Malaysia Marine & Heavy Engineering Holdings Bhd. · MYX:MHB

Malaysia Marine & Heavy Engineering Holdings Bhd — Q1 2018 Earnings Presentation

24 slides from Malaysia Marine & Heavy Engineering Holdings Bhd's earnings presentation, May 4, 2018

  1. Slide 1: Quarterly IR Updates: 1st Quarter 2018 Financial Results & Updates

    Slide 1: Quarterly IR Updates: 1st Quarter 2018 Financial Results & Updates

    QUARTERLY IR UPDATES 1st Quarter 2018 Financial Results & Updates 4th May 2018

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    Disclaimer This Presentation is not intended to form the basis of any investment decision with respect to Malaysia Marine and Heavy Engineering Holdings Berhad (MHB). Neither this presentation nor anything contained herein shall form the basis of, or be relied upon in connection with, any contract o

  3. Slide 3: Contents

    Slide 3: Contents

    Contents • Business Highlights • Projects • Financials • Shareholding Information • Key Focus Areas 3

  4. Slide 4: 1Q 2018 At A Glance

    Slide 4: 1Q 2018 At A Glance

    1Q 2018 At A Glance FINANCIALS • Revenue of RM188.3 mil • Pre-tax loss of RM25.3 mil Heavy Engineering Unit (HEU) milestones: Offshore • Sail-away of five units of Dangote CALM Buoy Onshore • Completion of centralised piping fabrication (CPF) for RAPID Package 5 Marine Business Unit (MBU) milestones

  5. Slide 5: Contents

    Slide 5: Contents

    Contents • Business Highlights • Projects • Financials • Shareholding Information • Key Focus Areas 5

  6. Slide 6: Dangote (CALM) Buoy

    Slide 6: Dangote (CALM) Buoy

    Sailed away on 6th March 2018 Dangote (CALM) Buoy 6

  7. Slide 7: RAPID Package 5 - Centralised Piping Fabrication (CPF)

    Slide 7: RAPID Package 5 - Centralised Piping Fabrication (CPF)

    Completed on 5th January 2018 RAPID Package 5 - Centralised Piping Fabrication (CPF) 7

  8. Slide 8: Bokor Phase 3 Re-Development CPP

    Slide 8: Bokor Phase 3 Re-Development CPP

    Progress at 10.15% Bokor Phase 3 Re-Development CPP 8

  9. Slide 9: Sepat-A WHP Topside & Substructure

    Slide 9: Sepat-A WHP Topside & Substructure

    Progress at 43.48% Sepat-A WHP Topside & Substructure 9

  10. Slide 10: RAPID Package 5 – Refinery of Gas (ROG)

    Slide 10: RAPID Package 5 – Refinery of Gas (ROG)

    Progress at 66.59% RAPID Package 5 – Refinery of Gas (ROG) 10

  11. Slide 11: RAPID Package 3 Area 2

    Slide 11: RAPID Package 3 Area 2

    Progress at 88.49% RAPID Package 3 Area 2 11

  12. Slide 12: RAPID Package 14

    Slide 12: RAPID Package 14

    Progress at 61.95% RAPID Package 14 12

  13. Slide 13: FSO 'Benchamas 2'

    Slide 13: FSO 'Benchamas 2'

    Refurbishment and conversion completed in March 2018 Sail-away in 2Q 2018 FSO ‘Benchamas 2’ 13

  14. Slide 14: FSO 'Nautica Bergading'

    Slide 14: FSO 'Nautica Bergading'

    Refurbishment and conversion (99.93% Progress) FSO ‘Nautica Bergading’ 14

  15. Slide 15: Contents

    Slide 15: Contents

    Contents • Business Highlights • Projects • Financials • Shareholding Information • Key Focus Areas 15

  16. Slide 16: Income Statement, Sequential Quarter

    Slide 16: Income Statement, Sequential Quarter

    Financial Updates Income Statement, Sequential Quarter • Revenue Income Statement (RM 'm) 1Q 2018 4Q 2017 • HEU – Lower revenue recognised from ongoing projects. Revenue 188.3 247.9 • MBU – Lesser repair works performed as some ship Heavy Engineering 111.3 162.3 owners have deferred their dry dockin

  17. Slide 17: Income Statement, Year-on-Year

    Slide 17: Income Statement, Year-on-Year

    Financial Updates Income Statement, Year-on-Year • Revenue Income Statement (RM 'm) 1Q 2018 1Q 2017 Revenue 188.3 235.8 • HEU – Lower revenue recognised from completed or sail Heavy Engineering 111.3 153.5 away projects while ongoing projects are either nearing Marine 77.0 82.4 completion or still a

  18. Slide 18: Balance Sheet

    Slide 18: Balance Sheet

    Financial Updates Balance Sheet Balance Sheet (RM 'm) Mar 2018 Dec 2017 • Total assets of RM3.2bil Non-Current Assets 1,849.9 1,839.4 • Higher Non-Current Assets – PPE • Lower Receivables & Payables – Major ongoing Inventories 4.0 2.4 project is still at early stages Receivables 783.2 819.3 • Lower

  19. Slide 19: Backlog & Order Intake

    Slide 19: Backlog & Order Intake

    Financial Updates Backlog & Order Intake Backlog RM million Backlog 2,556 1,575 1,273 1,023 1,216 629 CPP Bokor Dec13 Dec14 Dec15 Dec16 Dec17 Mar18 Backlog March 2018 Order Intake RM million RM1,216 mil Benchamas Sepat Phase 2A Besar A 130 2,559 Rapid (3 Packages) 105 Dangote CALM Buoy 420 Others 1,

  20. Slide 20: Contents

    Slide 20: Contents

    Contents • Business Highlights • Projects • Financials • Shareholding Information • Key Focus Areas 20

  21. Slide 21: Shareholding Information

    Slide 21: Shareholding Information

    Corporate Updates Shareholding Information Share Price RM Technip 8.50% Technip 8.50% 2.00 Lembaga Lembaga Tabung Haji Tabung Haji 6.69% 6.69% 1.50 PNB & PNB PNB & PNB Unit Trust As of Unit Trust As of Funds 2.07% 31 Dec 2017 Funds 1.86% 30 Mar 2018 0.95 EPF 1.53% EPF 1.40% 08/01/2018 0.71 0.75 1.00

  22. Slide 22: Contents

    Slide 22: Contents

    Contents • Business Highlights • Projects • Financials • Shareholding Information • Key Focus Areas 22

  23. Slide 23: Key Focus Areas

    Slide 23: Key Focus Areas

    Key Focus Areas • Tenders worth ~ RM2.8 billion have been submitted as of February 2018 • Other prospective works which we are exploring are worth ~ RM2.8 billion • Strategy & Initiatives • Continue pursuing existing business of Marine & Heavy Engineering, seizing available floaters conversion oppor

  24. Slide 24: Thank You

    Slide 24: Thank You

    Thank You MALAYSIA MARINE AND HEAVY ENGINEERING HOLDINGS BERHAD (178821-X) Level 31, Menara Dayabumi, Jalan Sultan Hishamuddin, 50050 Kuala Lumpur, Malaysia T : +603 2273 0266 F : +603 2273 8916 W =: www.mhb.com.my MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD (14558-P) MMHE West, PLO 3, Jalan Pekel

Source: Internet Archive copy of mhb.com.my