Tata Power Company Limited · NSE:TATAPOWER

Tata Power — The Tata Power Company — Investor Presentation (June 2010)

64 slides from Tata Power's investor presentation, June 2010

  1. Slide 1: The Tata Power Company Ltd Presentation June 2010

    Presentation Title The Tata Power Company Ltd PresentationJune 2010 Subtitle 1

  2. Slide 2: Disclaimer

    Disclaimer Certain statements made in this presentation may not be based on historical information or facts and may be “forward looking statements”, including those relating to The Tata Power Company Limited’s general business plans and strategy, its future outlook and growth prospects, and future d

  3. Slide 3: Agenda

    Agenda Part A: Overview of Tata Power Part B: Tata Power Generation Part C: Projects Part D: Other Power Businesses Part E: Other Businesses Part F: Financial Performance Part G: Sustainability 3

  4. Slide 4: Part A: Overview of Tata Power

    Part A: Overview of Tata Power

  5. Slide 5: A Tata Company

    A Tata Company Business Sectors Revenue Largest Companies FY 2009 15% Rs 325,334 cr $ 71 bn 24% 45% 3% 6% 3% 4% Profits FY 2009 Rs 8,163cr 25% $ 1.8 bn -30% 59% 10% 16% 12% 8% 5

  6. Slide 6: Tata Power Group – Major Investments

    Tata Power Group – Major Investments Tata Power Subsidiaries Joint Ventures Investments & Associates Coastal Gujarat Power TECHNOLOGY 100% 30% KPC Ltd. (Mundra UMPP) Trust Energy Resources 5% Exergen 100% 30% Arutmin Pte. Ltd 10% Geodynamics Maithon Power Ltd. 30% Indocoal 74% 40% Tubed Coal 74% Ind

  7. Slide 7: Businesses

    • Trombay 11,12,14 • Hydro 11,13 Businesses • Jojobera 16 • Belgaum 15 • Haldia 14 • Wind Farm 18 Generation • Mundra 21-25 Division • Maithon 26-28 Other Entities • IEL 17,29,30 • Dagachhu 31 Transmission • Mumbai 41 • Powerlinks 42 Power Business • Mumbai 38,39 Distribution • Delhi: NDPL 40 Tata P

  8. Slide 8: Part B: Tata Power Generation

    Part B: Tata Power Generation

  9. Slide 9: Generation: Business Models

    Generation: Business Models Returns Upside Value Drivers Our Projects Regulated Normative RoE Savings on Norms. Operational Mumbai License Area, PLF incentive Efficiency Maithon, Wind Captive Power PPA driven Merchant sales + Trading Jamshedpur (PH6), Plant Saving on agreed Capabilities + Jojobera t

  10. Slide 10: Existing Presence

    Existing Presence Mumbai 2027 MW Other Projects: 1. Indonesian Coal Mines: 30% stake Mumbai License Area 2. Australia: Geodynamics, 10% stake Generation 3. Australia: Exergen, 5% stake Thermal 1480 MW Powerlinks NDPL Hydro 447 MW Distribution Transmission Gujarat 50 MW Jojobera 428 MW Jamshedpur (IE

  11. Slide 11: Mumbai License Area (LA) - Generation

    Mumbai License Area (LA) - Generation Thermal Hydro Trombay - Thermal Unit Capacity Fuel Location Capacity Unit 4* 150 MW Oil & Gas Khopoli 72 MW Unit 5 500 MW Oil, Coal & Gas Bhivpuri 75 MW Unit 6 500 MW Oil & Gas Bhira 300 MW Unit 7 180 MW Gas Total 447 MW Unit 8 150 MW Coal Total 1480 MW * Unit 4

  12. Slide 12: LA Generation Performance - Thermal

    LA Generation Performance - Thermal Generation (MU) Availability (%) 10000 100 80 9500 60 9000 40 20 8500 0 FY07 FY08 FY09 FY10 FY07 FY08 FY09 FY10 PLF (%) Aux. Consumption (%) 100 4.5 80 60 40 20 0 3.5 FY07 FY08 FY09 FY10 FY07 FY08 FY09 FY10 “Best Operation and Maintenance Project in Asia” – Asian

