PT Perusahaan Gas Negara (Persero) Tbk Class B · IDX:PGAS
PT Perusahaan Gas Negara (Persero) Tbk Class B — Perusahaan Gas Negara — Investor Presentation (June 2010)
30 slides from PT Perusahaan Gas Negara (Persero) Tbk Class B's investor presentation, June 2010

Slide 1: Perusahaan Gas Negara Presentation to the investors
Perusahaan Gas Negara Presentation to the investors June 2010 update

Slide 2: Disclaimer
Disclaimer: The information contained in our presentation is intended solely for your personal reference. reference In addition, such information contains projections and forward-looking statements that reflect the Company’s current views with respect to future events and financial performance. Thes

Slide 3: Indonesia: A Major Producer of Natural Gas
3 Indonesia : A Major Producer of Natural Gas T h e largest The la r g e st proven p r o v e n gas reserves in Asia Pacific Ahead of Australia, China and Malaysia (BP World Energy Report 2010) 3.71 1.32 53.06 21.49 24.14 7.96 7.76 26.68 6.31 6.18 6.39 6.30 Source: Director General of Oil and Gas Nat

Slide 4: Demand for Natural Gas – Key Drivers
Demand for Natural Gas – Key Drivers No Subsidy of Fuel for the Industries • Subsidies for industries revoked in 2005 Pricing P i i and d Effi Efficiencies i i • Significant price and efficiencies benefits by converting to natural gas, as well as environmental concerns Conversion of Power Plants • P

Slide 5: Unmet Demand for Natural Gas
5 Unmet Demand for Natural Gas Power Sector 2500 PLN (state power company) gas demand wasas 1.8 1 8 BSCFD in 2009 for existing e isting dual d al fired power plants growing to 2.1 BSCFD in 2000 2015. Representing unmet demand of 0.8 BSCFD 1500 Demand Additional demand of 0.1 BSCFD from IPP 1000 Supp

Slide 6: Current Low Consumption to Drive Demand
6 Current Low Consumption to Drive Demand Low level of current consumption of natural gas and electricity Ensure the continuing growth of demand for natural gas

Slide 7: Opportunity: Price Advantages
7 Opportunity : Price Advantages Lower gas price compares to other fuels Industrial Prices are set on B‐to‐B basis PGN Gas Price and HSD Price 40.00 Natural Gas 6.35 PGN Average HSD Unsubsidized Price Selling Price (USD/MMBTU) LPG ‐ 3 kg (Subsidized) 10 05 10.05 35.00 PGN Average Selling Price (USD/

Slide 8: New Pricing Scheme
New Pricing Scheme Minister of Energy and Mineral Resources Decree No. 19 Year Cost of Gas 2009 • Allows pricing for “general users” to be determined by the Companies • General users are non‐subsidized industries and power plants Transport & Pricing Considerations Distribution Costs • Demand and Sup

Slide 9: Growing operational performance
9 Growing operational performance 800 900 Transmission Volume Distribution Volume 800 780 700 760 600 740 500 400 720 300 700 200 680 100 707 720 734 736 716 743 747 758 779 763 763 767 758 369 389 402 422 527 551 566 577 721 756 776 792 841 660 0 Volume (MMSCFD) Volume (MMSCFD) Deliver strong growt

Slide 10: Growing Revenues, Expanding EBITDA
10 Growing Revenues, Expanding EBITDA Revenue EBITDA and EBIT 20,000 10,000 60% 54% 55% 18,000 20 9,000 52% 50% 1,624 47% 16,000 8,000 14,000 7,000 40% 9,303 12,000 1,519 6,000 billion IDR billlion 10 000 10,000 5 000 5,000 IDR b 6,375 8,000 1,208 16,380 4,000 7,676 20% 6,000 , 3,000 , 11 275 11,275

