Tellurian — Investor Presentation (December 2017)
22 slides from Tellurian's investor presentation, Dec 18, 2017
Slide 1: Corporate presentation December 2017
Corporate presentation December 2017 Exhibit 99.1
Slide 2: Cautionary statements
Cautionary statements Forward looking statements fon in thi i * within the meaning of Section 274, iies Act of 1933, \ded, fie Act OF1934, os amended the projects, ‘Accordingly, the nature, fotoment ne wore ontipote-onume ‘stimate." “expect i “forecast” inf intend,” “may,” "plan, “should “wil” “woul
Slide 3: Introduction: Building a low-cost global natural gas business
$25 million $60 million $207 million Merger $100 million Upstream Acquisition LSTK February April August December January February June November December Charif Souki and Martin Houston establish Tellurian Management, friends and family invest $60 million Meg Gentle joins to lead the company as Pres
Slide 4: Accelerated demand growth driven by low LNG prices
Netback prices to US Gulf Coast(2) New liquefaction capacity required Sources: ICE via Marketview, Kpler, Wood Mackenzie, Platts and Tullett Prebon, Fearnleys, Tellurian Research. Notes: (1) Effective capacity is defined as total capacity less unplanned outages and gas constraints. Implied utilizati
Slide 5: Daily supply readily available across the globe
Daily supply readily available across the globe Sources:Kpler, Maran Gas, IHS, Wood Mackenzie. Notes: LNG storage assumes half of fleet is in ballast, 2.9 Bcf capacity per vessel. Average cargo size 2.9 Bcf, assuming 150,000 m3 ship. In 2017, approximately a third of all LNG cargoes are estimated to
Slide 6: Building a low-cost global gas business
Building a low-cost global gas business Pipeline Liquefaction Marketing Upstream Purchase low-cost gas at liquidity points or as reserves Diversify gas supply Develop pipeline solutions for constrained production basins Maximize access to supply liquidity Develop low-cost liquefaction ~$550 per tonn
Slide 7: Tellurian will offer equity interest in Driftwood Holdings
Tellurian will offer equity interest in Driftwood Holdings Driftwood Holdings will consist of Tellurian Production Company, Driftwood Pipeline and Driftwood LNG terminal (~27.6 mtpa) Equity will cost ~$1,500 per tonne Customer/Partner will receive equity LNG at tailgate of Driftwood LNG terminal at
Slide 8: Total cost of ~$3/mmBtu locks in low cost of supply
Total cost of ~$3/mmBtu locks in low cost of supply Potential margin capture from Driftwood Sources: Wood Mackenzie, Platts, Tullet Prebon, Tellurian Research. Notes: (1) Drilling and completion based on well cost of $10.2 million, 15.5 Bcf EUR, and 75.00% net revenue interest (“NRI”) (8/8ths). (2)
Slide 9: Illustrative financials
Illustrative financials Business model Notes: (1) Phase 1 of the EPC agreement reflects 2 plants, 1 berth, and 2 tanks; full development reflects 5 plants, 3 berths, and 3 tanks. (2) Resource need for 30 year period. (3) Drilling capital expenditures of $3.4 billion, net of $2.2 billion of gas sales
Slide 10: Return on $1,500 per tonne investment
Return on $1,500 per tonne investment Business model Payback period analysis(6) Years to recover capital $0 $(1,500) Cumulative cash flow $ millions $10/mmBtu $6/mmBtu Netback FOB U.S. Gulf Coast 4 10 Notes: (1) Equivalent to FOB price at U.S. Gulf Coast. (2) Assuming $3/mmBtu cost of LNG. (3) Assum
Slide 11: Driftwood vs. competitors – cost per tonne
