Hitachi Energy India Limited · NSE:POWERINDIA
Hitachi Energy India — Q2 FY27 Earnings Presentation
17 slides from Hitachi Energy India's earnings presentation, Nov 12, 2026
Slide 1: Analysts/Investors' Presentation filing letter
HITACHI November 12, 2026 The Secretary, The Manager, Listing Department, Listing Department, BSE Limited, National Stock Exchange of India Limited, 1st Floor, Phiroze Jeejeebhoy Towers, ‘Exchange Plaza’, 5th Floor, Plot No. C/1, G Block, Dalal Street, Bandra Kurla Complex, Bandra (East), Mumbai - 4
Slide 2: Q2 FY26-27 Analyst Conference Call
Hitachi Energy India Ltd Q2 FY26-27 | Analyst Conference Call N Venu, Managing Director and CEO Symbol: POWERINDIA | Scrip code: 543187 12th November 2026 Public © 2026 Hitachi Energy. All rights reserved.
Slide 3: Cautionary statement
Cautionary statement This presentation has been prepared by Hitachi Energy India Limited (“Company”) solely for information purposes. While reasonable care has been taken in preparing this presentation, no representation or warranty, express or implied, is made regarding the accuracy, completeness o
Slide 4: License to operate: Safety, Integrity and Quality
License to operate Safety, Integrity and Quality 0.10 1100+ Lifesaving rules inspections performed Safety Total recordable injury frequency rate (TRIFR) – YTD Target: 0.09 98.75% Integrity High risk hazards closed on time Zero 2000+ Quality Non-Conformance Reports (NCRs) Safety Observation Tours (SO
Slide 5: ESG progress against 2030 targets
ESG progress against 2030 targets Planet People Principle Segments Progress / 2030 target Segments Progress / 2030 target Segments Commitment / target CO₂ 74% reduction (86% excl. SF₆) emissions Target: 50% reduction Safety Zero-harm commitment Corruption Zero-incident commitment Renewable 100% clea
Slide 6: India's energy transition drives grid investment
India’s energy transition drives grid investment From long term planning to project approval increases conviction for multi year structural opportunity Growth drivers Grid investment catalysts In H1FY27, RE capacity in India reached 299.25 GW (33% of non fossil target of 900 GW Renewables 1 by 2036)
Slide 7: Solid performance driving growth and building margins
Solid performance driving growth and building margins Rs Crs Growth Growth Growth Particulars Q2FY27 YoY(%) QoQ (%) H1FY27 YoY(%) Orders in Q2FY27 Orders(with ✓ TBCB: secured four marquee transformers and substation 4,120.8 85.9% -19.1% 9.217.3 -32.0% HVDC) orders from two leading EPC players, inclu
Slide 8: Powering growth through successful project execution
Powering growth through successful project execution Fatehgarh III Grid automation for leading 33/220 KV AIS Main 220 KV Switchyard STATCOM utility – substation SAS and receiving Substation at Kalinganagar,Jajpur ,Odisha CRP Pallet Plant – 2.0 Sandur, Karnataka • First Grid Forming STATCOM in • Larg
Slide 9: Building capacity ahead of demand
Building capacity ahead of demand KARJAN SAVLI MYSURU High Voltage factory expansion and GIS Greenfield large power transformer Insulation factory expansion feeder factory HALOL MANEJA PEENYA Grid automation, expansion, refurbishment Dry bushing factory Power transformer factory expansion and locali
Slide 10: Powering India's energy future through collaboration and leadership
Powering India’s energy future through collaboration and leadership India–Japan Annual CIGRE 2026 Summit Brought global energy In the presence of Hon’ble leaders, partners and Prime Minister Shri customers together to Narendra Modi and accelerate the energy Hon’ble Prime Minister of transition. Japa
Slide 11: Order growth in transmission, industries and data centers fueled Q2FY27 performance
Order growth in transmission, industries and data centers fueled Q2FY27 performance # Key segments Growth Order Mix Transmission* Segment # Sector # Channel Q2FY26 Q2FY27 Q2FY26 Q2FY27 Q2FY26 Q2FY27 74% Industries 87% 96% 60% 62% Data center 34% 38% 34% Railway and 19% 28% metro 19% 16% 7% 7% 5% 6%
Slide 12: Export and Service orders are key levers of growth
Export and Service orders are key levers of growth Rs Crs Service ✓ Digitally enabled services and Service level agreement (SLA) ✓ Augmentation & extension service ✓ Orders across utilities, industry and EPCs including a major semiconductor customer Q2FY26 Q2FY27 H1FY26 H1FY27 Exports ✓ Received sev
Slide 13: Financial performance
Financial performance (Rs Crs) Q2FY27 Q2FY26 YoY% Q1FY27 QoQ% H1FY27 H1FY26 YoY% Orders (with HVDC) 4,120.8 2,217.1 85.9% 5,096.5 -19.1% 9,217.3 13,556.3 -32.0% Orders (without HVDC) 85.9% 21.8% 53.1% Revenue from operations 2,996.5 1,832.6 63.5% 2,493.7 20.2% 5,490.2 3,311.5 65.8% PBT 430.4 352.9 2
Slide 14: Financial statement analysis
Financial statement analysis Rs Crs Particulars 3 months ended 3 months ended 3 months ended 6 months ended 6 months ended Year ended 30.09.2026 30.06.2026 30.09.2025 30.09.2026 30.09.2025 31.03.2026 Crs % Crs % Crs % Crs % Crs % Crs % INCOME Revenue from operations 2,996.5 100.0% 2,493.7 100.0% 1,8
Slide 15: Priorities
Priorities Markets Business Function Strengthen the core – renewables, Strengthen BU service offerings Reinforce safety culture utilities, HVDC, industries and transport Operational excellence to Drive productivity and cost improve productivity, quality & AI discipline Harness new segments – data ad
Slide 16: Q&A
Q&A 15 Public © 2026 Hitachi Energy. All rights reserved.
Slide 17: For further information, please contact
For further information, please contact: Priyanka Bhagat Investor Relation [email protected] 16 Public © 2026 Hitachi Energy. All rights reserved.