Bayerische Motoren Werke AG · XETR:BMW

Bayerische Motoren Werke — BMW Group — Investor Presentation (March 2011)

9 slides from Bayerische Motoren Werke's investor presentation, Mar 15, 2011

  1. Slide 1: Financial Analysts' Meeting – SGL Automotive Carbon Fibers (SGL ACF)

    Financial Analysts’ Meeting – March 15, 2011 SGL Automotive Carbon Fibers (SGL ACF) Dr. Joerg Pohlman Managing Director SGL Automotive Carbon Fibers A BMW Group and SGL Group Joint Venture

  2. Slide 2: Carbon fiber materials are essential to meet lightweight requirements of the BMW Megacity Vehicle

    Page 2 SGL Automotive Carbon Fibers The utilization of carbon fiber materials is essential to meet the lightweight requirements of the BMW Megacity Vehicle Main arguments for the utilization of carbon fiber materials: • Low weight: CFRP parts are approx. 50% lighter than comparable steel parts and a

  3. Slide 3: The joint venture was initiated to meet BMW Group's demand for lightweight materials

    Page 3 SGL Automotive Carbon Fibers The joint venture was initiated to meet BMW Group‘s demand for lightweight materials made of carbon fibers Motivation for setting up the joint venture: • Supply guarantee: Securing sufficient long-term production capacity for carbon fibers and fabrics • Technologi

  4. Slide 4: Joint Venture Overview – Global Value Chain

    Page 4 Overview Global Value Chain SGL ACF is responsible for the purchasing of PAN precursor, the production of carbon fibers and fabrics and the recycling process SGL Automotive Carbon Fibers (Steam-) Ammoxi- Polymerisation/Spi Cracking dation nning Oxidation Carbonisation Knitting Crude Oil Propy

  5. Slide 5: Moses Lake Plant – Carbon Fibers

    Page 5 Moses Lake Plant – Carbon Fibers The carbon fiber plant will be the most efficient and sustainable of its kind Main facts: • Groundbreaking July 7, 2010 • Initial production capacity with 2 lines: 3,000 metric tons • Production Building 1 finished in Q1/2011 • Delivery of production material

  6. Slide 6: Wackersdorf Plant – Non-crimp Fabrics and Recycling Material

    Page 6 Wackersdorf Plant – Non-crimp Fabrics and Recycling Material The Wackersdorf plant utilizes advanced textile manufacturing technology Main facts: • Opening ceremony July 19, 2010 • Initial production capacity of fabrics: 3,000 metric tons • Commissioning of recycling machinery in Q1/2011 The

  7. Slide 7: Wackersdorf Plant – Fabrics delivered to CFRP production at BMW Landshut

    Page 7 Wackersdorf Plant – Non-crimp Fabrics and Recycling Material The manufactured fabrics are delivered to the CFRP production at BMW Landshut Material Milling Tempering input RTM-process 1 2 Preforming Assembly Automatic component handling 3 Diagram of hall layout Painting Removal of 1 Insertion

  8. Slide 8: Wackersdorf Plant – Recycling process

    Page 8 Wackersdorf Plant – Non-crimp Fabrics and Recycling Material The purpose of the recycling process is to reintroduce semi-finished recycling products into CFRP production Dry offcuts Fiber preparation Production of Production of non-wovens non-wovens / non-woven sheet complexes - Rovings/non-w

  9. Slide 9: Outlook and Challenges

    Page 9 Outlook and Challenges • Decrease in sales price to BMW driven by significant improvement in production efficiency and economies of scale • Identification of further sales price decrease potentials by employing alternative production technologies for specific automotive applications • Expansi

BMW Group — Investor Presentation (March 2011) on 6ix