Driftwood vs. competitors – cost per tonne Sources:Wood Mackenzie, The World Bank, Tellurian Research. Notes:(1) The World Bank bases the Logistics Performance Index (LPI) on surveys of operators to measure logistics “friendliness “ in respective countries which is supplemented by quantitative data
Slide 12: Integrated model prevalent internationally
Integrated model prevalent internationally Source:IHS. Projects include: Australasia APLNG, Darwin, GLNG, Gorgon, Ichthys, NWS, Pluto, Northwest Shelf, QCLNG, Wheatstone, PNG LNG, Tangguh, Brunei LNG, Donggi-Senoro, MLNG, Yamal LNG Mideast/Africa Angola LNG, EG LNG, Damietta, ELNG, Yemen LNG, Mozamb
Slide 13: Driftwood LNG terminal
Driftwood LNG terminal Notes:(1) Before owners’ costs, financing costs and contingencies. Driftwood LNG terminal Land ~1,000 acres near Lake Charles, LA Capacity ~27.6 mtpa Trains Up to 20 trains of ~1.38 mtpa each Chart heat exchangers GE LM6000 PF+ compressors Storage 3 storage tanks 235,000 m3 ea
Slide 14: Tellurian Pipeline Network
Tellurian Pipeline Network Notes: (1) Currently not included in Driftwood Holdings illustrative financials (slide 9) Tellurian Pipeline Network Driftwood Pipeline Capacity, Bcf/d 4.0 Cost, $ billions $2.2 Length, miles 96 Diameter, inches 48 Compression, HP 274,000 Status FERC approval pending Hayne
Slide 15: Demand triples in 7 years
Notes:(1) LNG demand includes ambient capacity. (2) Includes: Driftwood LNG, Sabine Pass LNG T1-3, Cameron LNG T1-3, SASOL, Lake Charles CCGT, G2X Big Lake Fuels, LACC – Lotte and Westlake Chemical. Source:Company data, Tellurian estimates. Louisiana Texas Gulf of Mexico Lake Charles Petrochemical c
Slide 16: Tellurian Production Company
Tellurian Production Company Acquire and develop long life, low-cost natural gas resources Low geological risk Scalable position Production of ~1.5 Bcf/d starting in 2022 Total resources of ~15 Tcf for Phase 1 Operatorship Low operating costs Flexible development Initially focused on Haynesville bas
Slide 17: Conclusions
LNG demand is growing at 12% per annum Netback LNG prices to the U.S. Gulf Coast of > $8.00/mmBtu have signaled that additional liquefaction capacity is needed The U.S. is best positioned to meet global LNG supply needs with access to abundant low-cost gas and a track record of building low-cost liq
Slide 18: Contact us
Contact us Amit Marwaha Director, Investor Relations & Finance +1 832 485 2004 [email protected] Joi Lecznar SVP, Public Affairs & Communication +1 832 962 4044 [email protected] @TellurianLNG Contacts
Slide 19: Additional detail
2017 Additional detail
Slide 20: Key terms of EPC agreements with Bechtel
Key terms of EPC agreements with Bechtel Additional detail Phase 1 Phase 2 Phase 3 Phase 4 Total 11.0 5.5 5.5 5.5 27.6 Trains 8 4 4 4 20 Storage facilities 2 0 1 0 3 Berths 1 1 1 0 3 Capacity
Slide 21: Tellurian Pipeline Network
Tellurian Pipeline Network Additional detail Gillis Market Area KMPL TETCO Trunkline Transco Tenn Gas CTPL Cameron FGT DWPL TETCO Trunkline Transco Tenn Gas CTPL Cameron Interconnects Permian Supply Area ETC –Comanche Trail ETC – Trans-Pecos ETC – Oasis Vaquero OneOK WesTex OXY Enterprise Jal El Pas
Slide 22: Haynesville type curve comparison
Haynesville type curve comparison Comparative type curve statistics Cumulative production normalized to 7,500’(3) Source:Company investor presentations. Notes:(1) Assumes 75.00% net revenue interest (“NRI”) (8/8ths). (2) Assumes gas prices of $3.00/mcf based on NRI and returns published specific to