Slide 11: Financial Statements (3M-2010)
11 Financial Statements (3M‐2010) 5,000 200 199 FX Gain/Loss 150 4,500 100 4,000 50 billion ‐ IDR b 3,500 (50) 3M09 3M10 3,000 (100) billion (150) (134) 2 500 2,500 IDR b 4,478 4,486 (200) 2,000 1,500 Exchange Rate 1,000 1,836 1,760 1,997 2,110 1,771 1,220 ‐ 31 Maret 2009 500 644 615 USD 1 = IDR 11,

Slide 12: Our Sound Balance Sheet
12 Our Sound Balance Sheet (IDR billion) Mar 31, 2009 Mar 31, 2010 % Current Assets 7,235 7 235 10,632 10 632 47 Non Current Assets 20,803 19,037 ‐8 Total Assets 28,038 29,668 6 Current Liabilities C Li bili i 4,071 4 071 3,600 3 600 ‐12 12 Non Current Liabilities 14,342 11,599 ‐19 Minority Interest

Slide 13: Debt Composition
13 DEBT COMPOSITION (as of March 31 31, 2010) Long-term debt amounting to USD 1.137 billion Mostly long dated/maturity loans from Developmental Banks JPY Fixed 41.7% Float 47.8% USD 52.2% 58.3% Effective Cost of Debt of Around 2.6%

Slide 14: Customers' Profile
14 Customers’ Profile As of March 31, 2010, sales volume of industrial customers was 826 MMSCFD or equal to 98% of PGN’s PGN s sales 40.00% 38.00% 30.00% 20.00% 14.00% 10.00% 9.00% 9.00% 8.00% 6.00% 5.00% 5.00% 3 00% 3.00% 2.00% 0.76% 0.03% 0.00% Power Chemical Ceramic Basic Food Glass Paper Fabrica

Slide 15: Our Business Model
15 Our Business Model GAS SUPPLY ‐ Contracted for Key Suppliers – Under Upstream Authority / BPMigas volume and prices PGN Industrial Power Sectors Commercial Residential CUSTOMERS Customers Customers (PLN, IPP) Customers ‐ Contracted for (Steel Millls, (Hotels, Shopping volume Petrochemical, Malls,

Slide 16: Our Network & Facilities
16 Our Network & Facilities PLN – Medan (80 MMSCFD) D i Duri Panaran Station, Station Batam KALIMANTAN Pagardewa Compressor St. Grissik Receiving Station Legend: Strategic Business Unit (SBU) I Strategic Business Unit (SBU) II Strategic Business Unit (SBU) III South Sumatera – West Java Transmission

Slide 17: Our Sources of Gas
17 Our Sources of Gas Pertamina Medan DOH Rantau 44 BCF Medco E&P Lematangg KALIMANTAN Lematang Block Grissik PSC Grissik Corridor Block 2581 BCF Medco E&P Indonesia South & Central Sumatra Block 14 BCF Pertamina Sumatera Selatan DOH Sumsel, Merbau Field, Pagardewa, Pertamina JBB Prabumenang, Tasim,

Slide 18: Update on South Sumatera Supply
18 Update on South Sumatera Supply Chevron – Duri Singapore – (Steamflood) Power Gas Grissik PGN (West Java & South Sumatera) Flow from South Sumatera Supply • No issue with production or technical aspect • PGN owns and operates all pipelines connecting to the gas field • Trend of increasing/recover

Slide 19: Strategy to Fulfill Demand
Strategy to Fulfill Demand Obtain access to new gas supplies • Actively seeking new gas supplies, starting from the ones located in the proximity of existing infrastructure • Seek to obtain more allocation from the imposed domestic market obligations to new productions and contracts, but will requir

Slide 20: Recent Developments
20 Recent Developments p Event Detail of Event Signing on second amendment of GSPA on gas Extending gas delivery of 3.78 TBTU starting from May supply from Pertamina ONWJ 2010 up to December 2010 Signing on amendment and restatement to Gas delivery of 12.5 BBTUD for 5 years starting June replace int