  13. Slide 13: LA Generation - Hydro

    LA Generation - Hydro Generation (MU)* Availability (%) 2500 100 2000 80 1500 60 1000 40 500 20 0 0 FY07 FY08 FY09 FY10 FY07 FY08 FY09 FY10 *Decrease due to adherence to KWTA limits PLF (%) Aux. Consumption (%) 1 60 40 0.5 20 0 0 FY07 FY08 FY09 FY10 FY07 FY08 FY09 FY10 Bhira PSU - CEA Silver Shield

  14. Slide 14: Merchant Capacity

    Merchant Capacity Haldia Trombay - Unit 8 Project Capacity 100 MW 100 MW Customers PPA with Tata Power Trading PPA with Tata Power Trading Hot flue gases from Hoogly Fuel Imported Coal Metcoke Note: Remaining 20 MW in Haldia under PPA to WBSEDCL Haldia Trombay Unit 8 14

  15. Slide 15: Belgaum

    Belgaum Capacity • 81 MW Generation (MU) Fuel Type • Heavy Fuel Oil 500 400 Customer • KPTCL 300 • 12 year PPA till 2012 200 100 Business • Bid Driven – Case 2 0 Model • Fuel charge is pass through FY07 FY08 FY09 FY10 • Other charges recovered as fixed PLF (%) 27 33 63 55 cost 15

  16. Slide 16: Jojobera

    Jojobera Capacity • 428 MW Generation (MU) • Unit 1: 67.5 MW, Unit 2-4: 120 MW each 3000 Fuel Type • Domestic Coal 2500 Customer • Tata Steel • 20 year PPA till 2017 2000 Business • Captive FY07 FY08 FY09 FY10 Model • Fuel and Interest are a pass through • Other expenses on normative basis PLF (%) 7

  17. Slide 17: PH-6 (IEL)

    PH-6 (IEL) Capacity • 120 MW Ownership • IEL (74:26 JV of Tata Power and Tata Steel) Structure Fuel Type • Coke Oven Gases of Tata Steel Customer • Tata Steel Business Model • Captive • Fuel and Interest are a pass through • Other expenses on normative basis 17

  18. Slide 18: Wind

    Wind Capacity • 200 MW Generation (MU) Customer • Maharashtra: TPC-D 100 MW • Karnataka: BESCOM 50 MW 400 • Gujarat: GUVNL 30 MW 3rd Party 20 MW 200 • Mainly Regulated 0 Business Model FY07 FY08 FY09 FY10 • Tariff based on State regulations PLF (%) 19 20 19 19 Tariff Annual (Rs / kwh) Escalation Mah

  19. Slide 19: Part C: Projects

    TATA ry | Part C: Projects

  20. Slide 20: Generation Projects Under Implementation

    Generation Projects Under Implementation Captive Coal Blocks: 1. Jharkhand: Tubed Block,40% stake 2. Orissa: Mandakini Block, 33% stake Tubed Maithon1050 MW Mundra 4000 MW Jojobera 120 MW Mandakini Maharashtra 94 MW Thermal 5170 MW Wind 94 MW Other Projects: 1. Bhutan: Dagachhu Hydro Project, 26% st

  21. Slide 21: Mundra UMPP

    Capacity • 4000 MW (5 x 800 MW) Ownership Structure • 100% subsidiary; Coastal Gujarat Power Limited Business Model • Case 2 – Bid Driven Fuel Requirement • Imported Coal, 11-12 mtpa Fuel Source • Offtake agreement with KPC and Arutmin for 10.11 ± 20% • Looking for additional mines in Australia, Moz

  22. Slide 22: Mundra UMPP

    Current Status • Overall 53% work completed; 10,500 people on site Construction  Unit 1 Boiler Hydro testing successfully completed on April 3, 2010 Activities  TG and Auxiliaries for Unit 1 received on site and TG Stator placed on deck  Structural erection work for Unit 2 is in very advanced sta

  23. Slide 23: Mundra – Site Photographs

    Mundra – Site Photographs West Side View 23

  24. Slide 24: Mundra – Site Photographs

    Mundra – Site Photographs Intake Channel - Charged 24

  25. Slide 25: Mundra – Site Photographs

    Mundra – Site Photographs Boilers – All 5 Units 25

  26. Slide 26: Maithon

    Capacity • 1050 MW (2 x 525MW) Ownership Structure • 74: 26 JV of Tata Power and Damodar Valley Corporation Business Model • CERC Regulated Fuel Requirement • Domestic Coal Fuel Source • 100% linkage sanctioned. Active discussions on to sign Fuel Supply Agreements with coal mines Customers • DVC (30

