Nu E Power Corp. · CSE:NUE

Nu E Power — Investor Presentation (October 2026)

16 slides from Nu E Power's investor presentation, October 2026

  1. Slide 1: Building for Demand

    Building for Demand Energy infrastructure developer Corporate presentation CSE NUE October 2026 OTC NUEPF FSE NUE1

  2. Slide 2: Completed to date, and the next twenty-four months

    Completed to date, and the next Completed Projected twenty-four months Nov 2025 New CEO, team and board Apr 2026 Darkhan Energy Park joint Aug 2024 Next 2028 to 2029 development Listed on the Canadian Regina land closing. Alberta Further energy parks agreement Securities Exchange definitive agreemen

  3. Slide 3: We develop megawatt-hours the way real-estate develops square footage

    We develop megawatt-hours the way real-estate develops square footage Exits by selling the Real-estate Zoning, permits Land Square footage entitled asset or developer and servicing building it out Permitting, Exits by selling, Sites with existing or rezoning, grid Megawatt- partnering or emerging de

  4. Slide 4: No matter the technology, we develop the infrastructure

    No matter the technology, we develop the infrastructure Renewables and storage Natural gas Nuclear (SMR) Grid connection Utility-scale renewables with Reciprocating engines and Small modular reactors, a co-located and standalone CCGT, firming power for large longer-term pathway Firm power to battery

  5. Slide 5: Every project clears four gates before capital scales

    Every project clears four gates before capital scales Capital released ~90% At sale Capital returned Capital released Capital released of development capital ~1% ~9% of development capital of development capital Gate 1 Gate 2 Gate 3 Gate 4 Screening to feasibility Feasibility to Development to Notic

  6. Slide 6: Three ways a ready-to-build project creates value

    Three ways a ready-to-build project creates value Sell at Sell down at Tokenization ready-to-build financial close (Royalty) Ready-to- build project Sell all or most of the project once it is permitted and Sell 60 to 80% of the equity to a construction partner, Keep a 5 to 10% stake or a management

  7. Slide 7: Operators who have built and run power at scale

    Operators who have built and run power at scale Management Board of directors Eugene Hodgson Bold Batsukh Peter Espig Hon. Tony Clement Government Energy and CEO, Nicola Former federal relations mining, Mongolia Mining cabinet minister Broderick Gunning John Windsor John Meekison, AJ Kiani President

  8. Slide 8: Key Projects

    Key Projects Short term Medium term Long term Lethbridge One Operating, 2.19 MW Alberta Energy net Regina-area land Park 29.44 acres, LOI 503.5 MW gross, LOI 1,112.25 Lethbridge Two offtake LOI Up to 17 MW Hays Project Darkhan, MW gross portfolio capacity 145 MWac, LOI, not in Mongolia Luxxfolio tot

  9. Slide 9: Lethbridge One has been generating since December 2024

    Lethbridge One has been generating since December 2024 8.75 MWac of solar in commercial operation, 2.19 MW net to NUE Power purchaser Lethbridge Electric Utility NUE position 25% working interest Operator JV partner 09

  10. Slide 10: 503.5 MW across three Alberta projects, advanced to letter of intent

    503.5 MW across three Alberta projects, advanced to letter of intent Lethbridge Two Lethbridge Three Hanna Solar and BESS 12.5 MWac 155 MWac 336 MWac 6.25 MW net + 10 MW BESS 77.5 MW net + 100 MW BESS 168 MW net + 100 MW BESS AUC approved AESO Cluster 3 AUC approved AESO Cluster 3 Pre-development AE

  11. Slide 11: Saskatchewan's largest investment must build most of its own power

    Saskatchewan's largest investment must build most of its own power 1,200 MW required by the $52B Regina AI hub, the largest private capital investment in Canadian history A Crown utility system 1,200 New large loads need new, dedicated supply alongside SaskPower's grid. MW Grid supply lags demand Co

  12. Slide 12: Land position near Regina

    Land position near Regina 29.44 acres under a non-binding letter of intent to acquire, signed August 7, 2026, for $2.7M Regina Area Hybrid Energy Park Concept Hybrid: solar, natural gas and battery storage Capacity To be defined Illustrative concept Zoning Not yet zoned or serviced for industrial us

  13. Slide 13: Darkhan Energy Park firm power for a coal-dependent grid

    Darkhan Energy Park Where it stands firm power for a Environmental and feasibility studies under way coal-dependent grid Offtake to the Mongolian grid is anticipated; no power purchase agreement is in place 600 Not owned by NUE at this time Darkhan MW Mongolia of HELE coal-fired generation, gross Ne

  14. Slide 14: $3.86M raised in August 2026, upsized from $3.0M

    $3.86M raised in August 2026, upsized from $3.0M $0.14 ~$12.8M 91.1M 131.5M share price market capitalization, basic shares fully diluted basic Trading August 2026 placement 30-day VWAP $0.16 Units 25.7M at $0.15 52-week range $0.10 to $0.27 Warrants Reserved for issuance 40.3M One-half at $0.25, th

  15. Slide 15: Demand-Led, Future Ready

    Demand-Led, Future Ready Energy infrastructure development Broderick Gunning Drew Finch Calgary Vancouver President and CEO Business Development www.nu-energy.ca [email protected] [email protected] CSE NUE OTC NUEPF FSE NUE1

  16. Slide 16: Disclaimer and forward-looking information

    Disclaimer and forward-looking information Important notice Cautionary note regarding forward-looking information This document has been prepared by NU E Power Corp. ("NUE" or This document contains forward-looking information within the meaning of applicable Canadian securities legislation, includi