Warren Resources — Canaccord Adams Global Growth Conference 2007
37 slides from Warren Resources's conference presentation, Aug 7, 2007
Slide 1: Warren Resources, Inc. Canaccord Adams Global Growth Conference
Warren Resources, Inc. August 8, 2007 CANACORD ADAMS GLOBAL GROWTH CONFERENCE
Slide 2: Disclaimer
Disclaimer Cautionary Note to U.S. Investors: This presentation includes "forward-looking statements" within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. The opinions, forecasts, projections or other stateme
Slide 3: Introduction
Introduction i
Slide 4: Investment Highlights
Investment Highlights Large, high-quality resource base with huge remaining oil-in-place (+/-550 MMBO) and over 1.0 TCF of potential gas reserves Long-lived reserves (+20 yrs) Low-risk development drilling program in giant Wilmington Oil Field in California and large high-quality CBM project in East
Slide 5: Warren Resources Operational Overview
Warren Resources Operational Overview Net proved reserves with a PV-10 value of $609 million (using $50.60 realized price per Bbl and $4.35 per MCF at 12/31/06), accounts for 10% of net acreage Interests in 205 gross (188 net) producing wells and are the operator or joint-operator in over 89% of the
Slide 6: Proved and Unrisked, Unbooked, Potential Reserves
Proved and Unrisked, Unbooked, Potential Reserves Washakie CBM – Net Proved Reserves 22.0 Bcfe Proved Reserves 349 Bcfe Unrisked, Unbooked Potential Reserves 1,165 Bcfe Wilmington – Net Proved Reserves 324.0 Bcfe 1% 3 Washakie Deep Unrisked, Unbooked Potential Net Gas Reserves 150 Bcfe Washakie CBM
Slide 7: Business Strategy
Business Strategy Exploit existing properties through the drillbit Increase proved reserves by drilling 1,800 identified Rocky Mountain CBM wells and 450 Wilmington oil wells Increase oil production by 100% or more in 2007 Increase our working interests in future wells due to prior completion of tur
Slide 8: Experienced Operating Team
Experienced Operating Team Warren has assembled a top-notch technical team of 10 petroleum engineers with considerable experience in our operating regions including: 5 Name Title Years Operating Experience Regional Focus Area of Expertise Lloyd G. Davies Chief Executive – Warren E&P 45 California &
Slide 9: Focused Operations - Wilmington Oil Field
Focused Operations - Wilmington Oil Field
Slide 10: The Wilmington Field
The Wilmington Field The Wilmington Field is the third largest oil field in the United States, having produced 3.5 billion barrels of oil, or 40% of estimated OOIP Prudhoe Bay in Alaska is the largest oil field and the East Texas oil field is the second largest Wilmington Field Wilmington Field 6
Slide 11: WTU (Warren) Structure
WTU (Warren) Structure is 18 ½ mile long, highly faulted, asymmetrical anticline Wilmington Fault Wilmington Field Geometry NWU (Warren) 7
Slide 12: Wilmington Townlot Unit (WTU)
Wilmington Townlot Unit (WTU) 8 Unitized in 1972 by Exxon Warren holds 98.6% WI, 81.8% NRI Produced 145 MMBO through 2006 24% of estimated 600 MMBO original oil in place (OOIP) 40% estimated ultimate recovery (currently 36%) in other parts of the field At 40% recovery in WTU, 95 MMBO (gross) potenti
Slide 13: Warren's Strategy
Warren’s Strategy Redevelop Upper Terminal & Ranger Reservoirs for Waterflood Improve vertical conformance and areal sweep efficiency of waterfloods Drilling new wells in 7-spot patterns to improve areal sweep, support pressure better Sub-zoning injection well completions to force more water into le