  27. Slide 27: Maithon

    Current Status  Over 82% of work completed Construction  Unit 1: Boiler Hydro test completed on March 23rd, 2010 Activity  Unit 1: Turbine erection to start shortly  FSA with BCCL signed for 1.6 MTPA; other FSAs expected soon  We expect to sign FSAs with CCL (~2 MTPA) and Tata Steel (~1 MTPA) 

  28. Slide 28: Maithon – Site Photographs

    Maithon – Site Photographs EOT Crane #1 commissioned at Power House #1 Power House #1 structural erection in progress 28

  29. Slide 29: IEL – Unit 5, Jojobera

    IEL – Unit 5, Jojobera Project Capacity • 120 MW Ownership Structure • IEL Business Model • CPP Funding • Project Cost: Rs 620 Crores • D/E 70:30 Construction • Synchronized on April 13, 2010 Activity • CoD expected in Q1 FY11 Project Description • Fuel: Coal Linkage from West Bokaro and Mahanadi Co

  30. Slide 30: Jojobera (Unit 5)

    Jojobera (Unit 5) CW Pump Motors Erected Mill and Bunker Erection in Progress 30

  31. Slide 31: Hydro Projects

    Hydro Projects  Exclusive partnership agreement with SN Power, Norway to develop joint hydropower projects in India and Nepal JV with SN Power  Aim to have 2000 MW under construction or in operation by 2015  Establish jointly owned Services Company to provide technical and managerial expertise 

  32. Slide 32: The National Solar Mission

    The National Solar Mission TARGET Grid-parity for solar power by 2022, and coal-based parity by 2030 ROADMAP Installed Capacity Phase I Phase II Phase III (in MW) 2009 - 2013 2013 - 2017 2017 - 2022 Grid-connected 1000 - 2000 4000 – 10,000 20,000 Off-grid 200 1000 2000 POLICY INCENTIVES - HIGHLIGHTS

  33. Slide 33: Solar Generation: Key CERC Guidelines

    Solar Generation: Key CERC Guidelines Eligibility: Technologies approved by the MNRE Tariff period: 25 years for Solar PV and Solar Thermal Projects (also its ‘useful life’) Capital Cost: Rs 17 Cr/MW for Solar PV and Rs 13 Cr/MW for Solar Thermal projects Actual capital cost can be used for the dete

  34. Slide 34: Captive Coal Blocks

    Captive Coal Blocks Mandakini Coal Block • 7.5 MTPA (jointly allotted with Jindal Photo Film and Monnet Ispat & Energy - each JV Partner having a share of 2.5 MTPA) at Dist. Angul, Orissa • Mining plan approved by MoC  Land acquisition for the coal block is expected by March 2012 and 6(i) notificat

  35. Slide 35: Projects in Pipeline

    Projects in Pipeline Generation Project Fuel Source Capacity (MW) Corus (Tata Steel) Production Gases (Corus) 525 Coastal Maharashtra (Dehrand) Imported Coal 1600 + 800 Naraj Marthapur IPP Captive Coal - Mandakini 1200 Captive Coal – Tubed + Tiruldih IPP / CPP 1200 Coal from Tata Steel Tama Koshi, N

  36. Slide 36: Generation Capacity (Tata Power Group)

    Generation Capacity (Tata Power Group) Excludes Projects Under Planning 10000 8242 Opening Capacity 2400 8000 Total Capacity at Year End 5842 1600 Capacity 6000 4242 1264 2978 4000 2786 192 421 2000 2365 Unit 8 250 PH6 120 Wind 81 Wind 42 New Units Commissioned Haldia 90 Haldia 30 0 2008 2009 2010 2

  37. Slide 37: Part D: Other Power Businesses

    Part D: Other Power Businesses

  38. Slide 38: Distribution Customer Profile – Mumbai LA

    Distribution Customer Profile – Mumbai LA Sales (MUs) Bill payment Kiosk Residential Commercial 4% 21% Essential 40% Industrial 35%  Over 50,000 customers since MERC Order allowing us to distribute power to retail customers  ~500 customers being added every day Regulated Equity: Rs 187 Cr (FY 10)

