  1. Slide 1: Distribution Resources Plan Overview

    Distribution Resources Plan Overview July 1, 2015

  2. Slide 2: SCE Distribution Resources Plan

    SCE Distribution Resources Plan AB 327 required IOU submissions of Distribution Resources Plans (DRP) on July 1, 2015 to integrate increasing penetration of Distributed Energy Resources (DERs). Key provisions of the DRP filing include: • Methodology/Tools for identifying optimal locations for DERs (

  3. Slide 3: SCE Grid Modernization Road Map

    SCE Grid Modernization Road Map SCE’s July 1, 2015 DRP supports the Commission’s proposed phased approach, which would be implemented over future General Rate Case (GRC) cycles 2015 - 2017 2018 - 2020 2021 + Cycle GRC Implement foundational Expand automation and Continue grid modernization, Technolo

  4. Slide 4: SCE DRP Capital Expenditure Estimates

    SCE DRP Capital Expenditure Estimates Time Period Capital Expenditures CPUC Approval Mechanism 2015-2017 Distribution Automation $40-70 million • Proposed memorandum account to record Substation Automation $30-60 million associated revenue Communications Systems $7-15 million requirement until Techn