Slide 14: Sub-zoned Waterflood (isolated injection)
Sub-zoned Waterflood (isolated injection) 2610 3450 SSTVD S T F G Hx J X Pao Bp R D1A Tar Formation Ranger Formation Upper Terminal Formation Isolated Water Injector Producer Injector Producer Injector Producer Injector Producer 10
Slide 15: D1-A (Tar) Horizontal Drilling Target
D1-A (Tar) Horizontal Drilling Target 10000 -- 0.1 0.0 ---- 0.5 1.0 ---- 0.0 Permeability Porosity Saturation Transition from oil to water Wilmington WTU-1829 Wilmington Tar Zone D1-A Current Hz Target DU Sand (possible Hz Target) D2 Sand D3 Sand Perforate & include in Ranger wells 11
Slide 16: Vertical vs. Horizontal Tar Wells
Vertical vs. Horizontal Tar Wells Cumulative Oil Production (from Simulation) Simulation Results Per Well Peak Rates Increase 300-400% Oil Recovery Improves 400% Drilling Costs Increase 50% over vertical wells Fewer wells required Cumulative Oil Production Increased Recovery Cumulative Days on Produ
Slide 17: PeriScope Geosteering of Hz Wells at WTU
PeriScope Geosteering of Hz Wells at WTU Planned Well Path Actual Well Path Forecasted Formation Top 13 PeriScope Directional Resistivity GR & ROP Gamma Counts( 0.00 to 80.00 GR II)00 RT IIe 0 00 to 150 00 ROP 5 Measure 0.00 to 500.00 GR. Squared 0.00 to 150.00 A34H_UNC_RT. Measured 0.10 to 100.00 F
Slide 18: Wilmington Townlot Unit
Wilmington Townlot Unit Two drilling cellars currently under construction - south ½ finished Two rows of wells in each cellar (140 wells/cellar) Zoning permit to drill up to 540 wells from cellars at WTU Production equipment below ground level Drilling Rig skid-mounted over cellar allows rapid rig m
Slide 19: WTU Central Facility & Drillsite - Plan View
WTU Central Facility & Drillsite – Plan View Cellar 1 Cellar 2 Cellar 3 15
Slide 20: Cellar #2 April 2007
Cellar #2 April 2007 Looking South Permanent Flowlines Conduits Well Heads Fence Electricity Well Testers Sumps installed 16
Slide 21: Wilmington Townlot Unit
Wilmington Townlot Unit Since taking over as WTU operator in 2005, Warren has: Increased oil production from 375 BOPD to over 2,700 BOPD Obtained zoning permit to drill up to 540 wells from Central Site Proceeded with construction of 2 multi-well cellars Drilled and completed 78 total wells Improved
Slide 22: WTU Oil Production Since 01/2004
18 WTU Oil Production Since 01/2004 0 1,000 2,000 3,000 05/2007 05/2006 05/2005 05/2004 BOPD Warren takes over operatorship of WTU Nabors 411 starts work Ensign 518 starts work Historic Production Decline
Slide 23: WTU Key Projects Underway
WTU Key Projects Underway WTU 10-inch oil sales pipeline (20 MBO/D capacity) to refinery by October to eliminate trucking Installation of Co-Gen, Micro-turbines to convert waste gas to net income Installation of Automated Well Testers to improve accuracy and reduce costs Make-up water source well be
Slide 24: North Wilmington Unit
North Wilmington Unit Unitized for Water Flood in 1977 by Sun Oil Produced 37 MMBO, or only 24% of the original 150 MMBO. Net proved reserves of 20 MMB in Ranger zone at 12/31/2006. Warren acquired NWU 12/31/05 for $23 MM Warren holds 100% W.I. and 84.6% N.R.I. Warren has focused on operational impr
Slide 25: NWU Oil Production Since 01/2004
21 NWU Oil Production Since 01/2004 0 100 200 300 400 500 600 05/2007 05/2006 05/2005 05/2004 BOPD Historic Production Decline Warren buys NWU Heater Treater Up-graded
Slide 26: California Operations Summary