  39. Slide 39: Our Growth Expectations in Mumbai

    Our Growth Expectations in Mumbai Customer Base (Lakhs) Energy (BU) and Peak Demand (MW) Regular Changeover 4.2 ~800MW 3.4 ~4.0 ~570MW 2.5 ~2.5 0.8 FY10 FY11 FY12 FY13 FY10 FY11 FY12 FY13 39

  40. Slide 40: North Delhi Power Limited (NDPL)

    North Delhi Power Limited (NDPL) PAT Rs. crore Customer Base • >1 million customers with 400.00 5000 MUs of consumption 300.00 200.00 Business Model • Regulated 100.00 Revenue (FY10) • Rs 3277 Cr - FY07 FY08** FY09 FY10 Regulated • Rs 720 Cr Equity Incentives* 72 53 79 58 * Reset of Target AT&C loss

  41. Slide 41: Mumbai LA - Transmission

    Mumbai LA - Transmission • Around 1100 ckm network comprising of 973 ckm of 220 kV / 110 kV overhead lines and 124 ckm of 220 kV / 110 kV underground cables. • Two Extra High Voltage (EHV) lines capacity augmented (170 MVA to 350 MVA) by replacement of the conductor with new technology “High Ampacit

  42. Slide 42: Powerlinks Transmission Limited

    Powerlinks Transmission Limited Capacity • 1200 km 400 kV double-circuit PAT Rs. crore transmission lines 120 Business Model • Regulated 100 80 Revenue (FY10) • Rs 301 Cr 60 40 Regulated Equity • Rs 464 Cr 20 0 ROE % • 15.5% FY08 FY09 FY10 Incentive • As a percent of equity on availability Structure

  43. Slide 43: Indonesian Coal Mines – Structure of Investment

    Indonesian Coal Mines – Structure of Investment Tata Power Company Ltd. (India) Bhivpuri Bhira Investments Ltd. Investments Ltd. (Cyprus) (Mauritius) Indocoal KPC Arutmin (Cayman Islands) (Indonesia) (Indonesia) Bumi Resources (Indonesia) 43

  44. Slide 44: Indonesian Coal Mines

    Indonesian Coal Mines Organizational Structure Offtake Agreement • 40% representation on the Board of • 10.1+ 20% MT on a take or pay basis Commissioners and the Board of Directors • Indocoal Resources (Cayman) agrees to with affirmative rights trade outside of India any coal that Tata • CFOs at KPC

  45. Slide 45: Indonesian Coal Mines

    Indonesian Coal Mines Operating Performance CY ‘09 CY ‘08 • Quantity mined (MT) ~63 ~53 • Average Selling Price (FOB USD/ton) ~62 ~73 • EBITDA from Operations (USD mn) 815 1131 Source – Bumi Resources Debt Repayment Schedule (as of Mar ‘10) Loan Loan Amount Interest Maturity Repayment Details Amount

  46. Slide 46: Shipping Subsidiaries

    Shipping Subsidiaries • Trust Energy Resources Pte Ltd incorporated in Singapore for owning ships to meet shipping requirements and trading in fuels, Energy Eastern Pte Ltd incorporated for chartering of ships • Present shipping requirements of 8 vessels for Mundra • To be met through a combination

  47. Slide 47: Tata Power Trading Company Limited

    Tata Power Trading Company Limited TPTCL Sales (MU) 5000 4000 3000 TPTCL is currently 2000 the third largest 1000 0 trading company FY06 FY07 FY08 FY09 FY10 with 9.26% market share FY10 Revenue – Rs 2357.7 Cr PAT – Rs 8.2 Cr 47

  48. Slide 48: Part E: Other Businesses

    Id TATA Part E: Other Businesses Lighting up Lives! ye *

  49. Slide 49: Strategic Electronics Division (SED)

    Strategic Electronics Division (SED) • Revenues of Rs.123 Cr (Mar 10) against Rs.101 Cr during the previous year. • First batch of Pinaka Launchers was successfully subjected to Factory Acceptance Tests (FAT) by the Ministry of Defence • SED completed the delivery of Air Defence Systems based on Com

  50. Slide 50: Tata BP Solar

    Tata BP Solar • 51:49 JV between BP Solar and Tata Power • Market leader in Solar Photovoltaic technology in India with a turnover of Rs 976 crores in FY10 • The turnover of the Co. in India and SAARC region is about Rs. 278 crores. With exports to BP Solar accounting for about Rs. 698 Crores • Near

