Leadership and team 04 05 Update on CapEx F
Slide 5: Data Centres: The New Grid-Scale Customer
INDUSTRY GROWTH DRIVERS · DATA CENTRES Data Centres: The New Grid-Scale Customer Each AI campus is a mini-utility: HV intake, MV distribution and full redundancy INDIA DATA -CENTR E CAPACITY B Y 2030 40–45% ₹60–70 Cr 3.4–6.5 GW Share of data-centre capex spent on electrical systems: the largest cost
Slide 6: Renewables, Storage & the Grid Build-Out
INDUSTRY GROWTH DRIVERS · ENERGY TRANSITION Renewables, Storage & the Grid Build-Out Every GW of solar, wind, storage or hydrogen needs switchgear to connect, protect and evacuate it RENEWAB L E S B ATTERY STORAGE TRANSM ISSI O N 300 GW ~11× ₹9.15 lakh Cr Non-fossil capacity (Jul 2026), 54% of total
Slide 7: Business Overview
BUSINESS OVERVIEW Business Overview Manufacturing & Supply Services & EPC • Ring Main Units (11kV–33kV) under technology transfer with Schneider Electric • Installation, testing & commissioning of substations and power cables (specialised SAS, France services from 415V to 220kV) • Compact / Package
Slide 8: Order Book Visibility
ORDER BOOK Order Book Visibility STRONG ORDER BOOK ORDER BOOK MIX ₹470 Cr Manufacturing Order 48.7% 25.7% Service Order EPC Order 25.6% Manufacturing, service and EPC orders on hand ₹228.67 Cr ₹120.79 Cr ₹120.14 Cr Manufacturing & Supply ₹228.67 Cr Services & EPC ₹240.93 Cr • 2000+ RMU orders under
Slide 9: Executive Directors
LEADERSHIP Executive Directors Mr. Jignesh Patel Mrs. Jemini Patel Managing Director Whole Time Director • Graduated from BVM Engineering College, SP University, with a • Science graduate who has worked in Parth Electricals since inception Bachelor of Engineering (B.E.) in electrical engineering tec
Slide 10: Our Core Team
MANAGEMENT Our Core Team Led by Mr. Jignesh Patel, Managing Director, and Mrs. Jemini Patel, Whole Time Director Mr. Darshan Shukla 33 Mr. Sanjay Patel 22 Mr. Pankaj Nayak 23 Mr. Dipesh Kamothi 18 Technical Director yrs exp. Works Manager yrs exp. Head, Projects yrs exp. Head, Services yrs exp. Ms.
Slide 11: Our Manufactured Products
PRODUCT PORTFOLIO Our Manufactured Products RMU MV Panels LT Panels Control & Relay Panels Smart RMU PSS CSS Earth Link Boxes Parth Electricals & Engineering Ltd. | H1 FY27 Earnings Presentation 10
Slide 12: Our New Products: 33kV RMU and Gas Insulated Switchgear
NEW PRODUCT DEVELOPMENT Our New Products: 33kV RMU and Gas Insulated Switchgear 33kV Ring Main Unit (RMU) Gas Insulated Switchgear (GIS) Parth Electricals & Engineering Ltd. | H1 FY27 Earnings Presentation 11
Slide 13: 33kV GIS and RMU: From Development to Market
NEW PRODUCT DEVELOPMENT 33kV GIS and RMU: From Development to Market Infrastructure & Product Portfolio 1 Completed Development 2 Final type testing 50% complete 33kV Gas Insulated Switchgear & Ring After Nov 2026 Main Unit 3 Roll-out from Vadodara plant inauguration Premium, technology-driven produ
Slide 14: Marquee Projects in the USA and India
EXPORTS & PRESTIGIOUS PROJECTS Marquee Projects in the USA and India USA · EXPORT • All payments fully realised Intelligent Motor Control • Additional scope order under Center (iMCC) finalization • Raised profile in the US market; high-value inquiries in pipeline 100% executed USA · NEW ORDER INDIA
Slide 15: Our Valued Clients
CLIENTS Our Valued Clients All client logos are for illustrative purposes only and remain the property of their respective owners. Parth Electricals & Engineering Ltd. | H1 FY27 Earnings Presentation 14
Slide 16: Manjusar, Vadodara: Manufacturing Facility
MANUFACTURING FACILITY · UNIT 1 Manjusar, Vadodara: Manufacturing Facility Parth Electricals & Engineering Ltd. | H1 FY27 Earnings Presentation 15
