  1. Slide 1: Initial Stakeholder Consultation Meeting

    Initial Stakeholder Consultation Meeting Oakdale West Estate November 2019 1

  2. Slide 2: Overview

    Overview • Welcome and Introductions • Project Summary and Program • Burton Contractors – Oakdale West Estate • Robson Civil Projects – West North South Link Road • Management of Environmental Aspects • Communications and Consultation Channels • Questions 2

  3. Slide 3: Welcome and Introductions

    Welcome and Introductions Organisation Project Team:Goodman AT&L Burton Robson Civil SLR Ecologique Ersed Contractors Projects Consulting Role Proponent Project Oakdale West – Western North Stakeholder Project Environmental Manager & Stage 1 Internal South Link Engagement Ecologist Representative Co

  4. Slide 4: Project Summary and Program

    Project Summary and Program • Goodman obtained State Significant Development Approval 7348 for staged development of the Oakdale West Estate for a warehousing and distribution hub comprising: – Concept Approval for the full site identifying primary access, road layouts, developable areas and biodive

  5. Slide 5: Site Plan

    Site Plan global environmental and advisory solutions S LR®

  6. Slide 6: Master Plan

    SSDA Estate Masterplan 7 = , WY) Y4 a Master Plan global environmental and advisory solutions

  7. Slide 7: Recent Projects - Goodman

    Recent Projects - Goodman Recent Goodman Projects include: • Oakdale South Estate • Oakdale Central Estate • Enfield Intermodal Logistics Centre Oakdale Central Estate Oakdale South Estate 7

  8. Slide 8: Burton Contractors Previous Project

    Burton Contractors Previous Project Oakdale Central, South Estate and the Old Wallgrove Rd Upgrade Burtons have extensive experience in the infrastructure scope of works for major industrial estates. Their primary activities include: • Bulk earthworks, including over 700,000m3 of cut-to-fill • Servi

  9. Slide 9: Oakdale West Estate (OWE)

    Oakdale West Estate (OWE) • Kick Off Works (Pre Christmas) – Establishment of Compound – Fencing – Sediment Controls – Dam dewatering – Tree Clearing – House Demolition – Earthworks for Permanent Compound location – Bulk earthworks in a small defined area • Plant and Machinery – 2 x 30t Excavators a

  10. Slide 10: Robson Civil Projects Pty Ltd Previous Project

    Robson Civil Projects Pty Ltd Previous Project • Southern Road Connection - Greystanes, NSW (20 Months) • Road works and Bridge construction on Reconciliation Road and the Parramatta to Liverpool Transitway (PLT) for Boral associated with the redevelopment of the old Prospect Quarry. • The PLT, brid

  11. Slide 11: West North South Link Road (WNSLR)

    West North South Link Road (WNSLR) • Kick Off Works (Pre Christmas) – Establishment of 2 Compounds (North and South) – Movement of Plant and Machinery to site – Sediment Controls – Establish traffic control requirements – Tree clearing – Bakers Lane connection – Commence watermain installation from

  12. Slide 12: Management of Environmental Aspects

    Management of Environmental Aspects There are a number of key environmental aspects applicable to the project, with associated management plans prepared to address the potential for impact including: • Traffic and Transport: – A Construction Traffic Management Plan (CTMP) has been prepared with a ke

  13. Slide 13: Management of Environmental Aspects

    Management of Environmental Aspects • Water and Soil Management: – Management plans include: • Erosion and Sediment Control Plan • Salinity Management Plan • Fill Importation Protocol • Dewatering and Management Procedure – Sediment laden runoff would be managed to capture and treat runoff prior to

  14. Slide 14: Management of Environmental Aspects

    Management of Environmental Aspects • Flora and Fauna: – Management Plans include: • Aquatic Flora and Fauna Management Plan • Terrestrial Flora and Fauna Management Plan – Preclearance surveys and inspections will occur by qualified ecologists to minimise impacts on site flora and fauna – Environme

  15. Slide 15: Management of Environmental Aspects

    Management of Environmental Aspects • Heritage: – An Unexpected Finds Protocol – Archaeological Items protocol will be established to guide construction – Contactors would be trained in the implementation of the Unexpected Finds Protocol – Works would cease in the event of a potential find, prior to

  16. Slide 16: Management of Environmental Aspects

    Management of Environmental Aspects • Noise and Vibration: – Noise and vibration will be managed by the Construction Noise and Vibration Management Plan – The Management Plan focuses on the limiting of noise where possible, timing of noisy activities to less intrusive times of the day and ongoing mo

  17. Slide 17: Management of Environmental Aspects

    Management of Environmental Aspects • Air Quality: – Air Quality will be managed by the Construction Air Quality Management Plan – Local weather conditions will be monitored to guide construction activities, with wind speeds directing mitigation measures and work programs – Dust suppression will occ

  18. Slide 18: Communications and Consultation Channels

    Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: [email protected] • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E

  19. Slide 19: Questions

    Questions global environmental and advisory solutions S | Re 19