  1. Slide 1: Camden Gas Project CCC Update

    Camden Gas Project CCC Update Community Consultative Committee July 2014

  2. Slide 2: Well Summary

    1 Well Summary Production Well Number Exploration Core Number Status (as of 29/07/14) Hole Status (as of 29/07/14) Drilled (total wells) 144 Drilled, Plugged and 6 Abandoned (Camden North) Wells under 0 Drilled, Plugged and 3 construction Abandoned (remainder PEL2) Producing and 96 dewatering wells

  3. Slide 3: Health, Safety and Environment

    2 Health, Safety and Environment › EPA 2013 Compliance Audit Report » Released 17 June 2014. » Corrective actions continue to be completed. » The latest update was uploaded to the project website on 30 July. › 2010-2012 Independent Environmental Audit » 3 remaining corrective actions to be completed

  4. Slide 4: Field operations

    3 Field operations › No CSG Drilling since September 2012. › No well workovers undertaken. › New access to RP09 well site constructed. › Familiarisation site visit by the Office of CSG to inspect production wells in Spring Farm and Menangle Park. › Camden Community Consultative Committee › July 2014

  5. Slide 5: Rosalind Park Gas Plant

    4 Rosalind Park Gas Plant › Compressor 1 Engine overhaul » Compressor engine removed off site on 25 July for engine overhaul » Expected to be reinstalled in November for commissioning in December › Noise monitoring » June 2014 quarterly monitoring results compliant › Air emissions monitoring » June

  6. Slide 6: Community

    Community 5 Open Day/ visits to Camden › Rotary Club of Camden › National Party › Community Open Day, July Community & business support › Cystic Fibrosis in Macarthur › St Vinnies, Nagle Care Centre › Champions of the West › Camden team volunteer day’s with Tahmoor Mens Shed › Camden Community Consu