Slide 17: Skill Development Centre: A Day-One Ready Workforce
HUMAN CAPITAL & SKILL DEVELOPMENT ( CapEx completed) Skill Development Centre: A Day-One Ready Workforce Skill Development Centre fully operational for in-house and customer training; the first batch of 25 trainees will be deployed to the Odisha plant 25 30 +50 Batch 1 · Odisha plant Batch 2 · Vadod
Slide 18: Karachiya, Vadodara: Construction Progress
MANUFACTURING FACILITY · UNIT 2 ( CapEx completed) Karachiya, Vadodara: Construction Progress UNDER CONSTRUCTION IN FY26 COMPLETED FACILITY INSIDE THE NEW SHOP FLOOR Facility completed · Inauguration Nov 2026 Parth Electricals & Engineering Ltd. | H1 FY27 Earnings Presentation 17
Slide 19: Khordha, Odisha: Facility Set Up
MANUFACTURING FACILITY · UNIT 3 (Ongoing CapEx) Khordha, Odisha: Facility Set Up Shopfloor set-up Store set-up Khordha, Odisha Machinery Parth Electricals & Engineering Ltd. | H1 FY27 Earnings Presentation 18
Slide 20: CapEx Update: Phase 1 Deployment Status
CAPEX UPDATE CapEx Update: Phase 1 Deployment Status All figures in ₹ Particulars of CapEx CapEx in H1 FY27 Total CapEx till date Karachiya, Vadodara (Unit-2) 13.13 Cr 21.79 Cr Khordha, Odisha (Unit-3) 6.64 Cr 6.64 Cr Total 19.77 Cr 28.43 Cr Completed - May 2026 Inauguration Nov 2026 Operational Und
Slide 21: H1 FY27 vs H1 FY26: Profit & Loss
PROFIT & LOSS STATEMENT H1 FY27 vs H1 FY26: Profit & Loss ₹ Crore H1 FY27 (U/A) H1 FY26 (U/A) YoY Cost structure (% of total income) Revenue from operations 114.19 80.40 +42.0% H1 FY26 H1 FY27 Other income 2.21 0.71 +211% 71.2% Materials Total income 116.40 81.11 +43.5% 66.8% 8.8% Cost of materials
Slide 22: H1 FY27 vs H1 FY26: Balance Sheet
BALANCE SHEET H1 FY27 vs H1 FY26: Balance Sheet Equity & liabilities Assets Return on equity (ROE) H1 FY27 H1 FY26 H1 FY27 H1 FY26 13.8% ₹ Crore ₹ Crore 12.8% (U/A) (U/A) (U/A) (U/A) 11.2% Share capital 14.83 13.67 Net fixed assets 30.33 21.03 Reserves & surplus 116.91 95.02 Capital WIP 21.55 7.69 N
Slide 23: Higher Profit; Cash Tied up in Growth
CASH FLOW STATEMENT Higher Profit; Cash Tied up in Growth ₹ Crore H1 FY27 (U/A) H1 FY26 (U/A) Working capital cycle (days) Operating profit before WC changes 13.20 9.53 Receivable days Inventory days Payable days Cash conversion cycle Working capital changes −16.67 1.94 Taxes paid −2.97 −2.52 94 107
Slide 24: Key Takeaways and Strategy
KEY TAKEAWAYS & STRATEGY Key Takeaways and Strategy Profitable Growth; Cash Conversion Is the H2 Focus Three Engines Behind the Outlook What went well in H1 • ₹470 Cr order book; ₹300 Cr+ bid pipeline • Total income +43.5% • Vadodara GIS unit from Nov 2026 • Gross margin +444 bps to 33.25%; PAT +49%
Slide 25: Proposed Acquisition of Takalkar Power Engineers & Consultants
STRATEGIC ACQUISITION Proposed Acquisition of Takalkar Power Engineers & Consultants 100% EQUITY ACQUISITION ABOUT TAKALKAR · BUSINESS OVERVIEW Takalkar Power Engineers & Consultants Pvt. Ltd. Vadodara, Gujarat · Operations across India ₹6.00 Cr All-cash deal – Takalkar will become a wholly owned En
Slide 26: Key Milestones over the Next Three Quarters
UPCOMING MILESTONES Key Milestones over the Next Three Quarters Q3 FY27 Q4 FY27 Q1 FY28 Nov 2026 Dec 2026 Feb 2027 Mar 2027 Jun 2027 Vadodara GIS plant Data centre order for UL-certified MV Odisha 60,000 sq ft Odisha facility fully inauguration; 33kV GIS Vertiv, Jamnagar, fully switchgear delivered
Slide 27: Thank you
Parth Electricals & Engineering Ltd. Thank you H1 FY27 Earnings Presentation · November 2026 INVESTOR RELATIONS ADVISORY Karnametic Partners LLP Karan Anchalia +91 70037 44201 [email protected]