California Operations Summary Quality Assets with huge remaining oil-in-place (+/-550 MMB) Newly proven technologies and high oil prices enable substantial remaining reserves to be captured economically WTU drilling and construction projects are well underway (execution risk minimal) Production volu
Slide 27: Focused Operations - Washakie Basin CBM
Focused Operations – Washakie Basin CBM Comprises the southeast one-third of the Greater Green River Basin in southwestern Wyoming Largest acreage position with 227,333 gross (125,779 net) acres Over 1,800 potential CBM drillsites on mostly 80-acre spacing with EUR over 1.0 Bcfe/well Own 42% average
Slide 28: Washakie Basin - Atlantic Rim CBM
Washakie Basin – Atlantic Rim CBM Located on the eastern rim of the Washakie Basin comprising 206,448 gross (109,152 net) acres Development of 141,000 gross acres in preferential CBM drilling fairway through a 50/50 joint venture with Anadarko Managed jointly through operating subcommittee with equa
Slide 29: Washakie Basin - Atlantic Rim - CBNG Units
Washakie Basin – Atlantic Rim – CBNG Units Sun Dog Pilot with 5-year production history De-watering phase with inclining production First 10 pilot wells averaging over 450 Mcf/d per well Two new wells averaging 200 Mcf/d (rather than zero gas production) due to benefits from pilot wells previous de-
Slide 30: Washakie Basin - Pacific Rim CBM
Washakie Basin – Pacific Rim CBM Located 60 miles due west of the Atlantic Rim Project comprising approximately 20,885 gross (16,626 net) acres High gas content and low permeability Five conventional wells producing 1,000 Mcf/d Received BLM approval of EA for 120 gas wells Operate Chicken Springs fe
Slide 31: Rocky Mountain Pipelines
Rocky Mountain Pipelines 27 There are fewer options for exporting Rockies gas than Gulf Coast gas. Sumas WASHINGTON MONTANA N. DAKOTA S DAKOTA OREGON IDAHO WYOMING NEBRASKA NEVADA UTAH COLORADO KANSAS OKLAHOMA NEW MEXICO CALIFORNIA ARIZONA TEXAS Buffalo Opal Rangely Denver Cheyenne Ignacio Blanco Hu
Slide 32: Financial Overview
Financial Overview 28
Slide 33: Capitalization ($Millions)
Capitalization ($Millions) 29 $ 280.0 $ 294.5 $ 382.8 Total capitalization Total stockholders' equity Common stock and additional paid in capital Preferred stock Stockholders' equity: $ 8.9 $ 9.5 $ 40.1 Debentures and other long-term liabilities Current portion of long-term debt $ 114.6 $ 43.0 $ 26.
Slide 34: Historical Financial Performance
Historical Financial Performance Year Ended December 31 30 2007 2006 Net Production Natural Gas (MMcf) 462.5 566.7 Oil (MBbls) 372.5 197.9 Equivalents (MMcfe) 2,700.4 1,753.8 Revenues: Oil and Gas Sales 22.8 $ 14.4 $ Interest and other income 1.4 2.5 Total Revenues 24.2 16.9 Costs and Operating Expe
Slide 35: Defined Growth
Defined Growth Planned 2007 Gross Wells of 142 2007 Drilling Budget of $90 Million (Includes $18 million for drilling cellars and facilities upgrades in Wilmington 31 NWU 17% Atlantic Rim and Other 41% WTU 36% Pacific Rim 6% NWU 18% WTU 24% Pacific Rim 1% Atlantic Rim and Other 57% As of March 31, 2
Slide 36: Investment Highlights
Investment Highlights Large, high-quality resource base with huge remaining oil-in-place (+/-550 MMBO) and over 1.0 TCF of potential gas reserves Long-lived reserves (+20 yrs) Low-risk development drilling program in giant Wilmington Oil Field in California and large high-quality CBM project in East
Slide 37: Warren Resources, Inc.
Warren RESOURCES, Inc.
Warren Resources — Canaccord Adams Global Growth Conference 2007 on 6ix