  51. Slide 51: Part F: Financial Performance

    Part F: Financial Performance

  52. Slide 52: Standalone – Year Ended March 2010

    Standalone – Year Ended March 2010 Rupee in Billions FY10 FY09 Operating Income 70.98 72.36 Operating Expenditure (52.36) (61.17) Operating Profit 18.62 11.19 Interest & Finance Charges (4.07) (3.06) Depreciation (4.78) (3.29) Other Income 2.29 4.88 Profit Before Tax 12.59 11.16 Provision for Taxes

  53. Slide 53: Consolidated – Year Ended March 2010

    Consolidated – Year Ended March 2010 Rupee in Billions FY10 FY09 Operating Income 189.86 180.61 Operating Expenditure (151.51) (145.16) Operating Profit 38.35 35.35 Interest & Finance Charges (7.64) (7.09) Depreciation / Impairment (8.93) (9.37) Other Income 1.33 3.99 Profit Before Tax 27.67 24.64 P

  54. Slide 54: Funding Requirement

    Funding Requirement Own Funds Debt (Rs.5,500 Crores) (Rs.18,100 Crores) • Internal accruals: Rs.2800 Crores • Domestic loans through domestic • GDR proceeds: Rs. 1600 Crores financial institutions, banks and • FCCB proceeds: $ 300 mn capital markets (equivalent to Rs. 1400 Crores) • Foreign loans th

  55. Slide 55: Tata Power – Financials (Standalone)

    Tata Power – Financials (Standalone) Annual Sales (MU) Profit After Tax (In Billion Rs.) 8.70 9.22 9.39 14,422 14,959 14,703 15,574 6.11 6.97 13,616 2006 2007 2008 2009 2010 2006 2007 2008 2009 2010 EPS (in Rs.) Net Worth (In Billion Rs.) 91.32 44 41 39 71.26 34 64.26 29 40.10 44.67 2006 2007 2008 2

  56. Slide 56: Tata Power – Financials (Consolidated)

    Tata Power – Financials (Consolidated) Profit After Tax (In Billion Rs.) 19.67 10.55 12.19 7.47 7.59 2006 2007 2008 2009 2010 EPS (in Rs.) Net Worth (In Billion Rs.) 85.01 100.84 57.09 76.73 47.47 64.78 35.95 37.19 39.26 44.27 2006 2007 2008 2009 2010 2006 2007 2008 2009 2010 56

  57. Slide 57: Dividend History

    Dividend History 50 50 Dividend (Rs) 45 EPS (Rs) 45 40 Payout Ratio (%) 40 35 35 30 30 Rs 25 25 % 20 20 15 15 10 10 5 5 0 0 FY06 FY07 FY08 FY09 FY10 57

  58. Slide 58: Part G: Sustainability

    Id TATA Part G: Sustainability Lighting up Lives! aye

  59. Slide 59: Our Sustainability Initiatives

    Our Sustainability Initiatives • Trombay SO2 emission of 24TPD (1330MW) - one of the most stringent • Forum of 46 global companies: New policy framework on Combating Climate Change (3C) • Carbon Footprint calculation for the Company completed • Sustainability Council formed - 17 CDM Projects Identif

  60. Slide 60: Thrust on Renewables

    Thrust on Renewables • Wind: Exploring newer technologies and development options • Solar: National Solar Mission Opportunity • Geothermal: Opportunities in Australia, Indonesia and India • Hydro Power: Identification and development of hydro projects • 26% stake in Dagachhu Hydro Project in Bhutan

  61. Slide 61: Various Technologies being Explored

    Various Technologies being Explored • Solar Concentrated Thermal (SCT) • Geo Thermal energy • Coal beneficiation technologies 61

  62. Slide 62: Demand Side Management and Energy Conservation

    Demand Side Management and Energy Conservation • Tata Power Energy Club formed for curbing energy wastage through school children. The Club has sensitised over 50,000 students across India who have sensitised over 75,000 people in their community • Energy conservation awareness campaigns for Custome

  63. Slide 63: Our initiatives on DSM and Energy Conservation

    Our initiatives on DSM and Energy Conservation 63

  64. Slide 64: Thank you

    kd TATA Thank you We take pride in Lighting up Lives! Lighting up Lives! TATA POWER :; 3K