Slide 1: Empire North Project Overview
Empire North Project Overview Farmington Public Information Session Nov. 9, 2017

Slide 2: The Company
The Company NFG is the only large, diversified public energy company headquartered in Western New York! 2,080 Full-Time $5.5 Billion Employees Across Investments in N.Y. & All Divisions Pa. since 2008 742,000 1,017 Utility accounts served Union 1.2 million people N.Y. Employees .5 million people Pa.

Slide 3: Company Structure
Company Structure National Fuel Gas Company (NYSE: NFG) Upstream Midstream Downstream Seneca National Fuel National Fuel Resources Gas Supply Gas Corporation Corporation Distribution Corporation National Fuel Empire Resources, Inc. Pipeline, Inc. National Fuel Gas Midstream Corporation 3

Slide 4: History of Empire Pipeline in Finger Lakes Region
History of Empire Pipeline in Finger Lakes Region Empire Pipeline transports natural gas to more than 1 million residential and major industrial companies, utilities and power producers in western and central New York and is an interstate pipeline regulated by the Federal Energy Regulatory Commiss

Slide 5: Empire North Project
Empire North Project This is a Federal Energy Regulatory Commission (FERC) jurisdictional project Increasing capacity of existing modern pipeline system Target In-Service: November 2019 System: Empire Pipeline, Inc. Estimated Cost: $141 million Natural gas delivery for N.Y. and Northeast

Slide 6: Farmington Compressor Station
Farmington Compressor Station Location: Farmington, N.Y. 92.4 acre parcel Compressor Station to take up less than 10 acres and be located over 1,660 ft. off Hook Road Adjacent to Rochester Gas & Electric substation/Utility power lines & ROWs/NYS Thruway Proposed site zoned GI-Industrial Desc

Slide 7: Compressor Station: Minimizing Impacts
Compressor Station: Minimizing Impacts FARMINGTON Commitment to low noise: Minimal to no increase over ambient noise levels at closest residences Low noise electric motor driven compressor packages Acoustically designed compressor buildings with sound suppression Low noise auxiliary equipmen

Slide 8: Compressor Station: Minimizing Impacts
Compressor Station: Minimizing Impacts Commitment to develop landscape plan during site plan process Commitment to no perceived increase in vibration Commitment to minimal, functional facility lighting Commitment to aesthetic architectural building treatment 8

Slide 9: Station can be Designed to Respect Agricultural Heritage
Station can be Designed to Respect Agricultural Heritage For Discussion Purposes Only 9

Slide 10: Safety
Safety Commitment to meet or beat all federal safety codes for design and operation Commitment to community outreach and dialogue INGAA Commitments Commitment to not seek any property tax abatements 10

Slide 11: FERC Review Process
FERC Review Process The Federal Energy Regulatory Commission (FERC) is an independent federal regulatory agency within the U.S. Department of Energy. Under the federal Natural Gas Act, FERC has exclusive jurisdiction over the environmental review, including the siting, of interstate natural gas

Slide 12: FERC Review Process
FERC Review Process Upon completion of a thorough environmental analysis, FERC will issue an environmental assessment, which will be an integral part of FERC’s decision on whether to approve the proposed project. FERC’s environmental assessments typically recommend various mitigation measures, w

Slide 13: Substantial New York State Investment
Substantial New York State Investment Empire North Project Investment $141 million overall expected cost ~$76 million in New York state Expected electric transmission upgrades will enhance reliability for local utility customers The Farmington Compressor Station will provide an estimated tot

Slide 14: Northeast Supplies Benefitting New York State
Northeast Supplies Benefitting New York State Twelve months ending September 2016 14

Slide 15: Extensive Planned Project Outreach
Extensive Planned Project Outreach PROPOSED TIMELINE Empire Informational Sessions November/December 2017 Empire Submits Section 7(c) Application January 2018 Commission Issues Certificate of Public Convenience and January 2019 Necessity Empire Submits the Implementation Plan February 2019 Empire Co

Slide 16: Contact Us
Contact Us Karen L. Merkel Corporate Communications [email protected] (716) 857-7654
Source: Internet Archive copy of nationalfuel.com
More decks from National Fuel Gas Company
FY2026 Earnings Presentation50 slides · Nov 4, 2026
National Fuel Gas Distribution — Corporate Update (October 2026)21 slides · Oct 20, 2026
Merger or Acquisition (October 2026)22 slides · Oct 14, 2026
Q3 2026 Earnings Presentation57 slides · Jul 30, 2026
Q3 FY2026 Earnings Presentation57 slides · Jul 29, 2026
Investor Presentation (May 2026)21 slides · May 21, 2026