Slide 21: Plan for New LNG Infrastructure
21 Plan for New LNG Infrastructure To Build the first 2 LNG Receivingg Terminals Arun Mahakam Block Tangguh Donggi Senoro (planned) Masela Existing LNG Liquefaction Plant (planned) Existing transmission pipelines Planned LNG Liquefaction Plant Planned LNG Receiving Terminal (Source : LNGpedia)

Slide 22: Floating LNG Terminals
22 Floating LNG Terminals Teesside Northeast Gateway Dubai LNG Ship “Golar Spirit” converted Livorno into LNG Regas Terminal (Source : LNGpedia) Gulf Gateway Kuwait Medan Pecem W. Java Operational Guanabara Bay Mossel Bay Under Development Bahía Blanca

Slide 23: Floating LNG Terminal Overview
23 Floating LNG Terminal Overview

Slide 24: LNG Receiving Terminals
24 LNG Receivingg Terminals WEST JAVA NORTH SUMATRA Location Jakarta Bay Belawan, Medan Capacity (MTPA) 1.5 – 3 MTPA Customers Power plants, industry Domestic and international P t ti l SSupply Potential l B t Bontang and d others th sources Owner PGN ((40%)) Pertamina ((60%)) PGN Scope FSRU, jetty,

Slide 25: West Java FSRU – Recent Developments
25 West Java FSRU – Recent Developments Cooperation aspects: • PLN pulled out of consortium citing focus on core‐business • JV between PGN and Pertamina signed Technical aspects: • JV appointed WorleyParsons Indonesia as Project Management Consultant • Tender for EIA Consultant in evaluation process

Slide 26: North Sumatera FSRU – Recent Developments
26 North o Su Sumatera a e a FSRU S U – Recent ece Developments e e op e s Legal/Coordination: • Close coordination with Regional Government of North Sumatera and Belawan Port Authority Technical aspects: • Site has been selected in consultation with Belawan Port Authority and Regional g Government

Slide 27: West Java Distribution Expansion
27 WEST JAVA DISTRIBUTION EXPANSION 460 km West Java Distribution Expansion Project Distribution of SSWJ gas expected in 2011 460 km expansion of Jakarta, Bekasi, Cikampek, Bogor and Banten distribution system Palembang System capacity increased by • 85% in West Java Bekasi Karawang • 50% nationwide

Slide 28: Recently Issued Regulations
28 Recently ece y Issued ssued Regulations egu a o s Government Regulation No. 55/2009 • Upstream has a mandate to meet domestic demand by allocating 25% of natural gas production Ministerial Decree No. 19/2009 • Set the structure of natural gas trading, transmission and distribution business and li

Slide 29: Guidance For 2010
29 Guidance For 2010 G Flow Gas l Projections j i • Transmission: flat • Distribution: 800‐900 MMSCFD Capital Expenditure • Commitment in 2010: USD 200-250 million

Slide 30: Thank You
30 THANK YOU Contact: Investor Relations PT Perusahaan Gas Negara (Persero) Tbk Jl. K H Zainul Arifin No. 20, Jakarta‐11140, Indonesia Ph: 62 21 6334838 Fax: 62 21 6331632 http://www.pgn.co.id
Source: Internet Archive copy of pgn.co.id
More decks from PT Perusahaan Gas Negara (Persero) Tbk Class B
FY2025 Earnings Presentation22 slides · 2026
PT Perusahaan Gas Negara — 9M 2025 Earnings Presentation19 slides · Nov 28, 2025
PT Perusahaan Gas Negara — 9M 2025 Earnings Presentation19 slides · Nov 5, 2025
PT Perusahaan Gas Negara — H1 2025 Earnings Presentation19 slides · Oct 7, 2025
PT Perusahaan Gas Negara — H1 2025 Earnings Presentation24 slides · Sep 10, 2025
PT Perusahaan Gas Negara — 3M 2025 Earnings Presentation18 slides · May 5, 2025