AGL Energy Limited · ASX:AGL
AGL Energy — Corporate Update (December 2014)
32 slides from AGL Energy's corporate update, Dec 3, 2014
Slide 1: Nyngan Solar Plant Community Consultative Committee
Nyngan Solar 1 Plant Community Consultative Committee 3 December 2014
Slide 2: Agenda
2 Agenda 1 Welcome December CCC 2 Review previous minutes 3 Overview of project status (AGL and First Solar) 4 Employment / local spending 5 Project planning 6 Construction community fund 7 Next meeting and close > Nyngan Solar Project > AGL Energy > 3 December 2014
Slide 3: Review of previous minutes
3 Review of previous minutes (all) > Presentation title > Author > Date (Verdana 10pt)
Slide 4: Review actions from previous meeting
4 2. Review actions from previous meeting Action item CCC Status Who meeting 1 AGL to progress the shopfront display. Waiting on April 2014 Open HO Bogan Shire Council to progress shop front letting agreements. 2 AGL to work in consultation with the community and October 2014 Open HO / community gro
Slide 5: Review actions from previous meeting
5 2. Review actions from previous meeting Action item CCC Status Who meeting 5 AGL to coordinate with First Solar the CCC site visit October Open HO on 6 December 2014 2014 6 AGL to progress the community open day at the October Open HO project’s completion 2014 7 HO to provide an update on visitors
Slide 6: Confirmation of June 2014 minutes
6 2. Confirmation of June 2014 minutes › Any comments on the October minutes? › Accept as accurate record of meeting? > Nyngan Solar Project > AGL Energy > 3 December 2014
Slide 7: Overview of project status
7 Overview of project status •Adam Mackett, AGL •Bruce Smith, First Solar > Presentation title > Author > Date (Verdana 10pt)
Slide 8: AGL overview of project status
8 3. AGL overview of project status Current status on the Nyngan Solar Plant: › Electrical works on site are progressing › Energisation and activities for generation approvals are progressing » Australian Energy Market Operator » Clean Energy Regulatory › Project on track for completion in June 2015
Slide 9: AGL overview: plant connection status
9 3. AGL overview of project status Status on the Nyngan Solar Plant connection: › Connection works are practically complete. » 132kV transmission line (Essential Energy) » 132kV Switchyard (Essential Energy) » 132kV Substation energised 26 November > Nyngan Solar Project > AGL Energy > 3 December 2
Slide 10: AGL overview of project status
10 3. AGL overview of project status 132kV transmission line energisation 132kV substation energised (Essential Energy asset) on 26 November > Nyngan Solar Project > AGL Energy > 3 December 2014
Slide 11: AGL overview of project status
11 3. AGL overview of project status › Essential Energy work » 33kV switchyard Energisation – availability (26 Nov 2014) › Communications, SCADA and protocol » AGL, First Solar, CPP, Essential Energy and AEMO single operation Switchboard in photo voltaic › Ready to Energise inverter switchgear (PV
Slide 12: First Solar overview: Nyngan Solar Plant progress
12 3. First Solar overview of project status Nyngan Solar Plant progress › 100% of the 137,752 steel posts have been installed › 112,000 of the 140,000 tilt brackets have been installed › 46,000 Tables installed › 678,400 of the 1,350,000 panels have been delivered › 273,000 panels installed to date
Slide 13: First Solar overview of project status
13 3. First Solar overview of project status PVIS building – cables installed Section 1 inclement weather (Aug from transformer 2014) > Nyngan Solar Project > AGL Energy > 3 December 2014
Slide 14: First Solar overview of project status
14 3. First Solar overview of project status 33kV AC Feeder cables from Testing at PVCS1 (Section 1) Section 1 and 2 (PVCS) > Nyngan Solar Project > AGL Energy > 3 December 2014
Slide 15: First Solar overview of project status
15 3. First Solar overview of project status Trench for 33kV AC Collector PV module storage area cable in Section 1 > Nyngan Solar Project > AGL Energy > 3 December 2014
Slide 16: First Solar overview of project status
16 3. First Solar overview of project status > Nyngan Solar Project > AGL Energy > 3 December 2014
Slide 17: First Solar overview of project status
17 3. First Solar overview of project status > Nyngan Solar Project > AGL Energy > 3 December 2014
Slide 18: Employment, Local spending, Information sharing
18 Employment Local spending Information sharing, community matters •Bruce Smith, First Solar > Presentation title > Author > Date (Verdana 10pt)
Slide 19: Employment
19 4. Employment Project labour › 30 local Nyngan residents employed › 40+ residents from Warren, Naromine, Dubbo, Orange and other areas. Nuts and Bolts Workshop at CWA hall › Coordinated between WBHO and JobLink Plus 3 local ladies supporting. Training › First Solar’s subcontractor (WBHO-Probuild)
Slide 20: Local spending
20 4. Local spending Economics – Solar Village Monthly spend of camp and dining facilities 50,000 PM First Solar spend at local businesses 10,000 PM WBHO spend at local businesses 50,000 PM Economics – Hotels and campground Monthly spend 152,000PM Total estimate 261,000PM > Broken Hill Solar Plant >
Slide 21: Information sharing, community matters
21 4. Information sharing, community matters Snake handling training › Three snake handlers on site Site visits › Cobar and Canterbury Council › Engineers Australia (Dubbo and regional group) › Over 10 Broken Hill tenderers visited the Nyngan site Pallet reuse, cardboard waste management › Skill Set
Slide 22: Snake handler training
Snake handler training Energy in action:
Slide 23: First Solar project contact details
23 4. First Solar project contact details First Solar contacts: Bruce Smith Michael Law Project Manager Construction Manager Mob: 0428 199 241 Mob: 0417 369 921 E: [email protected] E: [email protected] > Broken Hill Solar Plant > AGL Energy > 1 October 2014
Slide 24: Project planning
24 Project planning •Adam Mackett / Helena Orel, AGL > Presentation title > Author > Date (Verdana 10pt)
Slide 25: Project planning
25 5. Project planning Landscaping activities › Landscaping work timing second quarter 2015 Community site visits › 10am Saturday 6 December 2014 Solar plant tourism during operation ABC TV AGL completed filming for ABC Splash education video about the solar projects on 10 November 2014. Community f
Slide 26: Landscape plan
26 5. Landscape plan > Nyngan Solar Project > AGL Energy > 3 December 2014
Slide 27: Landscaping work
27 5. Landscaping work Groups to involve: › Nyngan Local Aboriginal Land Council › Local Land Services Central West › Community Hub › Direct neighbours › Local schools: » Nyngan Public school » Nyngan High School » St Josephs School » Girilambone Public School » Hermidale Public School › Need to dec
Slide 28: Construction community fund
28 Construction community fund •Helena Orel, AGL
Slide 29: Community fund
29 6. Community fund Update on the Community Fund › Planning to roll out second round of funding in the second quarter of 2015 › Fund will be advertised open for applications around April 2015 > Nyngan Solar Project > AGL Energy > 3 December2014
Slide 30: Other business, next meeting and close
30 Other business Next meeting and close
Slide 31: Any other business
31 7. Any other business › Questions from observers? > Nyngan Solar Project > AGL Energy > 3 December2014
Slide 32: Next meeting
32 7. Next meeting › Agenda – is there anything that you would like to discuss? › Next meeting: Wednesday 4 February › Time: 6pm – 8pm › Venue: CWA Hall > Nyngan Solar Project > AGL Energy > 3 December 2014