Nu E Power Corp. · CSE:NUE
Nu E Power — Investor Presentation (October 2026)
16 slides from Nu E Power's investor presentation, October 2026
Slide 1: Building for Demand
Building for Demand Energy infrastructure developer Corporate presentation CSE NUE October 2026 OTC NUEPF FSE NUE1
Slide 2: Completed to date, and the next twenty-four months
Completed to date, and the next Completed Projected twenty-four months Nov 2025 New CEO, team and board Apr 2026 Darkhan Energy Park joint Aug 2024 Next 2028 to 2029 development Listed on the Canadian Regina land closing. Alberta Further energy parks agreement Securities Exchange definitive agreemen
Slide 3: We develop megawatt-hours the way real-estate develops square footage
We develop megawatt-hours the way real-estate develops square footage Exits by selling the Real-estate Zoning, permits Land Square footage entitled asset or developer and servicing building it out Permitting, Exits by selling, Sites with existing or rezoning, grid Megawatt- partnering or emerging de
Slide 4: No matter the technology, we develop the infrastructure
No matter the technology, we develop the infrastructure Renewables and storage Natural gas Nuclear (SMR) Grid connection Utility-scale renewables with Reciprocating engines and Small modular reactors, a co-located and standalone CCGT, firming power for large longer-term pathway Firm power to battery
Slide 5: Every project clears four gates before capital scales
Every project clears four gates before capital scales Capital released ~90% At sale Capital returned Capital released Capital released of development capital ~1% ~9% of development capital of development capital Gate 1 Gate 2 Gate 3 Gate 4 Screening to feasibility Feasibility to Development to Notic
Slide 6: Three ways a ready-to-build project creates value
Three ways a ready-to-build project creates value Sell at Sell down at Tokenization ready-to-build financial close (Royalty) Ready-to- build project Sell all or most of the project once it is permitted and Sell 60 to 80% of the equity to a construction partner, Keep a 5 to 10% stake or a management
Slide 7: Operators who have built and run power at scale
Operators who have built and run power at scale Management Board of directors Eugene Hodgson Bold Batsukh Peter Espig Hon. Tony Clement Government Energy and CEO, Nicola Former federal relations mining, Mongolia Mining cabinet minister Broderick Gunning John Windsor John Meekison, AJ Kiani President
Slide 8: Key Projects
Key Projects Short term Medium term Long term Lethbridge One Operating, 2.19 MW Alberta Energy net Regina-area land Park 29.44 acres, LOI 503.5 MW gross, LOI 1,112.25 Lethbridge Two offtake LOI Up to 17 MW Hays Project Darkhan, MW gross portfolio capacity 145 MWac, LOI, not in Mongolia Luxxfolio tot
Slide 9: Lethbridge One has been generating since December 2024
Lethbridge One has been generating since December 2024 8.75 MWac of solar in commercial operation, 2.19 MW net to NUE Power purchaser Lethbridge Electric Utility NUE position 25% working interest Operator JV partner 09
Slide 10: 503.5 MW across three Alberta projects, advanced to letter of intent
503.5 MW across three Alberta projects, advanced to letter of intent Lethbridge Two Lethbridge Three Hanna Solar and BESS 12.5 MWac 155 MWac 336 MWac 6.25 MW net + 10 MW BESS 77.5 MW net + 100 MW BESS 168 MW net + 100 MW BESS AUC approved AESO Cluster 3 AUC approved AESO Cluster 3 Pre-development AE
Slide 11: Saskatchewan's largest investment must build most of its own power
Saskatchewan's largest investment must build most of its own power 1,200 MW required by the $52B Regina AI hub, the largest private capital investment in Canadian history A Crown utility system 1,200 New large loads need new, dedicated supply alongside SaskPower's grid. MW Grid supply lags demand Co
Slide 12: Land position near Regina
Land position near Regina 29.44 acres under a non-binding letter of intent to acquire, signed August 7, 2026, for $2.7M Regina Area Hybrid Energy Park Concept Hybrid: solar, natural gas and battery storage Capacity To be defined Illustrative concept Zoning Not yet zoned or serviced for industrial us
Slide 13: Darkhan Energy Park firm power for a coal-dependent grid
Darkhan Energy Park Where it stands firm power for a Environmental and feasibility studies under way coal-dependent grid Offtake to the Mongolian grid is anticipated; no power purchase agreement is in place 600 Not owned by NUE at this time Darkhan MW Mongolia of HELE coal-fired generation, gross Ne
Slide 14: $3.86M raised in August 2026, upsized from $3.0M
$3.86M raised in August 2026, upsized from $3.0M $0.14 ~$12.8M 91.1M 131.5M share price market capitalization, basic shares fully diluted basic Trading August 2026 placement 30-day VWAP $0.16 Units 25.7M at $0.15 52-week range $0.10 to $0.27 Warrants Reserved for issuance 40.3M One-half at $0.25, th
Slide 15: Demand-Led, Future Ready
Demand-Led, Future Ready Energy infrastructure development Broderick Gunning Drew Finch Calgary Vancouver President and CEO Business Development www.nu-energy.ca [email protected] [email protected] CSE NUE OTC NUEPF FSE NUE1
Slide 16: Disclaimer and forward-looking information
Disclaimer and forward-looking information Important notice Cautionary note regarding forward-looking information This document has been prepared by NU E Power Corp. ("NUE" or This document contains forward-looking information within the meaning of applicable Canadian securities legislation, includi